Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2021, January - 2018, February - 2021, February - 2018, March - 2021, March - 2018, April - 2021, April - 2018, May - 2021, May - 2018, June - 2018, July - 2017, July - 2020, August - 2017, August - 2020, September - 2017, September - 2020, October - 2017, October - 2020, November - 2017, December - 2020, December - 2017,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1293
(New)
170629-Widening & Improvement of Tarnawa Kohala Bala Road (35 Km) District Haripur.
Haripur
PKHA
- - - - Line Deptt 3100 0 20 20 0 0 0 0 - -
December - 2017
PC-II for Rs.15.500 m approved in DDWP on 19/06/2017 for conducting feasibility study and detailed engineering design. Dce submitted for Rs. 3384 M to PDWP
No Image
1293
(New)
170629-Widening & Improvement of Tarnawa Kohala Bala Road (35 Km) District Haripur.
Haripur
PKHA
30-11--1 30-11--1 - 30-11--1 Line Deptt 3100 0 20 20 0 0 0 0 - -
November - 2017
PC-II for Rs.15.500 m approved in DDWP on 19/06/2017 for conducting feasibility study and detailed engineering design. Consultant mobilized.
No Image
1293
(New)
170629-Widening & Improvement of Tarnawa Kohala Bala Road (35 Km) District Haripur.
Haripur
PKHA
30-11--1 30-11--1 - 30-11--1 Line Deptt 3100 0 20 20 0 0 0 0 - -
October - 2017
PC-II for Rs.15.500 m approved in DDWP on 19/06/2017 for conducting feasibility study and detailed engineering design. Consultant mobilized.
No Image
1293
(New)
170629-Widening & Improvement of Tarnawa Kohala Bala Road (35 Km) District Haripur.
Haripur
PKHA
- - - - Line Deptt 3100 0 20 20 0 0 0 0 - -
September - 2017
PC-II for Rs.15.500 m approved in DDWP on 19/06/2017 for conducting feasibility study and detailed engineering design. Consultant mobilized.
No Image
1293
(New)
170629-Widening & Improvement of Tarnawa Kohala Bala Road (35 Km) District Haripur.
Haripur
PKHA
- - - - Line Deptt 3100 0 20 20 0 0 0 0 - -
August - 2017
PC-II for Rs.15.500 m approved in DDWP on 19/06/2017 for conducting feasibility study and detailed engineering design. Consultant mobilized.
No Image
1293
(New)
170629-Widening & Improvement of Tarnawa Kohala Bala Road (35 Km) District Haripur.
Haripur
PKHA
- - - - Line Deptt 3100 0 20 20 0 0 0 0 - -
July - 2017
PC-II for Rs.15.500 m approved in DDWP on 19/06/2017 for conducting feasibility study and detailed engineering design.
No Image
1293
(New)
170629-Widening & Improvement of Tarnawa Kohala Bala Road (35 Km) District Haripur.
Haripur
PKHA
30-11--1 30-11--1 - 30-11--1 Line Deptt 3100 0 20 0 0 0 0 0 - -
June - 2018
PC-II for Rs.15.500 m approved in DDWP on 19/06/2017 for conducting feasibility study and detailed engineering design. DCE re-submitted with the reduced cost of Rs.2100 m.
No Image
1293
(New)
170629-Widening & Improvement of Tarnawa Kohala Bala Road (35 Km) District Haripur.
Haripur
PKHA
30-11--1 30-11--1 - 30-11--1 Line Deptt 3100 0 20 0 0 0 0 0 - -
May - 2018
PC-II for Rs.15.500 m approved in DDWP on 19/06/2017 for conducting feasibility study and detailed engineering design. DCE re-submitted with the reduced cost of Rs.2100 m.
No Image
1293
(New)
170629-Widening & Improvement of Tarnawa Kohala Bala Road (35 Km) District Haripur.
Haripur
PKHA
30-11--1 30-11--1 - 30-11--1 Line Deptt 3100 0 20 0 0 0 0 0 - -
April - 2018
PC-II for Rs.15.500 m approved in DDWP on 19/06/2017 for conducting feasibility study and detailed engineering design. DCE re-submitted with the reduced cost of RS. 2100 M
No Image
1293
(New)
170629-Widening & Improvement of Tarnawa Kohala Bala Road (35 Km) District Haripur.
Haripur
PKHA
30-11--1 30-11--1 - 30-11--1 Line Deptt 3100 0 20 75 75 75 75 0 - -
March - 2018
PC-II for Rs.15.500 m approved in DDWP on 19/06/2017 for conducting feasibility study and detailed engineering design. DCE re-submitted with the reduced cost of RS. 2100 M
No Image
1293
(New)
170629-Widening & Improvement of Tarnawa Kohala Bala Road (35 Km) District Haripur.
Haripur
PKHA
30-11--1 30-11--1 - 30-11--1 Line Deptt 3100 0 20 75 75 75 75 0 - -
February - 2018
PC-II for Rs.15.500 m approved in DDWP on 19/06/2017 for conducting feasibility study and detailed engineering design. DCE submitted for Rs.3384 m to PDWP. Pre-qualification called on 26/02/2018.
No Image
1293
(New)
170629-Widening & Improvement of Tarnawa Kohala Bala Road (35 Km) District Haripur.
Haripur
PKHA
30-11--1 30-11--1 - 30-11--1 Line Deptt 3100 0 20 20 0 0 0 0 - -
January - 2018
PC-II for Rs.15.500 m approved in DDWP on 19/06/2017 for conducting feasibility study and detailed engineering design. DCE submitted for Rs.3384 m to PDWP. Pre-qualification calle on 26/02/2018.
No Image
1293
(OG)
170291-Khyber Pakhtunkhwa Stunting Prevention and Rehabilitation Integrated Nutrition Gain (KP SPRING Project) (SDGs) Cost Rs. 2217.851 (Local=757.110 Foreign=1460.741)
Provincial
30-11--1 30-11--1 - 30-11--1 - 757.11 64 0 0 0 0 64 0 - -
December - 2020
No Image
1293
(OG)
170291-Khyber Pakhtunkhwa Stunting Prevention and Rehabilitation Integrated Nutrition Gain (KP SPRING Project) (SDGs) Cost Rs. 2217.851 (Local=757.110 Foreign=1460.741)
Provincial
30-11--1 30-11--1 - 30-11--1 - 757.11 64 0 0 0 0 64 0 - -
December - 2020
No Image
1293
(OG)
170291-Khyber Pakhtunkhwa Stunting Prevention and Rehabilitation Integrated Nutrition Gain (KP SPRING Project) (SDGs) Cost Rs. 2217.851 (Local=757.110 Foreign=1460.741)
Provincial
30-11--1 30-11--1 - 30-11--1 - 757.11 64 0 0 0 0 64 0 - -
October - 2020
No Image
1293
(OG)
170291-Khyber Pakhtunkhwa Stunting Prevention and Rehabilitation Integrated Nutrition Gain (KP SPRING Project) (SDGs) Cost Rs. 2217.851 (Local=757.110 Foreign=1460.741)
Provincial
30-11--1 30-11--1 - 30-11--1 - 757.11 64 0 0 0 0 64 0 - -
September - 2020
No Image
1293
(OG)
170291-Khyber Pakhtunkhwa Stunting Prevention and Rehabilitation Integrated Nutrition Gain (KP SPRING Project) (SDGs) Cost Rs. 2217.851 (Local=757.110 Foreign=1460.741)
Provincial
30-11--1 30-11--1 - 30-11--1 - 757.11 64 0 0 0 0 64 0 - -
August - 2020
No Image
1293
(OG)
170291-Khyber Pakhtunkhwa Stunting Prevention and Rehabilitation Integrated Nutrition Gain (KP SPRING Project) (SDGs) Cost Rs. 2217.851 (Local=757.110 Foreign=1460.741)
Provincial
30-11--1 30-11--1 - 30-11--1 - 757.11 64 0 0 0 0 64 0 -
July - 2020
No Image
1293
(OG)
170291-Khyber Pakhtunkhwa Stunting Prevention and Rehabilitation Integrated Nutrition Gain (KP SPRING Project) (SDGs) Cost Rs. 2217.851 (Local=757.110 Foreign=1460.741)
Provincial
30-11--1 30-11--1 - 30-11--1 - 757.11 64 0 0 0 0 64 0 - -
May - 2021
No Image
1293
(OG)
170291-Khyber Pakhtunkhwa Stunting Prevention and Rehabilitation Integrated Nutrition Gain (KP SPRING Project) (SDGs) Cost Rs. 2217.851 (Local=757.110 Foreign=1460.741)
Provincial
30-11--1 30-11--1 - 30-11--1 - 757.11 64 0 0 0 0 64 0 - -
April - 2021
No Image
1293
(OG)
170291-Khyber Pakhtunkhwa Stunting Prevention and Rehabilitation Integrated Nutrition Gain (KP SPRING Project) (SDGs) Cost Rs. 2217.851 (Local=757.110 Foreign=1460.741)
Provincial
30-11--1 30-11--1 - 30-11--1 - 757.11 64 0 0 0 0 64 0 - -
March - 2021
No Image
1293
(OG)
170291-Khyber Pakhtunkhwa Stunting Prevention and Rehabilitation Integrated Nutrition Gain (KP SPRING Project) (SDGs) Cost Rs. 2217.851 (Local=757.110 Foreign=1460.741)
Provincial
30-11--1 30-11--1 - 30-11--1 - 757.11 64 0 0 0 0 64 0 - -
February - 2021
No Image
1293
(OG)
170291-Khyber Pakhtunkhwa Stunting Prevention and Rehabilitation Integrated Nutrition Gain (KP SPRING Project) (SDGs) Cost Rs. 2217.851 (Local=757.110 Foreign=1460.741)
Provincial
30-11--1 30-11--1 - 30-11--1 - 757.11 64 0 0 0 0 64 0 - -
January - 2021
No Image
Pages : 1