Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2021, February - 2021, March - 2021, April - 2018, April - 2021, May - 2018, May - 2021, June - 2018, July - 2020, August - 2020, September - 2020, October - 2020, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1352
(OG)
191673-170026-lntegrated Development in Arang / Barang and Mamond / Salarzai Areas, in District Bajaur. [MA]
Bajaur
30-11--1 30-11--1 - 30-11--1 - 120 0 10 0 0 0 0 110 8% -
July - 2020
No Image
1352
(OG)
191673-170026-lntegrated Development in Arang / Barang and Mamond / Salarzai Areas, in District Bajaur. [MA]
Bajaur
HW
30-11--1 30-11--1 - 30-11--1 - 120 0 10 10 0 0 0 110 8% -
December - 2020
Tender approval in progress.
No Image
1352
(OG)
191673-170026-lntegrated Development in Arang / Barang and Mamond / Salarzai Areas, in District Bajaur. [MA]
Bajaur
HW
30-11--1 30-11--1 - 30-11--1 - 120 0 10 10 0 0 0 110 8% -
December - 2020
Tender approval in progress.
No Image
1352
(OG)
191673-170026-lntegrated Development in Arang / Barang and Mamond / Salarzai Areas, in District Bajaur. [MA]
Bajaur
HW
30-11--1 30-11--1 - 30-11--1 - 120 0 10 10 0 0 0 110 8% -
October - 2020
Approved.
No Image
1352
(OG)
191673-170026-lntegrated Development in Arang / Barang and Mamond / Salarzai Areas, in District Bajaur. [MA]
Bajaur
HW
30-11--1 30-11--1 - 30-11--1 - 120 0 10 10 0 0 0 110 8% -
September - 2020
Approved.
No Image
1352
(OG)
191673-170026-lntegrated Development in Arang / Barang and Mamond / Salarzai Areas, in District Bajaur. [MA]
Bajaur
HW
30-11--1 30-11--1 - 30-11--1 - 135 0 10 10 0 0 0 0 - -
August - 2020
PDWP held on 10/9/2020. Approved. AA awaited
No Image
1352
(OG)
191673-170026-lntegrated Development in Arang / Barang and Mamond / Salarzai Areas, in District Bajaur. [MA]
Bajaur
HW
30-11--1 30-11--1 - 30-11--1 - 120 0 10 0 0 0 0 110 8% -
May - 2021
Work in progress Demand Rs. 5 M fo tempo
No Image
Const: & B/T of Dangqool to Sro Wano Road 4 KM Phase-I
1352
(OG)
191673-170026-lntegrated Development in Arang / Barang and Mamond / Salarzai Areas, in District Bajaur. [MA]
Bajaur
HW
30-11--1 30-11--1 - 30-11--1 - 120 0 10 0 0 0 0 110 8% -
April - 2021
Work in progress Demand Rs. 5 M fo tempo
No Image
1352
(OG)
191673-170026-lntegrated Development in Arang / Barang and Mamond / Salarzai Areas, in District Bajaur. [MA]
Bajaur
HW
30-11--1 30-11--1 - 30-11--1 - 120 0 10 0 0 0 0 110 8% -
March - 2021
Work in progress
No Image
1352
(OG)
191673-170026-lntegrated Development in Arang / Barang and Mamond / Salarzai Areas, in District Bajaur. [MA]
Bajaur
HW
30-11--1 30-11--1 - 30-11--1 - 120 0 10 0 0 0 0 110 8% -
February - 2021
Tender approved Add: Security not yet deposited
No Image
1352
(OG)
191673-170026-lntegrated Development in Arang / Barang and Mamond / Salarzai Areas, in District Bajaur. [MA]
Bajaur
HW
30-11--1 30-11--1 - 30-11--1 - 120 0 10 10 0 0 0 110 8% -
January - 2021
Tender approval in progress.
No Image
1352
(OG)
150019-Development of Swat, Chitral, Mardan and Hund Museum Campuses.
Provincial
30-11--1 30-11--1 - 30-11--1 - 59.5 0 0 0 0 0 0 59.5 - -
June - 2018
Approved.
No Image
1352
(OG)
150019-Development of Swat, Chitral, Mardan and Hund Museum Campuses.
Provincial
30-11--1 30-11--1 - 30-11--1 - 59.5 0 0 0 0 0 0 59.5 - -
May - 2018
Approved.
No Image
1352
(OG)
150019-Development of Swat, Chitral, Mardan and Hund Museum Campuses.
Provincial
30-11--1 30-11--1 - 30-11--1 - 59.5 0 0 0 0 0 0 59.5 - -
April - 2018
Approved.
No Image
1352
(OG)
150019-Development of Swat, Chitral, Mardan and Hund Museum Campuses.
Swat
30-11--1 30-11--1 - 30-11--1 - 0 0 18 18 18 7.498 7.498 0 - -
June - 2018
Basement slab laid. GF cloumn completed.
No Image
1352
(OG)
150019-Development of Swat, Chitral, Mardan and Hund Museum Campuses.
Swat
30-11--1 30-11--1 - 30-11--1 - 0 0 18 18 18 7.498 7.498 0 - -
May - 2018
Basement slab laid. GF cloumn completed.
No Image
1352
(OG)
150019-Development of Swat, Chitral, Mardan and Hund Museum Campuses.
Swat
30-11--1 30-11--1 - 30-11--1 - 0 0 18 18 18 6.674 6.674 0 - -
April - 2018
Basement slab laid. GF cloumn completed.