Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1301 (OG) |
190446-Least developed districts uplift programme (Kolai Palas, Battagram, Tank, Kohistan Upper, Shangla, Buner, Chitral (Upper & Lower) and Hangu. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 220 | 0 | 92.663 | 92.663 | 92.663 | 92.562 | 92.562 | 127.337 | 42% |
42% April - 2021 |
10 units work in progress |
No Image |
| |||||||||||||||||||
1301 (OG) |
190446-Least developed districts uplift programme (Kolai Palas, Battagram, Tank, Kohistan Upper, Shangla, Buner, Chitral (Upper & Lower) and Hangu. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 220 | 0 | 78.201 | 78.201 | 78.201 | 72.259 | 72.259 | 141.799 | 36% |
33% March - 2021 |
10 units work in progress |
No Image |
| |||||||||||||||||||
1301 (OG) |
190446-Least developed districts uplift programme (Kolai Palas, Battagram, Tank, Kohistan Upper, Shangla, Buner, Chitral (Upper & Lower) and Hangu. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 220 | 0 | 78.201 | 78.201 | 78.201 | 58.292 | 58.292 | 141.799 | 36% |
26% February - 2021 |
10 units work in progress |
No Image |
| |||||||||||||||||||
1301 (OG) |
190446-Least developed districts uplift programme (Kolai Palas, Battagram, Tank, Kohistan Upper, Shangla, Buner, Chitral (Upper & Lower) and Hangu. |
Buner HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 220 | 0 | 92.663 | 92.663 | 92.663 | 92.562 | 92.562 | 127.337 | 42% |
42% May - 2021 |
10 units work in progress |
No Image |
| |||||||||||||||||||
1301 (OG) |
190446-Least developed districts uplift programme (Kolai Palas, Battagram, Tank, Kohistan Upper, Shangla, Buner, Chitral (Upper & Lower) and Hangu. |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 7.929 | 0 | 0 | 3.382 | 3.382 | 3.036 | 3.036 | 7.929 | - |
38% May - 2021 |
03- Units
1 Hall in Porgress
2 Hall in progress
3 Work in progress |
No Image |
| |||||||||||||||||||
1301 (OG) |
190446-Least developed districts uplift programme (Kolai Palas, Battagram, Tank, Kohistan Upper, Shangla, Buner, Chitral (Upper & Lower) and Hangu. |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 7.929 | 0 | 0 | 3.382 | 3.382 | 3.036 | 3.036 | 7.929 | - |
38% April - 2021 |
03 units - all in progress
1 Hall in Porgress
2 Hall in progress
3 Work in progress |
No Image |
| |||||||||||||||||||
1301 (OG) |
190446-Least developed districts uplift programme (Kolai Palas, Battagram, Tank, Kohistan Upper, Shangla, Buner, Chitral (Upper & Lower) and Hangu. |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 7.929 | 0 | 0 | 2.91 | 2.91 | 2.503 | 2.503 | 7.929 | - |
32% March - 2021 |
03 units - all in progress
1 Hall in Porgress
2 Hall in progress
3 Work in progress |
No Image |
| |||||||||||||||||||
1301 (OG) |
190446-Least developed districts uplift programme (Kolai Palas, Battagram, Tank, Kohistan Upper, Shangla, Buner, Chitral (Upper & Lower) and Hangu. |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 7.929 | 0 | 0 | 2.91 | 2.91 | 2.503 | 2.503 | 7.929 | - |
32% February - 2021 |
03 units - all in progress
1 Hall in Porgress
2 Hall in progress
3 Work in progress |
No Image |
| |||||||||||||||||||
1301 (OG) |
130510-Feasibility Study, Detailed Designing and Supervision of various roads of C&W Khyber Pakhtunkhwa. |
Provincial |
- | - | - | 26-12-13 | - | 100 | 2.473 | 44.422 | 11.105 | 0 | 0 | 2.473 | 0 | - |
- December - 2017 |
PC-II approved. |
No Image |
1301 (OG) |
130510-Feasibility Study, Detailed Designing and Supervision of various roads of C&W Khyber Pakhtunkhwa. |
Provincial |
- | - | - | 26-12-13 | - | 100 | 2.473 | 44.422 | 44.422 | 0 | 0 | 2.473 | 0 | - |
- September - 2017 |
PC-II approved. |
No Image |
1301 (OG) |
130510-Feasibility Study, Detailed Designing and Supervision of various roads of C&W Khyber Pakhtunkhwa. |
Provincial |
- | - | - | 26-12-13 | - | 100 | 2.473 | 44.422 | 44.422 | 0 | 0 | 2.473 | 0 | - |
- August - 2017 |
PC-II approved. |
No Image |
1301 (OG) |
130510-Feasibility Study, Detailed Designing and Supervision of various roads of C&W Khyber Pakhtunkhwa. |
Provincial |
- | - | - | 26-12-13 | - | 100 | 2.473 | 44.422 | 44.422 | 0 | 0 | 2.473 | 0 | - |
- July - 2017 |
PC-II approved. |
No Image |
1301 (OG) |
190446-Least developed districts uplift programme (Kolai Palas, Battagram, Tank, Kohistan Upper, Shangla, Buner, Chitral (Upper & Lower) and Hangu. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 3000 | 1597.5 | 773 | 773 | 0 | 0 | 1597.5 | 0 | - |
- December - 2020 |
No Image | |
1301 (OG) |
190446-Least developed districts uplift programme (Kolai Palas, Battagram, Tank, Kohistan Upper, Shangla, Buner, Chitral (Upper & Lower) and Hangu. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 3000 | 1597.5 | 773 | 773 | 0 | 0 | 1597.5 | 0 | - |
- December - 2020 |
No Image | |
1301 (OG) |
130510-Feasibility Study, Detailed Designing and Supervision of various roads of C&W Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 2.473 | 44.422 | 44.422 | 33.317 | 0 | 2.473 | 0 | - |
- November - 2017 |
PC-II approved. |
No Image |
1301 (OG) |
130510-Feasibility Study, Detailed Designing and Supervision of various roads of C&W Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 2.473 | 44.422 | 44.422 | 0 | 0 | 2.473 | 0 | - |
- October - 2017 |
PC-II approved. |
No Image |
1301 (OG) |
190446-Least developed districts uplift programme (Kolai Palas, Battagram, Tank, Kohistan Upper, Shangla, Buner, Chitral (Upper & Lower) and Hangu. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 3000 | 1597.5 | 773 | 773 | 0 | 0 | 1597.5 | 0 | - |
- October - 2020 |
No Image | |
1301 (OG) |
190446-Least developed districts uplift programme (Kolai Palas, Battagram, Tank, Kohistan Upper, Shangla, Buner, Chitral (Upper & Lower) and Hangu. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 3000 | 1597.5 | 773 | 773 | 0 | 0 | 1597.5 | 0 | - |
- September - 2020 |
No Image | |
1301 (OG) |
190446-Least developed districts uplift programme (Kolai Palas, Battagram, Tank, Kohistan Upper, Shangla, Buner, Chitral (Upper & Lower) and Hangu. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 3000 | 1597.5 | 773 | 773 | 0 | 0 | 1597.5 | 0 | - |
- August - 2020 |
No Image | |
1301 (OG) |
190446-Least developed districts uplift programme (Kolai Palas, Battagram, Tank, Kohistan Upper, Shangla, Buner, Chitral (Upper & Lower) and Hangu. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 3000 | 1597.5 | 773 | 0 | 0 | 0 | 1597.5 | 0 |
July - 2020 |
No Image | ||
1301 (OG) |
130510-Feasibility Study, Detailed Designing and Supervision of various roads of C&W Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 2.473 | 44.422 | 11.105 | 0 | 0 | 2.473 | 0 | - |
- June - 2018 |
PC-II approved. |
No Image |
1301 (OG) |
130510-Feasibility Study, Detailed Designing and Supervision of various roads of C&W Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 2.473 | 44.422 | 11.105 | 0 | 0 | 2.473 | 0 | - |
- May - 2018 |
PC-II approved. |
No Image |
1301 (OG) |
190446-Least developed districts uplift programme (Kolai Palas, Battagram, Tank, Kohistan Upper, Shangla, Buner, Chitral (Upper & Lower) and Hangu. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 3000 | 1597.5 | 773 | 773 | 0 | 0 | 1597.5 | 0 | - |
- May - 2021 |
No Image | |
1301 (OG) |
130510-Feasibility Study, Detailed Designing and Supervision of various roads of C&W Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 2.473 | 44.422 | 11.105 | 0 | 0 | 2.473 | 0 | - |
- April - 2018 |
PC-II approved. |
No Image |
1301 (OG) |
190446-Least developed districts uplift programme (Kolai Palas, Battagram, Tank, Kohistan Upper, Shangla, Buner, Chitral (Upper & Lower) and Hangu. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 3000 | 1597.5 | 773 | 773 | 0 | 0 | 1597.5 | 0 | - |
- April - 2021 |
No Image | |
1301 (OG) |
130510-Feasibility Study, Detailed Designing and Supervision of various roads of C&W Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 2.473 | 44.422 | 11.105 | 0 | 0 | 2.473 | 0 | - |
- March - 2018 |
PC-II approved. |
No Image |
1301 (OG) |
190446-Least developed districts uplift programme (Kolai Palas, Battagram, Tank, Kohistan Upper, Shangla, Buner, Chitral (Upper & Lower) and Hangu. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 3000 | 1597.5 | 773 | 773 | 0 | 0 | 1597.5 | 0 | - |
- March - 2021 |
No Image | |
1301 (OG) |
130510-Feasibility Study, Detailed Designing and Supervision of various roads of C&W Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 2.473 | 44.422 | 11.105 | 0 | 0 | 2.473 | 0 | - |
- February - 2018 |
PC-II approved. |
No Image |
1301 (OG) |
190446-Least developed districts uplift programme (Kolai Palas, Battagram, Tank, Kohistan Upper, Shangla, Buner, Chitral (Upper & Lower) and Hangu. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 3000 | 1597.5 | 773 | 773 | 0 | 0 | 1597.5 | 0 | - |
- February - 2021 |
No Image | |
1301 (OG) |
130510-Feasibility Study, Detailed Designing and Supervision of various roads of C&W Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 2.473 | 44.422 | 11.105 | 0 | 0 | 2.473 | 0 | - |
- January - 2018 |
PC-II approved. |
No Image |
1301 (OG) |
190446-Least developed districts uplift programme (Kolai Palas, Battagram, Tank, Kohistan Upper, Shangla, Buner, Chitral (Upper & Lower) and Hangu. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 3000 | 1597.5 | 773 | 773 | 0 | 0 | 1597.5 | 0 | - |
- January - 2021 |
No Image | |