Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1411 (OG) |
170288-Establishment of Emergency Rescue Service (Rescue-1122) in District Karak. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 69 | 96.22401 | 60 | 60 | 41.2 | 3.706 | 99.93001 | 0 | 100% |
100% December - 2020 |
2- componens.
MB- G/F finishing in progress. F/F roof laid.
2nd Floor Shuttering in progress.
B/Wall completed.
Unit- BD Shah.
Layout given
levelling /Dressing of site is under progress. |
No Image |
1) Emergency Rescue Service (Rescue 1122) Karak
2) Emergency Rescue Service (Rescue 1122) Banda Daud Shah | |||||||||||||||||||
1411 (OG) |
170288-Establishment of Emergency Rescue Service (Rescue-1122) in District Karak. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 69 | 96.22401 | 60 | 60 | 41.2 | 3.706 | 99.93001 | 0 | 100% |
100% December - 2020 |
2- componens.
MB- G/F finishing in progress. F/F roof laid.
2nd Floor Shuttering in progress.
B/Wall completed.
Unit- BD Shah.
Layout given
levelling /Dressing of site is under progress. |
No Image |
1) Emergency Rescue Service (Rescue 1122) Karak
2) Emergency Rescue Service (Rescue 1122) Banda Daud Shah | |||||||||||||||||||
1411 (OG) |
170288-Establishment of Emergency Rescue Service (Rescue-1122) in District Karak. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 69 | 96.22401 | 60 | 60 | 41.2 | 3.706 | 99.93001 | 0 | 100% |
100% October - 2020 |
2- componens.
MB- G/F finishing in progress. F/F roof laid.
2nd Floor Shuttering in progress.
B/Wall completed.
Unit- BD Shah.
Layout given
levelling /Dressing of site is under progress. |
No Image |
1) Emergency Rescue Service (Rescue 1122) Karak
2) Emergency Rescue Service (Rescue 1122) Banda Daud Shah | |||||||||||||||||||
1411 (OG) |
170288-Establishment of Emergency Rescue Service (Rescue-1122) in District Karak. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 69 | 96.22401 | 60 | 60 | 41.2 | 3.706 | 99.93001 | 0 | 100% |
100% September - 2020 |
2- componens.
MB- G/F finishing in progress. F/F roof laid.
2nd Floor Shuttering in progress.
B/Wall completed.
Unit- BD Shah.
Layout given
levelling /Dressing of site is under progress. |
No Image |
1) Emergency Rescue Service (Rescue 1122) Karak
2) Emergency Rescue Service (Rescue 1122) Banda Daud Shah | |||||||||||||||||||
1411 (OG) |
170288-Establishment of Emergency Rescue Service (Rescue-1122) in District Karak. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 69 | 96.22401 | 60 | 60 | 0 | 0 | 96.22401 | 0 | 100% |
100% August - 2020 |
2- componens.
MB- G/F finishing in progress. F/F roof laid.
2nd Floor Shuttering in progress.
B/Wall completed.
Unit- BD Shah.
Layout given
levelling /Dressing of site is under progress. |
No Image |
1) Emergency Rescue Service (Rescue 1122) Karak
2) Emergency Rescue Service (Rescue 1122) Banda Daud Shah | |||||||||||||||||||
1411 (OG) |
170288-Establishment of Emergency Rescue Service (Rescue-1122) in District Karak. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 69 | 96.22401 | 60 | 0 | 0 | 0 | 96.22401 | 0 | 100% |
100% July - 2020 |
Deposit Work - Workin progress
edxpenditure - 16 |
No Image |
1) Emergency Rescue Service (Rescue 1122) Kar | |||||||||||||||||||
1411 (OG) |
170288-Establishment of Emergency Rescue Service (Rescue-1122) in District Karak. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 69 | 16.382 | 60 | 61.2 | 61.2 | 22.348 | 38.73 | 0 | 100% |
56% May - 2021 |
02 Units
1 Finishing in progress
2 Foundation in progress |
No Image |
1) Emergency Rescue Service (Rescue 1122) Karak
2) Emergency Rescue Service (Rescue 1122) Banda Daud Shah | |||||||||||||||||||
1411 (OG) |
170288-Establishment of Emergency Rescue Service (Rescue-1122) in District Karak. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 69 | 16.382 | 60 | 61.2 | 61.2 | 22.348 | 38.73 | 0 | 100% |
56% April - 2021 |
02 Units
1 Finishing in progress
2 Foundation in progress |
No Image |
1) Emergency Rescue Service (Rescue 1122) Karak
2) Emergency Rescue Service (Rescue 1122) Banda Daud Shah | |||||||||||||||||||
1411 (OG) |
170288-Establishment of Emergency Rescue Service (Rescue-1122) in District Karak. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 69 | 16.382 | 60 | 56.2 | 56.2 | 7.692 | 24.074 | 0 | 100% |
35% March - 2021 |
02 Units
1 Finishing in progress
2 Foundation in progress |
No Image |
1) Emergency Rescue Service (Rescue 1122) Karak
2) Emergency Rescue Service (Rescue 1122) Banda Daud Shah | |||||||||||||||||||
1411 (OG) |
170288-Establishment of Emergency Rescue Service (Rescue-1122) in District Karak. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 69 | 16.382 | 60 | 56.2 | 56.2 | 7.692 | 24.074 | 0 | 100% |
35% February - 2021 |
02 Units
1 Finishing in progress
2 Foundation in progress |
No Image |
1) Emergency Rescue Service (Rescue 1122) Karak
2) Emergency Rescue Service (Rescue 1122) Banda Daud Shah | |||||||||||||||||||
1411 (OG) |
170288-Establishment of Emergency Rescue Service (Rescue-1122) in District Karak. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 69 | 96.22401 | 60 | 56.2 | 56.2 | 7.692 | 103.91601 | 0 | 100% |
100% January - 2021 |
2- componens.
MB- G/F finishing in progress. F/F roof laid.
2nd Floor Shuttering in progress.
B/Wall completed.
Unit- BD Shah.
Layout given
levelling /Dressing of site is under progress. |
No Image |
1) Emergency Rescue Service (Rescue 1122) Karak
2) Emergency Rescue Service (Rescue 1122) Banda Daud Shah | |||||||||||||||||||
Pages : 1 |