Progressive Review for the month(s) of : January - 2021, February - 2021, March - 2021, April - 2021, May - 2021, July - 2020, August - 2020, September - 2020, October - 2020, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1360
(OG)
191669-170376-FATA Infrastructure Development Programe. Phase- II [MA]
Bannu
HW
30-11--1 30-11--1 - 30-11--1 - 64 15.812 8.479 8.479 8.479 8.479 24.291 39.709 38% 38%
May - 2021
Work in progress. Demand Rs: 30 M P-II
No Image
Const: of 06 KMs B/T road form Malik Sabeel Khan Skana Ping Daryoba
1360
(OG)
191669-170376-FATA Infrastructure Development Programe. Phase- II [MA]
FR Bannu
30-11--1 30-11--1 - 30-11--1 - 64 15.812 15 15 8.479 6.374 22.186 33.188 48% 35%
December - 2020
Work in progress. Demand Rs: 30 M P-II
No Image
1360
(OG)
191669-170376-FATA Infrastructure Development Programe. Phase- II [MA]
FR Bannu
30-11--1 30-11--1 - 30-11--1 - 64 15.812 15 15 8.479 6.374 22.186 33.188 48% 35%
December - 2020
Work in progress. Demand Rs: 30 M P-II
No Image
1360
(OG)
191669-170376-FATA Infrastructure Development Programe. Phase- II [MA]
FR Bannu
30-11--1 30-11--1 - 30-11--1 - 64 15.812 15 15 0 0 15.812 33.188 48% 25%
October - 2020
Work in progress.
No Image
1360
(OG)
191669-170376-FATA Infrastructure Development Programe. Phase- II [MA]
FR Bannu
30-11--1 30-11--1 - 30-11--1 - 64 15.812 15 15 0 0 15.812 33.188 48% 25%
September - 2020
Work in progress.
No Image
1360
(OG)
191669-170376-FATA Infrastructure Development Programe. Phase- II [MA]
FR Bannu
30-11--1 30-11--1 - 30-11--1 - 64 15.812 15 15 0 0 15.812 33.188 48% 25%
August - 2020
Work in progress.
No Image
1360
(OG)
191669-170376-FATA Infrastructure Development Programe. Phase- II [MA]
FR Bannu
30-11--1 30-11--1 - 30-11--1 - 391.08 225.792 15 0 0 0 225.792 0
July - 2020
No Image
1360
(OG)
191669-170376-FATA Infrastructure Development Programe. Phase- II [MA]
FR Bannu
30-11--1 30-11--1 - 30-11--1 - 64 15.812 8.479 8.479 8.479 8.479 24.291 39.709 38% 38%
April - 2021
Work in progress. Demand Rs: 30 M P-II
No Image
Const: of 06 KMs B/T road form Malik Sabeel Khan Skana Ping Daryoba
1360
(OG)
191669-170376-FATA Infrastructure Development Programe. Phase- II [MA]
FR Bannu
30-11--1 30-11--1 - 30-11--1 - 64 15.812 8.479 8.479 8.479 8.479 24.291 39.709 38% 38%
March - 2021
Work in progress. Demand Rs: 30 M P-II
No Image
Const: of 06 KMs B/T road form Malik Sabeel Khan Skana Ping Daryoba
1360
(OG)
191669-170376-FATA Infrastructure Development Programe. Phase- II [MA]
FR Bannu
30-11--1 30-11--1 - 30-11--1 - 64 15.812 8.479 8.479 8.479 6.374 22.186 39.709 38% 35%
February - 2021
Work in progress. Demand Rs: 30 M P-II
No Image
Const: of 06 KMs B/T road form Malik Sabeel Khan Skana Ping Daryoba
1360
(OG)
191669-170376-FATA Infrastructure Development Programe. Phase- II [MA]
FR Bannu
30-11--1 30-11--1 - 30-11--1 - 64 15.812 8.479 8.479 8.479 6.374 22.186 39.709 38% 35%
January - 2021
Work in progress. Demand Rs: 30 M P-II
No Image
Const: of 06 KMs B/T road form Malik Sabeel Khan Skana Ping Daryoba
1360
(OG)
191669-170376-FATA Infrastructure Development Programe. Phase- II [MA]
North Waziristan
30-11--1 30-11--1 - 30-11--1 - 101.9 88.893 15 15 0 0 88.893 0 100% 87%
December - 2020
02- Units, Completed= 1 In progress=1
No Image
1360
(OG)
191669-170376-FATA Infrastructure Development Programe. Phase- II [MA]
North Waziristan
30-11--1 30-11--1 - 30-11--1 - 101.9 88.893 15 15 0 0 88.893 0 100% 87%
December - 2020
02- Units, Completed= 1 In progress=1
No Image
1360
(OG)
191669-170376-FATA Infrastructure Development Programe. Phase- II [MA]
North Waziristan
30-11--1 30-11--1 - 30-11--1 - 101.9 88.893 15 15 0 0 88.893 0 100% 87%
October - 2020
02- Units, Completed= 1 In progress=1
No Image
1360
(OG)
191669-170376-FATA Infrastructure Development Programe. Phase- II [MA]
North Waziristan
30-11--1 30-11--1 - 30-11--1 - 101.9 88.893 15 15 0 0 88.893 0 100% 87%
September - 2020
02- Units, Completed= 1 In progress=1
No Image
1360
(OG)
191669-170376-FATA Infrastructure Development Programe. Phase- II [MA]
North Waziristan
30-11--1 30-11--1 - 30-11--1 - 101.9 88.893 15 15 0 0 88.893 0 100% 87%
August - 2020
02- Units, Completed= 1 In progress=1
No Image
1360
(OG)
191669-170376-FATA Infrastructure Development Programe. Phase- II [MA]
North Waziristan
30-11--1 30-11--1 - 30-11--1 - 101.9 88.893 0 0 0 0 88.893 13.007 - 87%
March - 2021
02- Units, Completed= 1 In progress=1 Demand Rs: 13 M
No Image
1360
(OG)
191669-170376-FATA Infrastructure Development Programe. Phase- II [MA]
North Waziristan
30-11--1 30-11--1 - 30-11--1 - 101.9 88.893 0 0 0 0 88.893 13.007 - 87%
February - 2021
02- Units, Completed= 1 In progress=1 Demand Rs: 13 M
No Image
1360
(OG)
191669-170376-FATA Infrastructure Development Programe. Phase- II [MA]
North Waziristan
30-11--1 30-11--1 - 30-11--1 - 101.9 88.893 0 0 0 0 88.893 13.007 - 87%
January - 2021
02- Units, Completed= 1 In progress=1 Demand Rs: 13 M
No Image
1360
(OG)
191669-170376-FATA Infrastructure Development Programe. Phase- II [MA]
North Waziristan
HW
30-11--1 30-11--1 - 30-11--1 - 101.9 88.893 0 0 0 0 88.893 13.007 - 87%
May - 2021
02- Units, Completed= 1 In progress=1 Demand Rs: 13 M
No Image
1360
(OG)
191669-170376-FATA Infrastructure Development Programe. Phase- II [MA]
North Waziristan
HW
30-11--1 30-11--1 - 30-11--1 - 101.9 88.893 0 0 0 0 88.893 13.007 - 87%
April - 2021
02- Units, Completed= 1 In progress=1 Demand Rs: 13 M
No Image
1360
(OG)
191669-170376-FATA Infrastructure Development Programe. Phase- II [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 391.08 225.792 15 15 0 0 225.792 0 - -
December - 2020
No Image
1360
(OG)
191669-170376-FATA Infrastructure Development Programe. Phase- II [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 391.08 225.792 15 15 0 0 225.792 0 - -
December - 2020
No Image
1360
(OG)
191669-170376-FATA Infrastructure Development Programe. Phase- II [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 391.08 225.792 15 15 0 0 225.792 0 - -
October - 2020
No Image
1360
(OG)
191669-170376-FATA Infrastructure Development Programe. Phase- II [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 391.08 225.792 15 15 0 0 225.792 0 - -
September - 2020
No Image
1360
(OG)
191669-170376-FATA Infrastructure Development Programe. Phase- II [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 391.08 225.792 15 15 0 0 225.792 0 - -
August - 2020
No Image
1360
(OG)
191669-170376-FATA Infrastructure Development Programe. Phase- II [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 391.08 225.792 15 0 0 0 225.792 0
July - 2020
No Image
1360
(OG)
191669-170376-FATA Infrastructure Development Programe. Phase- II [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 391.08 225.792 15 15 0 0 225.792 0 - -
May - 2021
No Image
1360
(OG)
191669-170376-FATA Infrastructure Development Programe. Phase- II [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 391.08 225.792 15 15 0 0 225.792 0 - -
April - 2021
No Image
1360
(OG)
191669-170376-FATA Infrastructure Development Programe. Phase- II [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 391.08 225.792 15 15 0 0 225.792 0 - -
March - 2021
No Image
1360
(OG)
191669-170376-FATA Infrastructure Development Programe. Phase- II [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 391.08 225.792 15 15 0 0 225.792 0 - -
February - 2021
No Image
1360
(OG)
191669-170376-FATA Infrastructure Development Programe. Phase- II [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 391.08 225.792 15 15 0 0 225.792 0 - -
January - 2021
No Image
1360
(OG)
191669-170376-FATA Infrastructure Development Programe. Phase- II [MA]
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 46.169 38.968 0 0 0 0 38.968 7.201 - 84%
October - 2020
Physically completed. Liability 7.5 M
No Image
1360
(OG)
191669-170376-FATA Infrastructure Development Programe. Phase- II [MA]
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 46.169 38.968 0 0 0 0 38.968 7.201 - 84%
September - 2020
Physically completed. Liability 7.5 M
No Image
1360
(OG)
191669-170376-FATA Infrastructure Development Programe. Phase- II [MA]
South Waziristan
HW
30-11--1 30-11--1 - 30-11--1 - 49.5 38.968 0 0 0 0 38.968 10.532 - 79%
December - 2020
Physically completed. Liability 7.5 M
No Image
1360
(OG)
191669-170376-FATA Infrastructure Development Programe. Phase- II [MA]
South Waziristan
HW
30-11--1 30-11--1 - 30-11--1 - 49.5 38.968 0 0 0 0 38.968 10.532 - 79%
December - 2020
Physically completed. Liability 7.5 M
No Image
1360
(OG)
191669-170376-FATA Infrastructure Development Programe. Phase- II [MA]
South Waziristan
HW
30-11--1 30-11--1 - 30-11--1 - 49.5 38.968 0 0 0 0 38.968 10.532 - 79%
May - 2021
Physically completed. Liability 7.5 M
No Image
Const: of 3 KM BTR Kot Naseem Ullah S/O Mir Azam Khan Sararogha SWA
1360
(OG)
191669-170376-FATA Infrastructure Development Programe. Phase- II [MA]
South Waziristan
HW
30-11--1 30-11--1 - 30-11--1 - 49.5 38.968 0 0 0 0 38.968 10.532 - 79%
April - 2021
Physically completed. Liability 7.5 M
No Image
Const: of 3 KM BTR Kot Naseem Ullah S/O Mir Azam Khan Sararogha SWA
1360
(OG)
191669-170376-FATA Infrastructure Development Programe. Phase- II [MA]
South Waziristan
HW
30-11--1 30-11--1 - 30-11--1 - 49.5 38.968 0 0 0 0 38.968 10.532 - 79%
March - 2021
Physically completed. Liability 7.5 M
No Image
Const: of 3 KM BTR Kot Naseem Ullah S/O Mir Azam Khan Sararogha SWA
1360
(OG)
191669-170376-FATA Infrastructure Development Programe. Phase- II [MA]
South Waziristan
HW
30-11--1 30-11--1 - 30-11--1 - 49.5 38.968 0 0 0 0 38.968 10.532 - 79%
February - 2021
Physically completed. Liability 7.5 M
No Image
Const: of 3 KM BTR Kot Naseem Ullah S/O Mir Azam Khan Sararogha SWA
1360
(OG)
191669-170376-FATA Infrastructure Development Programe. Phase- II [MA]
South Waziristan
HW
30-11--1 30-11--1 - 30-11--1 - 49.5 38.968 0 0 0 0 38.968 10.532 - 79%
January - 2021
Physically completed. Liability 7.5 M