Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2021, February - 2021, March - 2021, April - 2021, May - 2021, July - 2020, August - 2020, September - 2020, October - 2020, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1448
(OG)
180590-Construction of Bachelor Hostel for C&W Staff at Tank
Tank
30-11--1 30-11--1 - 30-11--1 - 66.604 20 10 10 10 10 30 36.604 45% 45%
December - 2020
MB- finishing stage. Ist Floor finishing stage. T/Well structure completed. Overhead Tank in progress.
No Image
Tank
1448
(OG)
180590-Construction of Bachelor Hostel for C&W Staff at Tank
Tank
30-11--1 30-11--1 - 30-11--1 - 66.604 20 10 10 10 10 30 36.604 45% 45%
December - 2020
MB- finishing stage. Ist Floor finishing stage. T/Well structure completed. Overhead Tank in progress.
No Image
Tank
1448
(OG)
180590-Construction of Bachelor Hostel for C&W Staff at Tank
Tank
30-11--1 30-11--1 - 30-11--1 - 66.604 20 10 10 5 0 20 36.604 45% 30%
October - 2020
MB- finishing stage. Ist Floor finishing stage. T/Well structure completed. Overhead Tank in progress.
No Image
Tank
1448
(OG)
180590-Construction of Bachelor Hostel for C&W Staff at Tank
Tank
30-11--1 30-11--1 - 30-11--1 - 66.604 20 10 10 0 0 20 36.604 45% 30%
September - 2020
MB- finishing stage. Ist Floor finishing stage. T/Well structure completed. Overhead Tank in progress.
No Image
Tank
1448
(OG)
180590-Construction of Bachelor Hostel for C&W Staff at Tank
Tank
30-11--1 30-11--1 - 30-11--1 - 66.604 20 10 10 3 0 20 36.604 45% 30%
August - 2020
MB- G.F upto Roof leve. BW- 40 % Overhead Tank in progress.
No Image
Tank
1448
(OG)
180590-Construction of Bachelor Hostel for C&W Staff at Tank
Tank
30-11--1 30-11--1 - 30-11--1 - 66.604 20 10 0 0 0 20 36.604 45% 30%
July - 2020
MB- G.F upto Roof leve. BW- 40 % Overhead Tank
No Image
Tank
1448
(OG)
180590-Construction of Bachelor Hostel for C&W Staff at Tank
Tank
30-11--1 30-11--1 - 30-11--1 - 66.604 0 10 10 10 10 0 0
May - 2021
MB- finishing stage. Ist Floor finishing stage. T/Well structure completed. Overhead Tank in progress. Demand Rs: 22 M (Liability)
No Image
Tank
1448
(OG)
180590-Construction of Bachelor Hostel for C&W Staff at Tank
Tank
30-11--1 30-11--1 - 30-11--1 - 66.604 0 10 10 10 10 0 0
April - 2021
MB- finishing stage. Ist Floor finishing stage. T/Well structure completed. Overhead Tank in progress. Demand Rs: 22 M (Liability)
No Image
Tank
1448
(OG)
180590-Construction of Bachelor Hostel for C&W Staff at Tank
Tank
30-11--1 30-11--1 - 30-11--1 - 66.604 0 10 10 10 10 0 0
March - 2021
MB- finishing stage. Ist Floor finishing stage. T/Well structure completed. Overhead Tank in progress.
No Image
Tank
1448
(OG)
180590-Construction of Bachelor Hostel for C&W Staff at Tank
Tank
30-11--1 30-11--1 - 30-11--1 - 66.604 0 10 10 10 10 0 0
February - 2021
MB- finishing stage. Ist Floor finishing stage. T/Well structure completed. Overhead Tank in progress.
No Image
Tank
1448
(OG)
180590-Construction of Bachelor Hostel for C&W Staff at Tank
Tank
30-11--1 30-11--1 - 30-11--1 - 66.604 0 10 10 10 10 0 0
January - 2021
MB- finishing stage. Ist Floor finishing stage. T/Well structure completed. Overhead Tank in progress.
No Image
Tank
Pages : 1