Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2021, February - 2021, March - 2021, April - 2021, May - 2021, July - 2020, August - 2020, September - 2020, October - 2020, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1415
(OG)
150135-Establishment of Khyber Pakhtunkhwa Emergency Rescue Service (Rescue 1122) in District Swabi
Swabi
30-11--1 30-11--1 - 30-11--1 - 152.26 73.716 57 57 78.544 27.333 101.049 21.544 86% 66%
December - 2020
3- Units 1- 1.2nd Flooring Roofing in progress. 2- finishing in progress. Ist/Floor Roofing in progress, Water tank completed 3- finishing in progress.
No Image
1) Tehsil Swabi PK-44
2) Tehsil Topi PK-43
3) Tehsil Razzar PK-47
1415
(OG)
150135-Establishment of Khyber Pakhtunkhwa Emergency Rescue Service (Rescue 1122) in District Swabi
Swabi
30-11--1 30-11--1 - 30-11--1 - 152.26 73.716 57 57 78.544 27.333 101.049 21.544 86% 66%
December - 2020
3- Units 1- 1.2nd Flooring Roofing in progress. 2- finishing in progress. Ist/Floor Roofing in progress, Water tank completed 3- finishing in progress.
No Image
1) Tehsil Swabi PK-44
2) Tehsil Topi PK-43
3) Tehsil Razzar PK-47
1415
(OG)
150135-Establishment of Khyber Pakhtunkhwa Emergency Rescue Service (Rescue 1122) in District Swabi
Swabi
30-11--1 30-11--1 - 30-11--1 - 152.26 73.716 57 57 78.544 23.349 97.065 21.544 86% 64%
October - 2020
3- Units 1- 1.2nd Flooring Roofing in progress. 2- finishing in progress. Ist/Floor Roofing in progress, Water tank completed
No Image
1) Tehsil Swabi PK-44
2) Tehsil Topi PK-43
3) Tehsil Razzar PK-47
1415
(OG)
150135-Establishment of Khyber Pakhtunkhwa Emergency Rescue Service (Rescue 1122) in District Swabi
Swabi
30-11--1 30-11--1 - 30-11--1 - 152.26 73.716 57 57 0 0 73.716 21.544 86% 48%
September - 2020
3- Units 1- 1.2nd Flooring Roofing in progress. 2- finishing in progress. Ist/Floor Roofing in progress, Water tank completed
No Image
1) Tehsil Swabi PK-44
2) Tehsil Topi PK-43
3) Tehsil Razzar PK-47
1415
(OG)
150135-Establishment of Khyber Pakhtunkhwa Emergency Rescue Service (Rescue 1122) in District Swabi
Swabi
30-11--1 30-11--1 - 30-11--1 - 152.26 73.716 57 57 0 0 73.716 21.544 86% 48%
August - 2020
3- Units 1- 1.2nd Flooring Roofing in progress. 2- finishing in progress. Ist/Floor Roofing in progress, Water tank completed
No Image
1) Tehsil Swabi PK-44
2) Tehsil Topi PK-43
3) Tehsil Razzar PK-47
1415
(OG)
150135-Establishment of Khyber Pakhtunkhwa Emergency Rescue Service (Rescue 1122) in District Swabi
Swabi
30-11--1 30-11--1 - 30-11--1 - 152.26 157.874 57 0 0 0 157.874 0 100% 100%
July - 2020
3- Units 1- Site not provided. 2- Ist roof laid
No Image
1) Tehsil Swabi PK-44
2) Tehsil
1415
(OG)
150135-Establishment of Khyber Pakhtunkhwa Emergency Rescue Service (Rescue 1122) in District Swabi
Swabi
30-11--1 30-11--1 - 30-11--1 - 152.26 73.716 57 78.544 78.544 29.436 103.152 21.544 86% 68%
May - 2021
03- Units 1. plastering in progress. 2 Finishing in progress 3. Finishing in progress
No Image
1) Tehsil Swabi PK-44 .?.?. Rs: 58.00
2) Tehsil Topi PK-43 .?.?. Rs: 58.00 (TS 42.419)
3) Tehsil Razzar PK-47.?.?. Rs: 45.049
1415
(OG)
150135-Establishment of Khyber Pakhtunkhwa Emergency Rescue Service (Rescue 1122) in District Swabi
Swabi
30-11--1 30-11--1 - 30-11--1 - 152.26 73.716 57 78.544 78.544 29.436 103.152 21.544 86% 68%
April - 2021
3- Units 1. plastering in progress. 2 Finishing in progress 3. Finishing in progress
No Image
1) Tehsil Swabi PK-44 .?.?. Rs: 58.00
2) Tehsil Topi PK-43 .?.?. Rs: 58.00 (TS 42.419)
3) Tehsil Razzar PK-47.?.?. Rs: 45.049
1415
(OG)
150135-Establishment of Khyber Pakhtunkhwa Emergency Rescue Service (Rescue 1122) in District Swabi
Swabi
30-11--1 30-11--1 - 30-11--1 - 152.26 73.716 57 78.544 78.544 29.436 103.152 21.544 86% 68%
March - 2021
3- Units 1. plastering in progress. 2 Finishing in progress 3. Finishing in progress
No Image
1) Tehsil Swabi PK-44 .?.?. Rs: 58.00
2) Tehsil Topi PK-43 .?.?. Rs: 58.00 (TS 42.419)
3) Tehsil Razzar PK-47.?.?. Rs: 45.049
1415
(OG)
150135-Establishment of Khyber Pakhtunkhwa Emergency Rescue Service (Rescue 1122) in District Swabi
Swabi
30-11--1 30-11--1 - 30-11--1 - 152.26 73.716 57 78.544 78.544 27.333 101.049 21.544 86% 66%
February - 2021
3- Units 1. plastering in progress. 2 Finishing in progress 3. Finishing in progress
No Image
1) Tehsil Swabi PK-44 .?.?. Rs: 58.00
2) Tehsil Topi PK-43 .?.?. Rs: 58.00 (TS 42.419)
3) Tehsil Razzar PK-47.?.?. Rs: 45.049
1415
(OG)
150135-Establishment of Khyber Pakhtunkhwa Emergency Rescue Service (Rescue 1122) in District Swabi
Swabi
30-11--1 30-11--1 - 30-11--1 - 152.26 73.716 57 78.544 78.544 27.333 101.049 21.544 86% 66%
January - 2021
3- Units 1- 1.2nd Flooring Roofing in progress. 2- finishing in progress. Ist/Floor Roofing in progress, Water tank completed 3- finishing in progress.
No Image
1) Tehsil Swabi PK-44
2) Tehsil Topi PK-43
3) Tehsil Razzar PK-47
Pages : 1