Progressive Review for the month(s) of : January - 2021, January - 2018, February - 2021, February - 2018, March - 2021, March - 2018, April - 2021, April - 2018, May - 2021, May - 2018, June - 2018, July - 2017, July - 2020, August - 2017, August - 2020, September - 2017, September - 2020, October - 2017, October - 2020, November - 2017, December - 2020, December - 2017,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1367
(OG)
120209-Reconstruction of old pavilion at Qayyum Stadium, Peshawar (Phase-II).
Peshawar
PBC-2
03-06-14 30-06-18 - 27-12-12 - 164.306 110.465 44.941 44.941 33.705 33.705 144.17 8.9 95% 88%
December - 2017
Spectators steps concreting 1/2 portion completed. Main building GF, FF, flooring, brick work in progress. Inaugurated.
No Image
1367
(OG)
120209-Reconstruction of old pavilion at Qayyum Stadium, Peshawar (Phase-II).
Peshawar
PBC-2
30-11--1 30-11--1 - 30-11--1 - 164.306 110.465 44.941 44.941 22.47 22.47 132.935 8.9 95% 81%
November - 2017
Spectators steps concreting 1/2 portion completed. Main building GF, FF, flooring, brick work in progress.
No Image
1367
(OG)
120209-Reconstruction of old pavilion at Qayyum Stadium, Peshawar (Phase-II).
Peshawar
PBC-2
30-11--1 30-11--1 - 30-11--1 - 164.306 110.465 44.941 44.941 22.47 18.178 128.643 8.9 95% 78%
October - 2017
Spectators steps concreting 1/2 portion completed. Main building GF, FF, flooring, brick work in progress.
No Image
1367
(OG)
120209-Reconstruction of old pavilion at Qayyum Stadium, Peshawar (Phase-II).
Peshawar
PBC-2
03-06-14 30-06-18 - 27-12-12 - 164.306 110.465 44.941 44.941 22.47 18.178 128.643 8.9 95% 78%
September - 2017
Spectators steps concreting 1/2 portion completed. Main building GF, FF, flooring, brick work in progress.
No Image
1367
(OG)
120209-Reconstruction of old pavilion at Qayyum Stadium, Peshawar (Phase-II).
Peshawar
PBC-2
03-06-14 30-06-18 - 27-12-12 - 164.306 110.465 44.941 44.941 22.47 18.178 128.643 8.9 95% 78%
August - 2017
Spectators steps concreting 1/2 portion completed. Main building GF, FF, flooring, brick work in progress.
No Image
1367
(OG)
120209-Reconstruction of old pavilion at Qayyum Stadium, Peshawar (Phase-II).
Peshawar
PBC-2
03-06-14 30-06-18 - 27-12-12 - 164.306 110.465 44.941 44.941 0 0 110.465 8.9 95% 67%
July - 2017
Spectators steps concreting 1/2 portion completed. Main building GF, FF, flooring, brick work in progress.
No Image
1367
(OG)
120209-Reconstruction of old pavilion at Qayyum Stadium, Peshawar (Phase-II).
Peshawar
PBC-2
30-11--1 30-11--1 - 30-11--1 - 164.306 110.465 44.941 44.941 44.941 44.941 155.406 8.9 95% 95%
June - 2018
Spectators steps concreting 1/2 portion completed. Main building GF, FF, flooring, brick work in progress. Inaugurated.
No Image
Qayyum Stadiun, Peshawar
1367
(OG)
120209-Reconstruction of old pavilion at Qayyum Stadium, Peshawar (Phase-II).
Peshawar
PBC-2
30-11--1 30-11--1 - 30-11--1 - 164.306 110.465 44.941 44.941 44.941 44.941 155.406 8.9 95% 95%
May - 2018
Spectators steps concreting 1/2 portion completed. Main building GF, FF, flooring, brick work in progress. Inaugurated. Demand Rs.44.830 m for completion.
No Image
Qayyum Stadiun, Peshawar
1367
(OG)
120209-Reconstruction of old pavilion at Qayyum Stadium, Peshawar (Phase-II).
Peshawar
PBC-2
30-11--1 30-11--1 - 30-11--1 - 164.306 110.465 44.941 44.941 44.941 42.011 152.476 8.9 95% 93%
April - 2018
Spectators steps concreting 1/2 portion completed. Main building GF, FF, flooring, brick work in progress. Inaugurated. Demand Rs.44.830 m for completion.
No Image
Qayyum Stadiun, Peshawar
1367
(OG)
120209-Reconstruction of old pavilion at Qayyum Stadium, Peshawar (Phase-II).
Peshawar
PBC-2
30-11--1 30-11--1 - 30-11--1 - 164.306 110.465 44.941 44.941 44.941 42.011 152.476 8.9 95% 93%
March - 2018
Spectators steps concreting 1/2 portion completed. Main building GF, FF, flooring, brick work in progress. Inaugurated. Demand Rs.44.830 m for completion.
No Image
Qayyum Stadiun, Peshawar
1367
(OG)
120209-Reconstruction of old pavilion at Qayyum Stadium, Peshawar (Phase-II).
Peshawar
PBC-2
30-11--1 30-11--1 - 30-11--1 - 164.306 110.465 44.941 44.941 33.705 33.705 144.17 8.9 95% 88%
February - 2018
Spectators steps concreting 1/2 portion completed. Main building GF, FF, flooring, brick work in progress. Inaugurated. Demand Rs.44.830 m for completion.
No Image
Qayyum Stadiun, Peshawar
1367
(OG)
120209-Reconstruction of old pavilion at Qayyum Stadium, Peshawar (Phase-II).
Peshawar
PBC-2
30-11--1 30-11--1 - 30-11--1 - 164.306 110.465 44.941 44.941 33.705 33.705 144.17 8.9 95% 88%
January - 2018
Spectators steps concreting 1/2 portion completed. Main building GF, FF, flooring, brick work in progress. Inaugurated.
No Image
1367
(OG)
191682-130451-Mohmand Area Development Project, Phase-IV, FATA. (INL Assisted). PSDP=281.791M [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 114.769 37.5 0 0 0 0 37.5 0 - -
December - 2020
No Image
1367
(OG)
191682-130451-Mohmand Area Development Project, Phase-IV, FATA. (INL Assisted). PSDP=281.791M [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 114.769 37.5 0 0 0 0 37.5 0 - -
December - 2020
No Image
1367
(OG)
191682-130451-Mohmand Area Development Project, Phase-IV, FATA. (INL Assisted). PSDP=281.791M [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 114.769 37.5 0 0 0 0 37.5 0 - -
October - 2020
No Image
1367
(OG)
191682-130451-Mohmand Area Development Project, Phase-IV, FATA. (INL Assisted). PSDP=281.791M [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 114.769 37.5 0 0 0 0 37.5 0 - -
September - 2020
No Image
1367
(OG)
191682-130451-Mohmand Area Development Project, Phase-IV, FATA. (INL Assisted). PSDP=281.791M [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 114.769 37.5 0 0 0 0 37.5 0 - -
August - 2020
No Image
1367
(OG)
191682-130451-Mohmand Area Development Project, Phase-IV, FATA. (INL Assisted). PSDP=281.791M [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 114.769 37.5 0 0 0 0 37.5 0 -
July - 2020
No Image
1367
(OG)
191682-130451-Mohmand Area Development Project, Phase-IV, FATA. (INL Assisted). PSDP=281.791M [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 114.769 37.5 0 0 0 0 37.5 0 - -
May - 2021
No Image
1367
(OG)
191682-130451-Mohmand Area Development Project, Phase-IV, FATA. (INL Assisted). PSDP=281.791M [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 114.769 37.5 0 0 0 0 37.5 0 - -
April - 2021
No Image
1367
(OG)
191682-130451-Mohmand Area Development Project, Phase-IV, FATA. (INL Assisted). PSDP=281.791M [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 114.769 37.5 0 0 0 0 37.5 0 - -
March - 2021
No Image
1367
(OG)
191682-130451-Mohmand Area Development Project, Phase-IV, FATA. (INL Assisted). PSDP=281.791M [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 114.769 37.5 0 0 0 0 37.5 0 - -
February - 2021
No Image
1367
(OG)
191682-130451-Mohmand Area Development Project, Phase-IV, FATA. (INL Assisted). PSDP=281.791M [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 114.769 37.5 0 0 0 0 37.5 0 - -
January - 2021
No Image