Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1294 (New) |
160249-Provincial Roads Rehabilitation Project "Under PKHA Portfolio" (ADB Assisted). |
Peshawar PKHA |
- | - | - | 06-10-17 | - | 14567.928 | 0 | 5240.75 | 5240.75 | 0 | 0 | 0 | 9327.178 | 36% |
- December - 2017 |
Approved. Under process with ADB. Meeting with ADB held on 07/12/2016 and finalized portfolio. |
No Image |
1294 (New) |
160249-Provincial Roads Rehabilitation Project "Under PKHA Portfolio" (ADB Assisted). |
Peshawar PKHA |
- | - | - | 06-10-17 | - | 2535.072 | 0 | 72 | 72 | 0 | 0 | 0 | 2463.072 | 3% |
- December - 2017 |
Approved. Under process with ADB. Meeting with ADB held on 07/12/2016 and finalized portfolio. |
No Image |
1294 (New) |
160249-Provincial Roads Rehabilitation Project "Under PKHA Portfolio" (ADB Assisted). |
Peshawar PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2535.072 | 0 | 72 | 72 | 0 | 0 | 0 | 2463.072 | 3% |
- November - 2017 |
Approved. Under process with ADB. Meeting with ADB held on 07/12/2016 and finalized portfolio. |
No Image |
1294 (New) |
160249-Provincial Roads Rehabilitation Project "Under PKHA Portfolio" (ADB Assisted). |
Peshawar PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 14567.928 | 0 | 5240.75 | 5240.75 | 0 | 0 | 0 | 9327.178 | 36% |
- November - 2017 |
Approved. Under process with ADB. Meeting with ADB held on 07/12/2016 and finalized portfolio. |
No Image |
1294 (New) |
160249-Provincial Roads Rehabilitation Project "Under PKHA Portfolio" (ADB Assisted). |
Peshawar PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 3354.081 | 0 | 72 | 72 | 0 | 0 | 0 | 0 | - |
- October - 2017 |
Under process with ADB. Meeting with ADB held on 07/12/2016 and finalized portfolio. |
No Image |
1294 (New) |
160249-Provincial Roads Rehabilitation Project "Under PKHA Portfolio" (ADB Assisted). |
Peshawar PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 20963 | 0 | 5240.75 | 5240.75 | 0 | 0 | 0 | 0 | - |
- October - 2017 |
Under process with ADB. Meeting with ADB held on 07/12/2016 and finalized portfolio. |
No Image |
1294 (New) |
160249-Provincial Roads Rehabilitation Project "Under PKHA Portfolio" (ADB Assisted). |
Peshawar PKHA |
- | - | - | - | - | 3354.081 | 0 | 72 | 72 | 0 | 0 | 0 | 0 | - |
- September - 2017 |
Under process with ADB. Meeting with ADB held on 07/12/2016 and finalized portfolio. |
No Image |
1294 (New) |
160249-Provincial Roads Rehabilitation Project "Under PKHA Portfolio" (ADB Assisted). |
Peshawar PKHA |
- | - | - | - | - | 20963 | 0 | 5240.75 | 5240.75 | 0 | 0 | 0 | 0 | - |
- September - 2017 |
Under process with ADB. Meeting with ADB held on 07/12/2016 and finalized portfolio. |
No Image |
1294 (New) |
160249-Provincial Roads Rehabilitation Project "Under PKHA Portfolio" (ADB Assisted). |
Peshawar PKHA |
- | - | - | - | - | 3354.081 | 0 | 72 | 72 | 0 | 0 | 0 | 0 | - |
- August - 2017 |
Under process with ADB. Meeting with ADB held on 07/12/2016 and finalized portfolio. |
No Image |
1294 (New) |
160249-Provincial Roads Rehabilitation Project "Under PKHA Portfolio" (ADB Assisted). |
Peshawar PKHA |
- | - | - | - | - | 20963 | 0 | 5240.75 | 5240.75 | 0 | 0 | 0 | 0 | - |
- August - 2017 |
Under process with ADB. Meeting with ADB held on 07/12/2016 and finalized portfolio. |
No Image |
1294 (New) |
160249-Provincial Roads Rehabilitation Project "Under PKHA Portfolio" (ADB Assisted). |
Peshawar PKHA |
- | - | - | - | - | 3354.081 | 0 | 72 | 72 | 0 | 0 | 0 | 0 | - |
- July - 2017 |
Under process with ADB. Meeting with ADB held on 07/12/2016 and finalized portfolio. |
No Image |
1294 (New) |
160249-Provincial Roads Rehabilitation Project "Under PKHA Portfolio" (ADB Assisted). |
Peshawar PKHA |
- | - | - | - | - | 20963 | 0 | 5240.75 | 5240.75 | 0 | 0 | 0 | 0 | - |
- July - 2017 |
Under process with ADB. Meeting with ADB held on 07/12/2016 and finalized portfolio. |
No Image |
1294 (New) |
160249-Provincial Roads Rehabilitation Project "Under PKHA Portfolio" (ADB Assisted). |
Peshawar PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 14567.928 | 0 | 5240 | 5240 | 0 | 0 | 0 | 9327.928 | 36% |
- June - 2018 |
Approved. Under process with ADB. Meeting with ADB held on 07/12/2016 and finalized portfolio. PC-I/DCE for Rs.1045.2 m submitted to Chief Infra P&D Deptt on 20/03/2018. |
No Image |
1294 (New) |
160249-Provincial Roads Rehabilitation Project "Under PKHA Portfolio" (ADB Assisted). |
Peshawar PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2535.072 | 0 | 72 | 14.722 | 14.722 | 14.722 | 14.722 | 2463.072 | 3% |
1% June - 2018 |
Approved. Under process with ADB. Meeting with ADB held on 07/12/2016 and finalized portfolio. PC-I/DCE for Rs.1045.2 m submitted to Chief Infra P&D Deptt on 20/03/2018. |
No Image |
1294 (New) |
160249-Provincial Roads Rehabilitation Project "Under PKHA Portfolio" (ADB Assisted). |
Peshawar PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 14567.928 | 0 | 5240 | 5240 | 0 | 0 | 0 | 9327.928 | 36% |
- May - 2018 |
Approved. Under process with ADB. Meeting with ADB held on 07/12/2016 and finalized portfolio. PC-I/DCE for Rs.1045.2 m submitted to Chief Infra P&D Deptt on 20/03/2018. |
No Image |
1294 (New) |
160249-Provincial Roads Rehabilitation Project "Under PKHA Portfolio" (ADB Assisted). |
Peshawar PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2535.072 | 0 | 72 | 72 | 18 | 18 | 18 | 2463.072 | 3% |
1% May - 2018 |
Approved. Under process with ADB. Meeting with ADB held on 07/12/2016 and finalized portfolio. PC-I/DCE for Rs.1045.2 m submitted to Chief Infra P&D Deptt on 20/03/2018. |
No Image |
1294 (New) |
160249-Provincial Roads Rehabilitation Project "Under PKHA Portfolio" (ADB Assisted). |
Peshawar PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 14567.928 | 0 | 5240 | 5240 | 0 | 0 | 0 | 9327.928 | 36% |
- April - 2018 |
Approved. Under process with ADB. Meeting with ADB held on 07/12/2016 and finalized portfolio. PC-I/DCE for Rs.1045.2 m submitted to Chief Infra P&D Deptt on 20/03/2018. |
No Image |
1294 (New) |
160249-Provincial Roads Rehabilitation Project "Under PKHA Portfolio" (ADB Assisted). |
Peshawar PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2535.072 | 0 | 72 | 72 | 18 | 18 | 18 | 2463.072 | 3% |
1% April - 2018 |
Approved. Under process with ADB. Meeting with ADB held on 07/12/2016 and finalized portfolio. PC-I/DCE for Rs.1045.2 m submitted to Chief Infra P&D Deptt on 20/03/2018. |
No Image |
1294 (New) |
160249-Provincial Roads Rehabilitation Project "Under PKHA Portfolio" (ADB Assisted). |
Peshawar PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 14567.928 | 0 | 5240.75 | 5240.75 | 0 | 0 | 0 | 9327.178 | 36% |
- March - 2018 |
Approved. Under process with ADB. Meeting with ADB held on 07/12/2016 and finalized portfolio. PC-I/DCE for Rs.1045.2 m submitted to Chief Infra P&D Deptt on 20/03/2018. |
No Image |
1294 (New) |
160249-Provincial Roads Rehabilitation Project "Under PKHA Portfolio" (ADB Assisted). |
Peshawar PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2535.072 | 0 | 72 | 72 | 0 | 0 | 0 | 2463.072 | 3% |
- March - 2018 |
Approved. Under process with ADB. Meeting with ADB held on 07/12/2016 and finalized portfolio. PC-I/DCE for Rs.1045.2 m submitted to Chief Infra P&D Deptt on 20/03/2018. |
No Image |
1294 (New) |
160249-Provincial Roads Rehabilitation Project "Under PKHA Portfolio" (ADB Assisted). |
Peshawar PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 14567.928 | 0 | 5240.75 | 5240.75 | 0 | 0 | 0 | 9327.178 | 36% |
- February - 2018 |
Approved. Under process with ADB. Meeting with ADB held on 07/12/2016 and finalized portfolio. |
No Image |
1294 (New) |
160249-Provincial Roads Rehabilitation Project "Under PKHA Portfolio" (ADB Assisted). |
Peshawar PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2535.072 | 0 | 72 | 72 | 0 | 0 | 0 | 2463.072 | 3% |
- February - 2018 |
Approved. Under process with ADB. Meeting with ADB held on 07/12/2016 and finalized portfolio. |
No Image |
1294 (New) |
160249-Provincial Roads Rehabilitation Project "Under PKHA Portfolio" (ADB Assisted). |
Peshawar PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 14567.928 | 0 | 5240.75 | 5240.75 | 0 | 0 | 0 | 9327.178 | 36% |
- January - 2018 |
Approved. Under process with ADB. Meeting with ADB held on 07/12/2016 and finalized portfolio. |
No Image |
1294 (New) |
160249-Provincial Roads Rehabilitation Project "Under PKHA Portfolio" (ADB Assisted). |
Peshawar PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2535.072 | 0 | 72 | 72 | 0 | 0 | 0 | 2463.072 | 3% |
- January - 2018 |
Approved. Under process with ADB. Meeting with ADB held on 07/12/2016 and finalized portfolio. |
No Image |
1294 (OG) |
170422-KP Reconstruction Programme (KPRP) (USAID Assisted) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0.001 | 0 | 0.001 | 0.001 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
No Image | |
1294 (OG) |
170422-KP Reconstruction Programme (KPRP) (USAID Assisted) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0.001 | 0 | 0.001 | 0.001 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
No Image | |
1294 (OG) |
170422-KP Reconstruction Programme (KPRP) (USAID Assisted) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0.001 | 0 | 0.001 | 0.001 | 0 | 0 | 0 | 0 | - |
- October - 2020 |
No Image | |
1294 (OG) |
170422-KP Reconstruction Programme (KPRP) (USAID Assisted) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0.001 | 0 | 0.001 | 0.001 | 0 | 0 | 0 | 0 | - |
- September - 2020 |
No Image | |
1294 (OG) |
170422-KP Reconstruction Programme (KPRP) (USAID Assisted) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0.001 | 0 | 0.001 | 0.001 | 0 | 0 | 0 | 0 | - |
- August - 2020 |
No Image | |
1294 (OG) |
170422-KP Reconstruction Programme (KPRP) (USAID Assisted) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0.001 | 0 | 0.001 | 0 | 0 | 0 | 0 | 0 | - |
- July - 2020 |
No Image | |
1294 (OG) |
170422-KP Reconstruction Programme (KPRP) (USAID Assisted) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0.001 | 0 | 0.001 | 0.001 | 0 | 0 | 0 | 0 | - |
- May - 2021 |
No Image | |
1294 (OG) |
170422-KP Reconstruction Programme (KPRP) (USAID Assisted) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0.001 | 0 | 0.001 | 0.001 | 0 | 0 | 0 | 0 | - |
- April - 2021 |
No Image | |
1294 (OG) |
170422-KP Reconstruction Programme (KPRP) (USAID Assisted) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0.001 | 0 | 0.001 | 0.001 | 0 | 0 | 0 | 0 | - |
- March - 2021 |
No Image | |
1294 (OG) |
170422-KP Reconstruction Programme (KPRP) (USAID Assisted) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0.001 | 0 | 0.001 | 0.001 | 0 | 0 | 0 | 0 | - |
- February - 2021 |
No Image | |
1294 (OG) |
170422-KP Reconstruction Programme (KPRP) (USAID Assisted) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0.001 | 0 | 0.001 | 0.001 | 0 | 0 | 0 | 0 | - |
- January - 2021 |
No Image | |
Pages : 1 |