Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1441 (OG) |
191177-170340-Maintenance / Repair and Rehabiliation of Damaged Building Infrastructure in FATA [MA] |
Bajaur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 37.323 | 32.596 | 5 | 5 | 5 | 0 | 32.596 | 0 | 100% |
87% December - 2020 |
05 - Units completed |
No Image |
1441 (OG) |
191177-170340-Maintenance / Repair and Rehabiliation of Damaged Building Infrastructure in FATA [MA] |
Bajaur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 37.323 | 32.596 | 5 | 5 | 5 | 0 | 32.596 | 0 | 100% |
87% December - 2020 |
05 - Units completed |
No Image |
1441 (OG) |
191177-170340-Maintenance / Repair and Rehabiliation of Damaged Building Infrastructure in FATA [MA] |
Bajaur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 37.323 | 32.596 | 0 | 0 | 0 | 0 | 32.596 | 4.727 | - |
87% October - 2020 |
05 - Units finishing in progres. |
No Image |
1441 (OG) |
191177-170340-Maintenance / Repair and Rehabiliation of Damaged Building Infrastructure in FATA [MA] |
Bajaur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 37.323 | 32.596 | 0 | 0 | 0 | 0 | 32.596 | 4.727 | - |
87% September - 2020 |
05 - Units finishing in progres. |
No Image |
1441 (OG) |
191177-170340-Maintenance / Repair and Rehabiliation of Damaged Building Infrastructure in FATA [MA] |
Bajaur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 37.323 | 32.596 | 0 | 0 | 0 | 0 | 32.596 | 4.727 | - |
87% May - 2021 |
05 - Units
All Completed & H/O |
No Image |
1 AHQ Khar office
2 AHQ Khar Jirga Hall
3 AHQ Khar Bachelor Hostel
4 Check Post
5 Civil Colony Nawagai
| |||||||||||||||||||
1441 (OG) |
191177-170340-Maintenance / Repair and Rehabiliation of Damaged Building Infrastructure in FATA [MA] |
Bajaur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 37.323 | 32.596 | 0 | 0 | 0 | 0 | 32.596 | 4.727 | - |
87% April - 2021 |
05 - Units completed & H/O |
No Image |
1 AHQ Khar office
2 AHQ Khar Jirga Hall
3 AHQ Khar Bachelor Hostel
4 Check Post
5 Civil Colony Nawagai
| |||||||||||||||||||
1441 (OG) |
191177-170340-Maintenance / Repair and Rehabiliation of Damaged Building Infrastructure in FATA [MA] |
Bajaur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 37.323 | 32.596 | 0 | 0 | 0 | 0 | 32.596 | 4.727 | - |
87% March - 2021 |
05 - Units completed & H/O |
No Image |
1 AHQ Khar office
2 AHQ Khar Jirga Hall
3 AHQ Khar Bachelor Hostel
4 Check Post
5 Civil Colony Nawagai
| |||||||||||||||||||
1441 (OG) |
191177-170340-Maintenance / Repair and Rehabiliation of Damaged Building Infrastructure in FATA [MA] |
Bajaur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 37.323 | 32.596 | 5 | 5 | 5 | 0 | 32.596 | 0 | 100% |
87% February - 2021 |
05 - Units completed & H/O |
No Image |
1 AHQ Khar office
2 AHQ Khar Jirga Hall
3 AHQ Khar Bachelor Hostel
4 Check Post
5 Civil Colony Nawagai
| |||||||||||||||||||
1441 (OG) |
191177-170340-Maintenance / Repair and Rehabiliation of Damaged Building Infrastructure in FATA [MA] |
Bajaur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 37.323 | 32.596 | 5 | 5 | 5 | 0 | 32.596 | 0 | 100% |
87% January - 2021 |
05 - Units completed |
No Image |
1 AHQ Khar office
2 AHQ Khar Jirga Hall
3 AHQ Khar Bachelor Hostel
4 Check Post
5 Civil Colony Nawagai
| |||||||||||||||||||
1441 (OG) |
191177-170340-Maintenance / Repair and Rehabiliation of Damaged Building Infrastructure in FATA [MA] |
FR Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 12.602 | 7.541 | 0 | 0 | 0 | 0 | 7.541 | 5.061 | - |
60% December - 2020 |
Completed.
Rs: 3.9 M Contractor Liability |
No Image |
1441 (OG) |
191177-170340-Maintenance / Repair and Rehabiliation of Damaged Building Infrastructure in FATA [MA] |
FR Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 12.602 | 7.541 | 0 | 0 | 0 | 0 | 7.541 | 5.061 | - |
60% December - 2020 |
Completed.
Rs: 3.9 M Contractor Liability |
No Image |
1441 (OG) |
191177-170340-Maintenance / Repair and Rehabiliation of Damaged Building Infrastructure in FATA [MA] |
FR Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 12.602 | 3.759 | 0 | 0 | 0 | 0 | 3.759 | 8.843 | - |
30% October - 2020 |
Completed. |
No Image |
1441 (OG) |
191177-170340-Maintenance / Repair and Rehabiliation of Damaged Building Infrastructure in FATA [MA] |
FR Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 3.759 | 3.759 | 0 | 0 | 0 | 0 | 3.759 | 0 | - |
100% September - 2020 |
Completed |
No Image |
1441 (OG) |
191177-170340-Maintenance / Repair and Rehabiliation of Damaged Building Infrastructure in FATA [MA] |
FR Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 3.759 | 3.759 | 0 | 0 | 0 | 0 | 3.759 | 0 | - |
100% August - 2020 |
Completed |
No Image |
1441 (OG) |
191177-170340-Maintenance / Repair and Rehabiliation of Damaged Building Infrastructure in FATA [MA] |
FR Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 197.06 | 112.032 | 24.613 | 0 | 0 | 0 | 112.032 | 0 |
July - 2020 |
No Image | ||
1441 (OG) |
191177-170340-Maintenance / Repair and Rehabiliation of Damaged Building Infrastructure in FATA [MA] |
FR Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 12.602 | 7.541 | 0 | 0 | 0 | 0 | 7.541 | 5.061 | - |
60% May - 2021 |
Completed.
Rs: 3.9 M Contractor Liability |
No Image |
Repair of DC office | |||||||||||||||||||
1441 (OG) |
191177-170340-Maintenance / Repair and Rehabiliation of Damaged Building Infrastructure in FATA [MA] |
FR Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 12.602 | 7.541 | 0 | 0 | 0 | 0 | 7.541 | 5.061 | - |
60% April - 2021 |
Completed.
Rs: 3.9 M Contractor Liability |
No Image |
Repair of DC office | |||||||||||||||||||
1441 (OG) |
191177-170340-Maintenance / Repair and Rehabiliation of Damaged Building Infrastructure in FATA [MA] |
FR Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 12.602 | 7.541 | 0 | 0 | 0 | 0 | 7.541 | 5.061 | - |
60% March - 2021 |
Completed.
Rs: 3.9 M Contractor Liability |
No Image |
Repair of DC office | |||||||||||||||||||
1441 (OG) |
191177-170340-Maintenance / Repair and Rehabiliation of Damaged Building Infrastructure in FATA [MA] |
FR Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 12.602 | 7.541 | 0 | 0 | 0 | 0 | 7.541 | 5.061 | - |
60% February - 2021 |
Completed.
Rs: 3.9 M Contractor Liability |
No Image |
Repair of DC office | |||||||||||||||||||
1441 (OG) |
191177-170340-Maintenance / Repair and Rehabiliation of Damaged Building Infrastructure in FATA [MA] |
FR Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 12.602 | 7.541 | 0 | 0 | 0 | 0 | 7.541 | 5.061 | - |
60% January - 2021 |
Completed.
Rs: 3.9 M Contractor Liability |
No Image |
Repair of DC office | |||||||||||||||||||
1441 (OG) |
191177-170340-Maintenance / Repair and Rehabiliation of Damaged Building Infrastructure in FATA [MA] |
FR Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 5.541 | 0 | 0 | 0 | 0 | 0 | 0 | 5.541 | - |
- December - 2020 |
Work in Progress. |
No Image |
1441 (OG) |
191177-170340-Maintenance / Repair and Rehabiliation of Damaged Building Infrastructure in FATA [MA] |
FR Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 5.541 | 0 | 0 | 0 | 0 | 0 | 0 | 5.541 | - |
- December - 2020 |
Work in Progress. |
No Image |
1441 (OG) |
191177-170340-Maintenance / Repair and Rehabiliation of Damaged Building Infrastructure in FATA [MA] |
FR Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 5.541 | 0 | 0 | 0 | 0 | 0 | 0 | 5.541 | - |
- October - 2020 |
Work in Progress. |
No Image |
1441 (OG) |
191177-170340-Maintenance / Repair and Rehabiliation of Damaged Building Infrastructure in FATA [MA] |
FR Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 5.541 | 0 | 0 | 0 | 0 | 0 | 0 | 5.541 | - |
- September - 2020 |
Work in Progress. |
No Image |
1441 (OG) |
191177-170340-Maintenance / Repair and Rehabiliation of Damaged Building Infrastructure in FATA [MA] |
FR Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 5.541 | 0 | 0 | 0 | 0 | 0 | 0 | 5.541 | - |
- August - 2020 |
Work in Progress. |
No Image |
1441 (OG) |
191177-170340-Maintenance / Repair and Rehabiliation of Damaged Building Infrastructure in FATA [MA] |
FR Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 5.541 | 112.032 | 24.613 | 0 | 0 | 0 | 112.032 | 0 | 100% |
100% July - 2020 |
No Image | |
1441 (OG) |
191177-170340-Maintenance / Repair and Rehabiliation of Damaged Building Infrastructure in FATA [MA] |
FR Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 5.541 | 0 | 0 | 0 | 0 | 0 | 0 | 5.541 | - |
- May - 2021 |
Work order not issued Scope of work awaited |
No Image |
1441 (OG) |
191177-170340-Maintenance / Repair and Rehabiliation of Damaged Building Infrastructure in FATA [MA] |
FR Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 5.541 | 0 | 0 | 0 | 0 | 0 | 0 | 5.541 | - |
- April - 2021 |
Work order not issued Scope of work awaited |
No Image |
1441 (OG) |
191177-170340-Maintenance / Repair and Rehabiliation of Damaged Building Infrastructure in FATA [MA] |
FR Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 5.541 | 0 | 0 | 0 | 0 | 0 | 0 | 5.541 | - |
- March - 2021 |
Work order not issued Scope of work awaited |
No Image |
1441 (OG) |
191177-170340-Maintenance / Repair and Rehabiliation of Damaged Building Infrastructure in FATA [MA] |
FR Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 5.541 | 0 | 0 | 0 | 0 | 0 | 0 | 5.541 | - |
- February - 2021 |
Work order not issued Scope of work awaited |
No Image |
1441 (OG) |
191177-170340-Maintenance / Repair and Rehabiliation of Damaged Building Infrastructure in FATA [MA] |
FR Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 5.541 | 0 | 0 | 0 | 0 | 0 | 0 | 5.541 | - |
- January - 2021 |
Work order not issued |
No Image |
1441 (OG) |
191177-170340-Maintenance / Repair and Rehabiliation of Damaged Building Infrastructure in FATA [MA] |
FR Lakki |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 8.843 | 8.843 | 0 | 0 | 0 | 0 | 8.843 | 0 | - |
100% December - 2020 |
03- Units work in progress. |
No Image |
1441 (OG) |
191177-170340-Maintenance / Repair and Rehabiliation of Damaged Building Infrastructure in FATA [MA] |
FR Lakki |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 8.843 | 8.843 | 0 | 0 | 0 | 0 | 8.843 | 0 | - |
100% December - 2020 |
03- Units work in progress. |
No Image |
1441 (OG) |
191177-170340-Maintenance / Repair and Rehabiliation of Damaged Building Infrastructure in FATA [MA] |
FR Lakki |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 8.843 | 8.843 | 0 | 0 | 0 | 0 | 8.843 | 0 | - |
100% October - 2020 |
03- Units work in progress. |
No Image |
1441 (OG) |
191177-170340-Maintenance / Repair and Rehabiliation of Damaged Building Infrastructure in FATA [MA] |
FR Lakki |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 8.843 | 8.843 | 0 | 0 | 0 | 0 | 8.843 | 0 | - |
100% September - 2020 |
03- Units work in progress. |
No Image |
1441 (OG) |
191177-170340-Maintenance / Repair and Rehabiliation of Damaged Building Infrastructure in FATA [MA] |
FR Lakki |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 8.843 | 8.843 | 0 | 0 | 0 | 0 | 8.843 | 0 | - |
100% August - 2020 |
03- Units work in progress. |
No Image |
1441 (OG) |
191177-170340-Maintenance / Repair and Rehabiliation of Damaged Building Infrastructure in FATA [MA] |
FR Lakki |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 197.06 | 112.032 | 24.613 | 0 | 0 | 0 | 112.032 | 0 |
July - 2020 |
No Image | ||
1441 (OG) |
191177-170340-Maintenance / Repair and Rehabiliation of Damaged Building Infrastructure in FATA [MA] |
FR Lakki |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 8.843 | 7.541 | 0 | 0 | 0 | 0 | 7.541 | 1.302 | - |
85% April - 2021 |
04- Units
1 Completed
2
a Flooring in progress
b Electrificaiton in progress
c Completed |
No Image |
1 Repari of DC Office (Bannu)
2
a. Badraga Room in Sub Division Lakki
b Re-Const: OF Tehsil Building at Tajori
c Repair of Shadi Khel Rest House
| |||||||||||||||||||
1441 (OG) |
191177-170340-Maintenance / Repair and Rehabiliation of Damaged Building Infrastructure in FATA [MA] |
FR Lakki |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 8.843 | 7.541 | 0 | 0 | 0 | 0 | 7.541 | 1.302 | - |
85% March - 2021 |
04- Units
1 Completed
2
a Flooring in progress
b Electrificaiton in progress
c Completed |
No Image |
1 Repari of DC Office (Bannu)
2
a. Badraga Room in Sub Division Lakki
b Re-Const: OF Tehsil Building at Tajori
c Repair of Shadi Khel Rest House
| |||||||||||||||||||
1441 (OG) |
191177-170340-Maintenance / Repair and Rehabiliation of Damaged Building Infrastructure in FATA [MA] |
FR Lakki |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 8.843 | 7.541 | 0 | 0 | 0 | 0 | 7.541 | 1.302 | - |
85% February - 2021 |
04- Units
1 Completed
2
a Flooring in progress
b Electrificaiton in progress
c Completed |
No Image |
1 Repari of DC Office (Bannu)
2
a. Badraga Room in Sub Division Lakki
b Re-Const: OF Tehsil Building at Tajori
c Repair of Shadi Khel Rest House
| |||||||||||||||||||
1441 (OG) |
191177-170340-Maintenance / Repair and Rehabiliation of Damaged Building Infrastructure in FATA [MA] |
FR Lakki |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 8.843 | 3.782 | 0 | 0 | 0 | 0 | 3.782 | 5.061 | - |
43% January - 2021 |
03- Units work in progress. |
No Image |
1 Badraga Room in Sub Division Lakki
2 Re-Const: OF Tehsil Building at Tajori
3 Repair of Shadi Khel Rest House
| |||||||||||||||||||
1441 (OG) |
191177-170340-Maintenance / Repair and Rehabiliation of Damaged Building Infrastructure in FATA [MA] |
FR Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1.411 | 0 | 0 | 0 | 0 | 0 | 0 | 1.411 | - |
- December - 2020 |
DPC in Progress. |
No Image |
1441 (OG) |
191177-170340-Maintenance / Repair and Rehabiliation of Damaged Building Infrastructure in FATA [MA] |
FR Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1.411 | 0 | 0 | 0 | 0 | 0 | 0 | 1.411 | - |
- December - 2020 |
DPC in Progress. |
No Image |
1441 (OG) |
191177-170340-Maintenance / Repair and Rehabiliation of Damaged Building Infrastructure in FATA [MA] |
FR Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1.411 | 0 | 0 | 0 | 0 | 0 | 0 | 1.411 | - |
- October - 2020 |
DPC in Progress. |
No Image |
1441 (OG) |
191177-170340-Maintenance / Repair and Rehabiliation of Damaged Building Infrastructure in FATA [MA] |
FR Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1.411 | 0 | 0 | 0 | 0 | 0 | 0 | 1.411 | - |
- September - 2020 |
Work in Progress. |
No Image |
1441 (OG) |
191177-170340-Maintenance / Repair and Rehabiliation of Damaged Building Infrastructure in FATA [MA] |
FR Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1.411 | 0 | 0 | 0 | 0 | 0 | 0 | 1.411 | - |
- August - 2020 |
Work in Progress. |
No Image |
1441 (OG) |
191177-170340-Maintenance / Repair and Rehabiliation of Damaged Building Infrastructure in FATA [MA] |
FR Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 5.851 | 112.032 | 24.613 | 0 | 0 | 0 | 112.032 | 0 | 100% |
100% July - 2020 |
No Image | |
1441 (OG) |
191177-170340-Maintenance / Repair and Rehabiliation of Damaged Building Infrastructure in FATA [MA] |
FR Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1.411 | 0 | 0 | 0 | 0 | 0 | 0 | 1.411 | - |
- May - 2021 |
work order not issued |
No Image |
1441 (OG) |
191177-170340-Maintenance / Repair and Rehabiliation of Damaged Building Infrastructure in FATA [MA] |
FR Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1.411 | 0 | 0 | 0 | 0 | 0 | 0 | 1.411 | - |
- April - 2021 |
work order not issued |
No Image |
1441 (OG) |
191177-170340-Maintenance / Repair and Rehabiliation of Damaged Building Infrastructure in FATA [MA] |
FR Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1.411 | 0 | 0 | 0 | 0 | 0 | 0 | 1.411 | - |
- March - 2021 |
work order not issued |
No Image |
Pages : 1 2 3 |