Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1315 (OG) |
150447-Construction of T.A.B.D.E.E.L.I Centre at Hayatabad Peshawar. |
Peshawar BD-2 |
- | 30-06-18 | - | 14-04-17 | - | 58.605 | 1.732 | 57.868 | 57.868 | 21.8 | 15.668 | 17.4 | 0 | 100% |
30% December - 2017 |
Drawing approved by PDA on 03/06/2017.
Basement roofing in progress. |
No Image |
PDA charges --- Rs.0.200 m + Plot restoration chages to PDA --- Rs.4.850 m = Rs.5.050 m | |||||||||||||||||||
1315 (OG) |
150447-Construction of T.A.B.D.E.E.L.I Centre at Hayatabad Peshawar. |
Peshawar BD-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 58.605 | 1.732 | 57.868 | 57.868 | 21.8 | 15.668 | 17.4 | 0 | 100% |
30% November - 2017 |
Drawing approved by PDA on 03/06/2017. Basement roofing in progress. |
No Image |
PDA charges --- Rs.0.200 m + Plot restoration chages to PDA --- Rs.4.850 m = Rs.5.050 m | |||||||||||||||||||
1315 (OG) |
150447-Construction of T.A.B.D.E.E.L.I Centre at Hayatabad Peshawar. |
Peshawar BD-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 58.605 | 1.732 | 57.868 | 57.868 | 21.8 | 12.257 | 13.989 | 0 | 100% |
24% October - 2017 |
Drawing approved by PDA on 03/06/2017. Basement roofing in progress. |
No Image |
PDA charges --- Rs.0.200 m + Plot restoration chages to PDA --- Rs.4.850 m = Rs.5.050 m | |||||||||||||||||||
1315 (OG) |
150447-Construction of T.A.B.D.E.E.L.I Centre at Hayatabad Peshawar. |
Peshawar BD-2 |
- | 30-06-18 | - | 14-04-17 | - | 58.605 | 1.732 | 57.868 | 57.868 | 21.8 | 0 | 1.732 | 0 | 100% |
3% September - 2017 |
Drawing approved by PDA on 03/06/2017. Raft foundation completed. |
No Image |
PDA charges --- Rs.0.200 m + Plot restoration chages to PDA --- Rs.4.850 m = Rs.5.050 m | |||||||||||||||||||
1315 (OG) |
150447-Construction of T.A.B.D.E.E.L.I Centre at Hayatabad Peshawar. |
Peshawar BD-2 |
- | 30-06-18 | - | 14-04-17 | - | 58.605 | 1.732 | 57.868 | 57.868 | 21.8 | 0 | 1.732 | 0 | 100% |
3% August - 2017 |
Work started. Drawing approved by PDA on 03/06/2017. |
No Image |
PDA charges --- Rs.0.200 m + Plot restoration chages to PDA --- Rs.4.850 m = Rs.5.050 m | |||||||||||||||||||
1315 (OG) |
150447-Construction of T.A.B.D.E.E.L.I Centre at Hayatabad Peshawar. |
Peshawar BD-2 |
- | 30-06-18 | - | 14-04-17 | - | 58.605 | 1.732 | 57.868 | 57.868 | 0 | 0 | 1.732 | 0 | 100% |
3% July - 2017 |
Work started. Drawing approved by PDA on 03/06/2017. |
No Image |
PDA charges --- Rs.0.200 m + Plot restoration chages to PDA --- Rs.4.850 m = Rs.5.050 m | |||||||||||||||||||
1315 (OG) |
150447-Construction of T.A.B.D.E.E.L.I Centre at Hayatabad Peshawar. |
Peshawar BD-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 58.605 | 1.732 | 57.868 | 24.773 | 24.773 | 24.773 | 26.505 | 0 | 100% |
45% June - 2018 |
Drawing approved by PDA on 03/06/2017. Basement work in progress. |
No Image |
Phase-V Hayatabad, Peshawar | |||||||||||||||||||
1315 (OG) |
150447-Construction of T.A.B.D.E.E.L.I Centre at Hayatabad Peshawar. |
Peshawar BD-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 58.605 | 1.732 | 57.868 | 57.868 | 43.401 | 24.773 | 26.505 | 0 | 100% |
45% May - 2018 |
Drawing approved by PDA on 03/06/2017. Basement work in progress. |
No Image |
Phase-V Hayatabad, Peshawar | |||||||||||||||||||
1315 (OG) |
150447-Construction of T.A.B.D.E.E.L.I Centre at Hayatabad Peshawar. |
Peshawar BD-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 58.605 | 1.732 | 57.868 | 57.868 | 43.401 | 24.799 | 26.531 | 0 | 100% |
45% April - 2018 |
Drawing approved by PDA on 03/06/2017. Basement work in progress. |
No Image |
Phase-V Hayatabad, Peshawar | |||||||||||||||||||
1315 (OG) |
150447-Construction of T.A.B.D.E.E.L.I Centre at Hayatabad Peshawar. |
Peshawar BD-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 58.605 | 1.732 | 57.868 | 57.868 | 43.401 | 21.804 | 23.536 | 0 | 100% |
40% March - 2018 |
Drawing approved by PDA on 03/06/2017. Basement work in progress. Cannot be completed in CFY because of delay of approval of drawing by PDA. |
No Image |
Phase-V Hayatabad, Peshawar | |||||||||||||||||||
1315 (OG) |
150447-Construction of T.A.B.D.E.E.L.I Centre at Hayatabad Peshawar. |
Peshawar BD-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 58.605 | 1.732 | 57.868 | 57.868 | 21.8 | 20.623 | 22.355 | 0 | 100% |
38% February - 2018 |
Drawing approved by PDA on 03/06/2017.
Basement work in progress. Cannot be Complted in CFY because of dealy of approval of drawing by PDA. |
No Image |
Phase-V Hayatabad, Peshawar | |||||||||||||||||||
1315 (OG) |
150447-Construction of T.A.B.D.E.E.L.I Centre at Hayatabad Peshawar. |
Peshawar BD-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 58.605 | 1.732 | 57.868 | 57.868 | 21.8 | 18.328 | 20.06 | 0 | 100% |
34% January - 2018 |
Drawing approved by PDA on 03/06/2017. Basement roofing in progress. |
No Image |
Phase-V Hayatabad Peshawar | |||||||||||||||||||
1315 (OG) |
70532- Establishment of M&E System in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1132.348 | 769.87 | 0 | 0 | 0 | 0 | 769.87 | 0 | - |
- December - 2020 |
No Image | |
1315 (OG) |
70532- Establishment of M&E System in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1132.348 | 769.87 | 0 | 0 | 0 | 0 | 769.87 | 0 | - |
- December - 2020 |
No Image | |
1315 (OG) |
70532- Establishment of M&E System in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1132.348 | 769.87 | 0 | 0 | 0 | 0 | 769.87 | 0 | - |
- October - 2020 |
No Image | |
1315 (OG) |
70532- Establishment of M&E System in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1132.348 | 769.87 | 0 | 0 | 0 | 0 | 769.87 | 0 | - |
- September - 2020 |
No Image | |
1315 (OG) |
70532- Establishment of M&E System in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1132.348 | 769.87 | 0 | 0 | 0 | 0 | 769.87 | 0 | - |
- August - 2020 |
No Image | |
1315 (OG) |
70532- Establishment of M&E System in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1132.348 | 769.87 | 0 | 0 | 0 | 0 | 769.87 | 0 | - |
July - 2020 |
No Image | |
1315 (OG) |
70532- Establishment of M&E System in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1132.348 | 769.87 | 0 | 0 | 0 | 0 | 769.87 | 0 | - |
- May - 2021 |
No Image | |
1315 (OG) |
70532- Establishment of M&E System in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1132.348 | 769.87 | 0 | 0 | 0 | 0 | 769.87 | 0 | - |
- April - 2021 |
No Image | |
1315 (OG) |
70532- Establishment of M&E System in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1132.348 | 769.87 | 0 | 0 | 0 | 0 | 769.87 | 0 | - |
- March - 2021 |
No Image | |
1315 (OG) |
70532- Establishment of M&E System in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1132.348 | 769.87 | 0 | 0 | 0 | 0 | 769.87 | 0 | - |
- February - 2021 |
No Image | |
1315 (OG) |
70532- Establishment of M&E System in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1132.348 | 769.87 | 0 | 0 | 0 | 0 | 769.87 | 0 | - |
- January - 2021 |
No Image | |