1448 (OG) |
180590-Construction of Bachelor Hostel for C&W Staff at Tank |
Tank |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 66.604 | 20 | 10 | 10 | 10 | 10 | 30 | 36.604 | 45% |
45% December - 2020 |
MB- finishing stage.
Ist Floor finishing stage.
T/Well structure completed.
Overhead Tank in progress. |
No Image |
Tank | |||||||||||||||||||
1448 (OG) |
180590-Construction of Bachelor Hostel for C&W Staff at Tank |
Tank |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 66.604 | 20 | 10 | 10 | 10 | 10 | 30 | 36.604 | 45% |
45% December - 2020 |
MB- finishing stage.
Ist Floor finishing stage.
T/Well structure completed.
Overhead Tank in progress. |
No Image |
Tank | |||||||||||||||||||
1448 (OG) |
180590-Construction of Bachelor Hostel for C&W Staff at Tank |
Tank |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 66.604 | 20 | 10 | 10 | 5 | 0 | 20 | 36.604 | 45% |
30% October - 2020 |
MB- finishing stage.
Ist Floor finishing stage.
T/Well structure completed.
Overhead Tank in progress. |
No Image |
Tank | |||||||||||||||||||
1448 (OG) |
180590-Construction of Bachelor Hostel for C&W Staff at Tank |
Tank |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 66.604 | 20 | 10 | 10 | 0 | 0 | 20 | 36.604 | 45% |
30% September - 2020 |
MB- finishing stage.
Ist Floor finishing stage.
T/Well structure completed.
Overhead Tank in progress. |
No Image |
Tank | |||||||||||||||||||
1448 (OG) |
180590-Construction of Bachelor Hostel for C&W Staff at Tank |
Tank |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 66.604 | 20 | 10 | 10 | 3 | 0 | 20 | 36.604 | 45% |
30% August - 2020 |
MB- G.F upto Roof leve.
BW- 40 %
Overhead Tank in progress. |
No Image |
Tank | |||||||||||||||||||
1448 (OG) |
180590-Construction of Bachelor Hostel for C&W Staff at Tank |
Tank |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 66.604 | 20 | 10 | 0 | 0 | 0 | 20 | 36.604 | 45% |
30% July - 2020 |
MB- G.F upto Roof leve.
BW- 40 %
Overhead Tank |
No Image |
Tank | |||||||||||||||||||
1448 (OG) |
180590-Construction of Bachelor Hostel for C&W Staff at Tank |
Tank |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 66.604 | 0 | 10 | 10 | 10 | 10 | 0 | 0 |
May - 2021 |
MB- finishing stage.
Ist Floor finishing stage.
T/Well structure completed.
Overhead Tank in progress.
Demand Rs: 22 M (Liability) |
No Image | |
Tank | |||||||||||||||||||
1448 (OG) |
180590-Construction of Bachelor Hostel for C&W Staff at Tank |
Tank |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 66.604 | 0 | 10 | 10 | 10 | 10 | 0 | 0 |
April - 2021 |
MB- finishing stage.
Ist Floor finishing stage.
T/Well structure completed.
Overhead Tank in progress.
Demand Rs: 22 M (Liability) |
No Image | |
Tank | |||||||||||||||||||
1448 (OG) |
180590-Construction of Bachelor Hostel for C&W Staff at Tank |
Tank |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 66.604 | 0 | 10 | 10 | 10 | 10 | 0 | 0 |
March - 2021 |
MB- finishing stage.
Ist Floor finishing stage.
T/Well structure completed.
Overhead Tank in progress. |
No Image | |
Tank | |||||||||||||||||||
1448 (OG) |
180590-Construction of Bachelor Hostel for C&W Staff at Tank |
Tank |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 66.604 | 0 | 10 | 10 | 10 | 10 | 0 | 0 |
February - 2021 |
MB- finishing stage.
Ist Floor finishing stage.
T/Well structure completed.
Overhead Tank in progress. |
No Image | |
Tank | |||||||||||||||||||
1448 (OG) |
180590-Construction of Bachelor Hostel for C&W Staff at Tank |
Tank |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 66.604 | 0 | 10 | 10 | 10 | 10 | 0 | 0 |
January - 2021 |
MB- finishing stage.
Ist Floor finishing stage.
T/Well structure completed.
Overhead Tank in progress. |
No Image | |
Tank | |||||||||||||||||||