Progressive Review for the month(s) of : January - 2018, January - 2021, February - 2018, February - 2021, March - 2018, March - 2021, April - 2018, April - 2021, May - 2018, May - 2021, June - 2018, July - 2017, July - 2020, August - 2017, August - 2020, September - 2017, September - 2020, October - 2017, October - 2020, November - 2017, December - 2017, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1315
(OG)
150447-Construction of T.A.B.D.E.E.L.I Centre at Hayatabad Peshawar.
Peshawar
BD-2
- 30-06-18 - 14-04-17 - 58.605 1.732 57.868 57.868 21.8 15.668 17.4 0 100% 30%
December - 2017
Drawing approved by PDA on 03/06/2017. Basement roofing in progress.
No Image
PDA charges --- Rs.0.200 m + Plot restoration chages to PDA --- Rs.4.850 m = Rs.5.050 m
1315
(OG)
150447-Construction of T.A.B.D.E.E.L.I Centre at Hayatabad Peshawar.
Peshawar
BD-2
30-11--1 30-11--1 - 30-11--1 - 58.605 1.732 57.868 57.868 21.8 15.668 17.4 0 100% 30%
November - 2017
Drawing approved by PDA on 03/06/2017. Basement roofing in progress.
No Image
PDA charges --- Rs.0.200 m + Plot restoration chages to PDA --- Rs.4.850 m = Rs.5.050 m
1315
(OG)
150447-Construction of T.A.B.D.E.E.L.I Centre at Hayatabad Peshawar.
Peshawar
BD-2
30-11--1 30-11--1 - 30-11--1 - 58.605 1.732 57.868 57.868 21.8 12.257 13.989 0 100% 24%
October - 2017
Drawing approved by PDA on 03/06/2017. Basement roofing in progress.
No Image
PDA charges --- Rs.0.200 m + Plot restoration chages to PDA --- Rs.4.850 m = Rs.5.050 m
1315
(OG)
150447-Construction of T.A.B.D.E.E.L.I Centre at Hayatabad Peshawar.
Peshawar
BD-2
- 30-06-18 - 14-04-17 - 58.605 1.732 57.868 57.868 21.8 0 1.732 0 100% 3%
September - 2017
Drawing approved by PDA on 03/06/2017. Raft foundation completed.
No Image
PDA charges --- Rs.0.200 m + Plot restoration chages to PDA --- Rs.4.850 m = Rs.5.050 m
1315
(OG)
150447-Construction of T.A.B.D.E.E.L.I Centre at Hayatabad Peshawar.
Peshawar
BD-2
- 30-06-18 - 14-04-17 - 58.605 1.732 57.868 57.868 21.8 0 1.732 0 100% 3%
August - 2017
Work started. Drawing approved by PDA on 03/06/2017.
No Image
PDA charges --- Rs.0.200 m + Plot restoration chages to PDA --- Rs.4.850 m = Rs.5.050 m
1315
(OG)
150447-Construction of T.A.B.D.E.E.L.I Centre at Hayatabad Peshawar.
Peshawar
BD-2
- 30-06-18 - 14-04-17 - 58.605 1.732 57.868 57.868 0 0 1.732 0 100% 3%
July - 2017
Work started. Drawing approved by PDA on 03/06/2017.
No Image
PDA charges --- Rs.0.200 m + Plot restoration chages to PDA --- Rs.4.850 m = Rs.5.050 m
1315
(OG)
150447-Construction of T.A.B.D.E.E.L.I Centre at Hayatabad Peshawar.
Peshawar
BD-2
30-11--1 30-11--1 - 30-11--1 - 58.605 1.732 57.868 24.773 24.773 24.773 26.505 0 100% 45%
June - 2018
Drawing approved by PDA on 03/06/2017. Basement work in progress.
No Image
Phase-V Hayatabad, Peshawar
1315
(OG)
150447-Construction of T.A.B.D.E.E.L.I Centre at Hayatabad Peshawar.
Peshawar
BD-2
30-11--1 30-11--1 - 30-11--1 - 58.605 1.732 57.868 57.868 43.401 24.773 26.505 0 100% 45%
May - 2018
Drawing approved by PDA on 03/06/2017. Basement work in progress.
No Image
Phase-V Hayatabad, Peshawar
1315
(OG)
150447-Construction of T.A.B.D.E.E.L.I Centre at Hayatabad Peshawar.
Peshawar
BD-2
30-11--1 30-11--1 - 30-11--1 - 58.605 1.732 57.868 57.868 43.401 24.799 26.531 0 100% 45%
April - 2018
Drawing approved by PDA on 03/06/2017. Basement work in progress.
No Image
Phase-V Hayatabad, Peshawar
1315
(OG)
150447-Construction of T.A.B.D.E.E.L.I Centre at Hayatabad Peshawar.
Peshawar
BD-2
30-11--1 30-11--1 - 30-11--1 - 58.605 1.732 57.868 57.868 43.401 21.804 23.536 0 100% 40%
March - 2018
Drawing approved by PDA on 03/06/2017. Basement work in progress. Cannot be completed in CFY because of delay of approval of drawing by PDA.
No Image
Phase-V Hayatabad, Peshawar
1315
(OG)
150447-Construction of T.A.B.D.E.E.L.I Centre at Hayatabad Peshawar.
Peshawar
BD-2
30-11--1 30-11--1 - 30-11--1 - 58.605 1.732 57.868 57.868 21.8 20.623 22.355 0 100% 38%
February - 2018
Drawing approved by PDA on 03/06/2017. Basement work in progress. Cannot be Complted in CFY because of dealy of approval of drawing by PDA.
No Image
Phase-V Hayatabad, Peshawar
1315
(OG)
150447-Construction of T.A.B.D.E.E.L.I Centre at Hayatabad Peshawar.
Peshawar
BD-2
30-11--1 30-11--1 - 30-11--1 - 58.605 1.732 57.868 57.868 21.8 18.328 20.06 0 100% 34%
January - 2018
Drawing approved by PDA on 03/06/2017. Basement roofing in progress.
No Image
Phase-V Hayatabad Peshawar
1315
(OG)
70532- Establishment of M&E System in Khyber Pakhtunkhwa.
Provincial
30-11--1 30-11--1 - 30-11--1 - 1132.348 769.87 0 0 0 0 769.87 0 - -
December - 2020
No Image
1315
(OG)
70532- Establishment of M&E System in Khyber Pakhtunkhwa.
Provincial
30-11--1 30-11--1 - 30-11--1 - 1132.348 769.87 0 0 0 0 769.87 0 - -
December - 2020
No Image
1315
(OG)
70532- Establishment of M&E System in Khyber Pakhtunkhwa.
Provincial
30-11--1 30-11--1 - 30-11--1 - 1132.348 769.87 0 0 0 0 769.87 0 - -
October - 2020
No Image
1315
(OG)
70532- Establishment of M&E System in Khyber Pakhtunkhwa.
Provincial
30-11--1 30-11--1 - 30-11--1 - 1132.348 769.87 0 0 0 0 769.87 0 - -
September - 2020
No Image
1315
(OG)
70532- Establishment of M&E System in Khyber Pakhtunkhwa.
Provincial
30-11--1 30-11--1 - 30-11--1 - 1132.348 769.87 0 0 0 0 769.87 0 - -
August - 2020
No Image
1315
(OG)
70532- Establishment of M&E System in Khyber Pakhtunkhwa.
Provincial
30-11--1 30-11--1 - 30-11--1 - 1132.348 769.87 0 0 0 0 769.87 0 -
July - 2020
No Image
1315
(OG)
70532- Establishment of M&E System in Khyber Pakhtunkhwa.
Provincial
30-11--1 30-11--1 - 30-11--1 - 1132.348 769.87 0 0 0 0 769.87 0 - -
May - 2021
No Image
1315
(OG)
70532- Establishment of M&E System in Khyber Pakhtunkhwa.
Provincial
30-11--1 30-11--1 - 30-11--1 - 1132.348 769.87 0 0 0 0 769.87 0 - -
April - 2021
No Image
1315
(OG)
70532- Establishment of M&E System in Khyber Pakhtunkhwa.
Provincial
30-11--1 30-11--1 - 30-11--1 - 1132.348 769.87 0 0 0 0 769.87 0 - -
March - 2021
No Image
1315
(OG)
70532- Establishment of M&E System in Khyber Pakhtunkhwa.
Provincial
30-11--1 30-11--1 - 30-11--1 - 1132.348 769.87 0 0 0 0 769.87 0 - -
February - 2021
No Image
1315
(OG)
70532- Establishment of M&E System in Khyber Pakhtunkhwa.
Provincial
30-11--1 30-11--1 - 30-11--1 - 1132.348 769.87 0 0 0 0 769.87 0 - -
January - 2021
No Image
Pages : 1