Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2021, February - 2021, March - 2021, April - 2021, April - 2018, May - 2021, May - 2018, June - 2018, July - 2020, August - 2020, September - 2020, October - 2020, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1350
(OG)
191674-170096-Integrated Area Development Projects in Khyber Agency. [MA]
Khyber
30-11--1 30-11--1 - 30-11--1 - 43.468 20 0 0 0 0 20 23.468 - 46%
December - 2020
5- Units 4 units work in progress 1 unit work not yet started.
No Image
1350
(OG)
191674-170096-Integrated Area Development Projects in Khyber Agency. [MA]
Khyber
30-11--1 30-11--1 - 30-11--1 - 43.468 20 0 0 0 0 20 23.468 - 46%
December - 2020
5- Units 4 units work in progress 1 unit work not yet started.
No Image
1350
(OG)
191674-170096-Integrated Area Development Projects in Khyber Agency. [MA]
Khyber
30-11--1 30-11--1 - 30-11--1 - 43.468 20 0 0 0 0 20 23.468 - 46%
October - 2020
5- Units 4 units work in progress 1 unit work not yet started.
No Image
1350
(OG)
191674-170096-Integrated Area Development Projects in Khyber Agency. [MA]
Khyber
30-11--1 30-11--1 - 30-11--1 - 43.468 20 0 0 0 0 20 23.468 - 46%
September - 2020
5- Units 4 units work in progress 1 unit work not yet started.
No Image
1350
(OG)
191674-170096-Integrated Area Development Projects in Khyber Agency. [MA]
Khyber
30-11--1 30-11--1 - 30-11--1 - 43.468 20 0 0 0 0 20 23.468 - 46%
August - 2020
5- Units 4 units work in progress 1 unit work not yet started.
No Image
1350
(OG)
191674-170096-Integrated Area Development Projects in Khyber Agency. [MA]
Khyber
30-11--1 30-11--1 - 30-11--1 - 70.154 35 0 0 0 0 35 35.154 - 50%
July - 2020
3 Units Work in progress on all.
No Image
1350
(OG)
191674-170096-Integrated Area Development Projects in Khyber Agency. [MA]
Khyber
30-11--1 30-11--1 - 30-11--1 - 43.468 20 0 0 0 0 20 23.468 - 46%
July - 2020
5- Units 4 units work in progress 1 unit work not yet started.
No Image
1350
(OG)
191674-170096-Integrated Area Development Projects in Khyber Agency. [MA]
Khyber
30-11--1 30-11--1 - 30-11--1 - 43.468 20 0 0 0 0 20 23.468 - 46%
May - 2021
5- Units 4 units work in progress 1 unit work not yet started.
No Image
1 GPS Sandana
2 GPS Wacha Wana
3 GGPS Tarkokhas
4 GMS Khasta Gul Sara Wala
5 GMS Tarkokas
1350
(OG)
191674-170096-Integrated Area Development Projects in Khyber Agency. [MA]
Khyber
30-11--1 30-11--1 - 30-11--1 - 43.468 20 0 0 0 0 20 23.468 - 46%
April - 2021
5- Units 4 units work in progress 1 unit work not yet started.
No Image
1 GPS Sandana
2 GPS Wacha Wana
3 GGPS Tarkokhas
4 GMS Khasta Gul Sara Wala
5 GMS Tarkokas
1350
(OG)
191674-170096-Integrated Area Development Projects in Khyber Agency. [MA]
Khyber
30-11--1 30-11--1 - 30-11--1 - 43.468 20 0 0 0 0 20 23.468 - 46%
March - 2021
5- Units 4 units work in progress 1 unit work not yet started.
No Image
1 GPS Sandana
2 GPS Wacha Wana
3 GGPS Tarkokhas
4 GMS Khasta Gul Sara Wala
5 GMS Tarkokas
1350
(OG)
191674-170096-Integrated Area Development Projects in Khyber Agency. [MA]
Khyber
30-11--1 30-11--1 - 30-11--1 - 43.468 20 0 0 0 0 20 23.468 - 46%
February - 2021
5- Units 4 units work in progress 1 unit work not yet started.
No Image
1 GPS Sandana
2 GPS Wacha Wana
3 GGPS Tarkokhas
4 GMS Khasta Gul Sara Wala
5 GMS Tarkokas
1350
(OG)
191674-170096-Integrated Area Development Projects in Khyber Agency. [MA]
Khyber
30-11--1 30-11--1 - 30-11--1 - 43.468 20 0 0 0 0 20 23.468 - 46%
January - 2021
5- Units 4 units work in progress 1 unit work not yet started.
No Image
1 GPS Sandana
2 GPS Wacha Wana
3 GGPS Tarkokhas
4 GMS Khasta Gul Sara Wala
5 GMS Tarkokas
1350
(OG)
191674-170096-Integrated Area Development Projects in Khyber Agency. [MA]
Khyber
HW
30-11--1 30-11--1 - 30-11--1 - 70.154 35 2 2 2 2 37 33.154 53% 53%
December - 2020
3 Units E/Work Road work & S/Work in progress. 2- Sub/Structure 100% Super/Structure 100% 3- Sub/Structure 80% Super/Structure 30% P-II : Demand Rs. 44 M
No Image
1) Constn of 5Km B/T road at Stori Khel Malik Almas Killi in upper Bara.
2) Suspension Bridge (Pedestrain) at Haji Mehmood Killi Upper Bara (L-600 Reft)
3) Suspension Bridge (Pedestrain) at Haji Mehraban Killi Upper Bara.
1350
(OG)
191674-170096-Integrated Area Development Projects in Khyber Agency. [MA]
Khyber
HW
30-11--1 30-11--1 - 30-11--1 - 70.154 35 2 2 2 2 37 33.154 53% 53%
December - 2020
3 Units E/Work Road work & S/Work in progress. 2- Sub/Structure 100% Super/Structure 100% 3- Sub/Structure 80% Super/Structure 30% P-II : Demand Rs. 44 M
No Image
1) Constn of 5Km B/T road at Stori Khel Malik Almas Killi in upper Bara.
2) Suspension Bridge (Pedestrain) at Haji Mehmood Killi Upper Bara (L-600 Reft)
3) Suspension Bridge (Pedestrain) at Haji Mehraban Killi Upper Bara.
1350
(OG)
191674-170096-Integrated Area Development Projects in Khyber Agency. [MA]
Khyber
HW
30-11--1 30-11--1 - 30-11--1 - 70.154 35 2 2 2 2 37 33.154 53% 53%
October - 2020
3 Units E/Work Road work & S/Work in progress. 2- Sub/Structure 100% Super/Structure 100% 3- Sub/Structure 80% Super/Structure 30%
No Image
1) Constn of 5Km B/T road at Stori Khel Malik Almas Killi in upper Bara.
2) Suspension Bridge (Pedestrain) at Haji Mehmood Killi Upper Bara (L-600 Reft)
3) Suspension Bridge (Pedestrain) at Haji Mehraban Killi Upper Bara.
1350
(OG)
191674-170096-Integrated Area Development Projects in Khyber Agency. [MA]
Khyber
HW
30-11--1 30-11--1 - 30-11--1 - 70.154 35 2 2 2 2 37 33.154 53% 53%
September - 2020
3 Units E/Work Road work & S/Work in progress. 2- Sub/Structure 100% Super/Structure 100% 3- Sub/Structure 80% Super/Structure 30%
No Image
1) Constn of 5Km B/T road at Stori Khel Malik Almas Killi in upper Bara.
2) Suspension Bridge (Pedestrain) at Haji Mehmood Killi Upper Bara (L-600 Reft)
3) Suspension Bridge (Pedestrain) at Haji Mehraban Killi Upper Bara.
1350
(OG)
191674-170096-Integrated Area Development Projects in Khyber Agency. [MA]
Khyber
HW
30-11--1 30-11--1 - 30-11--1 - 70.154 35 0 0 0 0 35 35.154 - 50%
August - 2020
3 Units Work in progress on all.
No Image
1350
(OG)
191674-170096-Integrated Area Development Projects in Khyber Agency. [MA]
Khyber
HW
30-11--1 30-11--1 - 30-11--1 - 70.154 23.2 2 2 2 2 25.2 44.954 36% 36%
May - 2021
3 Units E/Work Road work & S/Work in progress. 2- Sub/Structure 100% Super/Structure 100% 3- Sub/Structure 80% Super/Structure 30% P-II : Demand Rs. 44 M
No Image
1) Constn of 5Km B/T road at Stori Khel Malik Almas Killi in upper Bara.
2) Suspension Bridge (Pedestrain) at Haji Mehmood Killi Upper Bara (L-600 Reft)
3) Suspension Bridge (Pedestrain) at Haji Mehraban Killi Upper Bara.
1350
(OG)
191674-170096-Integrated Area Development Projects in Khyber Agency. [MA]
Khyber
HW
30-11--1 30-11--1 - 30-11--1 - 70.154 23.2 2 2 2 2 25.2 44.954 36% 36%
April - 2021
3 Units E/Work Road work & S/Work in progress. 2- Sub/Structure 100% Super/Structure 100% 3- Sub/Structure 80% Super/Structure 30% P-II : Demand Rs. 44 M
No Image
1) Constn of 5Km B/T road at Stori Khel Malik Almas Killi in upper Bara.
2) Suspension Bridge (Pedestrain) at Haji Mehmood Killi Upper Bara (L-600 Reft)
3) Suspension Bridge (Pedestrain) at Haji Mehraban Killi Upper Bara.
1350
(OG)
191674-170096-Integrated Area Development Projects in Khyber Agency. [MA]
Khyber
HW
30-11--1 30-11--1 - 30-11--1 - 70.154 23.2 2 2 2 2 25.2 44.954 36% 36%
March - 2021
3 Units E/Work Road work & S/Work in progress. 2- Sub/Structure 100% Super/Structure 100% 3- Sub/Structure 80% Super/Structure 30% P-II : Demand Rs. 44 M
No Image
1) Constn of 5Km B/T road at Stori Khel Malik Almas Killi in upper Bara.
2) Suspension Bridge (Pedestrain) at Haji Mehmood Killi Upper Bara (L-600 Reft)
3) Suspension Bridge (Pedestrain) at Haji Mehraban Killi Upper Bara.
1350
(OG)
191674-170096-Integrated Area Development Projects in Khyber Agency. [MA]
Khyber
HW
30-11--1 30-11--1 - 30-11--1 - 70.154 23.2 2 2 2 2 25.2 44.954 36% 36%
February - 2021
3 Units E/Work Road work & S/Work in progress. 2- Sub/Structure 100% Super/Structure 100% 3- Sub/Structure 80% Super/Structure 30% P-II : Demand Rs. 44 M
No Image
1) Constn of 5Km B/T road at Stori Khel Malik Almas Killi in upper Bara.
2) Suspension Bridge (Pedestrain) at Haji Mehmood Killi Upper Bara (L-600 Reft)
3) Suspension Bridge (Pedestrain) at Haji Mehraban Killi Upper Bara.
1350
(OG)
191674-170096-Integrated Area Development Projects in Khyber Agency. [MA]
Khyber
HW
30-11--1 30-11--1 - 30-11--1 - 70.154 35 2 2 2 2 37 33.154 53% 53%
January - 2021
3 Units E/Work Road work & S/Work in progress. 2- Sub/Structure 100% Super/Structure 100% 3- Sub/Structure 80% Super/Structure 30% P-II : Demand Rs. 44 M
No Image
1) Constn of 5Km B/T road at Stori Khel Malik Almas Killi in upper Bara.
2) Suspension Bridge (Pedestrain) at Haji Mehmood Killi Upper Bara (L-600 Reft)
3) Suspension Bridge (Pedestrain) at Haji Mehraban Killi Upper Bara.
1350
(OG)
191674-170096-Integrated Area Development Projects in Khyber Agency. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 280.5 0 9.392 9.392 0 0 0 0 - -
December - 2020
No Image
1350
(OG)
191674-170096-Integrated Area Development Projects in Khyber Agency. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 280.5 0 9.392 9.392 0 0 0 0 - -
December - 2020
No Image
1350
(OG)
191674-170096-Integrated Area Development Projects in Khyber Agency. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 280.5 0 9.392 9.392 0 0 0 0 - -
October - 2020
No Image
1350
(OG)
191674-170096-Integrated Area Development Projects in Khyber Agency. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 280.5 0 9.392 9.392 0 0 0 0 - -
September - 2020
No Image
1350
(OG)
191674-170096-Integrated Area Development Projects in Khyber Agency. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 280.5 0 9.392 9.392 0 0 0 0 - -
August - 2020
No Image
1350
(OG)
191674-170096-Integrated Area Development Projects in Khyber Agency. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 280.5 0 9.392 0 0 0 0 0 - -
July - 2020
No Image
1350
(OG)
120087-Conservation & Development of World Heritage Sites of Khyber Pakhtunkhwa.
Provincial
30-11--1 30-11--1 - 30-11--1 - 60 0 0 0 0 0 0 60 - -
June - 2018
Approved.
No Image
1350
(OG)
120087-Conservation & Development of World Heritage Sites of Khyber Pakhtunkhwa.
Provincial
30-11--1 30-11--1 - 30-11--1 - 60 0 0 0 0 0 0 60 - -
May - 2018
Approved.
No Image
1350
(OG)
191674-170096-Integrated Area Development Projects in Khyber Agency. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 280.5 0 9.392 9.392 0 0 0 0 - -
May - 2021
No Image
1350
(OG)
120087-Conservation & Development of World Heritage Sites of Khyber Pakhtunkhwa.
Provincial
30-11--1 30-11--1 - 30-11--1 - 60 0 0 0 0 0 0 60 - -
April - 2018
Approved.
No Image
1350
(OG)
191674-170096-Integrated Area Development Projects in Khyber Agency. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 280.5 0 9.392 9.392 0 0 0 0 - -
April - 2021
No Image
1350
(OG)
191674-170096-Integrated Area Development Projects in Khyber Agency. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 280.5 0 9.392 9.392 0 0 0 0 - -
March - 2021
No Image
1350
(OG)
191674-170096-Integrated Area Development Projects in Khyber Agency. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 280.5 0 9.392 9.392 0 0 0 0 - -
February - 2021
No Image
1350
(OG)
191674-170096-Integrated Area Development Projects in Khyber Agency. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 280.5 0 9.392 9.392 0 0 0 0 - -
January - 2021
No Image
Pages : 1