Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1282 (OG) |
140624-Dualization of Sherkot Hangu Section of Provincial Highway S-7 (24 Km), District Kohat and Hangu. |
Hangu PKHA |
21-10-15 | - | - | 25-03-15 | - | 2759.858 | 509.99 | 100 | 261.638 | 236.638 | 236.638 | 746.628 | 2149.868 | 22% |
27% December - 2017 |
Pack-1 (6 Km) - embankment, in progress Km-1, 3, 4, 5, clearing/grubbing and NGC 90% completed. Pack-2 (6 Km) - Km-9, 10, 11 hillside cutting, RW in progress. Pack-3 (6 Km) - embankment in progress Km-16, 17, clearing/grubbing and NGC 80% completed. Pack-4 (6 Km) - clearing/grubbing Km-19, 20, embankment in progress. Pack-5 (4 bridges) - contractor machinery and staff mobilized on site. Design awaited for bridge pile from design consultant. |
No Image |
1282 (OG) |
140624-Dualization of Sherkot Hangu Section of Provincial Highway S-7 (24 Km), District Kohat and Hangu. |
Hangu PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2759.858 | 509.99 | 100 | 276.138 | 35 | 35 | 544.99 | 2149.868 | 22% |
20% November - 2017 |
Pack-1 (6 Km) - embankment, in progress Km-1, 3, 4, 5, clearing/grubbing and NGC 90% completed. Pack-2 (6 Km) - Km-9, 10, 11 hillside cutting, RW in progress. Pack-3 (6 Km) - embankment in progress Km-16, 17, clearing/grubbing and NGC 80% completed. Pack-4 (6 Km) - clearing/grubbing Km-19, 20, embankment in progress. Pack-5 (4 bridges) - contractor machinery and staff mobilized on site. Design awaited for bridge pile from design consultant. |
No Image |
1282 (OG) |
140624-Dualization of Sherkot Hangu Section of Provincial Highway S-7 (24 Km), District Kohat and Hangu. |
Hangu PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2759.858 | 509.99 | 100 | 100 | 35.5 | 35 | 544.99 | 2149.868 | 22% |
20% October - 2017 |
Pack-1 (6 Km) - embankment, in progress Km-1, 3, 4, 5, clearing/grubbing and NGC 90% completed. Pack-2 (6 Km) - Km-9, 10, 11 hillside cutting, RW in progress. Pack-3 (6 Km) - embankment in progress Km-16, 17, clearing/grubbing and NGC 80% completed. Pack-4 (6 Km) - clearing/grubbing Km-19, 20, embankment in progress. Pack-5 (4 bridges) - contractor machinery and staff mobilized on site. Design awaited for bridge pile from design consultant. |
No Image |
1282 (OG) |
140624-Dualization of Sherkot Hangu Section of Provincial Highway S-7 (24 Km), District Kohat and Hangu. |
Hangu PKHA |
21-10-15 | - | - | 25-03-15 | - | 2759.858 | 509.99 | 100 | 100 | 35.5 | 35 | 544.99 | 2149.868 | 22% |
20% September - 2017 |
Pack-1 (6 Km) - embankment, in progress Km-1, 3, 4, 5, clearing/grubbing and NGC 90% completed. Pack-2 (6 Km) - Km-9, 10, 11 hillside cutting, RW in progress. Pack-3 (6 Km) - embankment in progress Km-16, 17, clearing/grubbing and NGC 80% completed. Pack-4 (6 Km) - clearing/grubbing Km-19, 20, embankment in progress. Pack-5 (4 bridges) - contractor machinery and staff mobilized on site. Design awaited for bridge pile from design consultant. |
No Image |
1282 (OG) |
140624-Dualization of Sherkot Hangu Section of Provincial Highway S-7 (24 Km), District Kohat and Hangu. |
Hangu PKHA |
21-10-15 | - | - | 25-03-15 | - | 2759.858 | 509.99 | 100 | 100 | 35.5 | 35 | 544.99 | 2149.868 | 22% |
20% August - 2017 |
Pack-1 (6 Km) - embankment, in progress Km-1, 3, 4, 5, clearing/grubbing and NGC 90% completed. Pack-2 (6 Km) - Km-9, 10, 11 hillside cutting, RW in progress. Pack-3 (6 Km) - embankment in progress Km-16, 17, clearing/grubbing and NGC 80% completed. Pack-4 (6 Km) - clearing/grubbing Km-19, 20, embankment in progress. Pack-5 (4 bridges) - contractor machinery and staff mobilized on site. Design awaited for bridge pile from design consultant. |
No Image |
1282 (OG) |
140624-Dualization of Sherkot Hangu Section of Provincial Highway S-7 (24 Km), District Kohat and Hangu. |
Hangu PKHA |
21-10-15 | - | - | 25-03-15 | - | 2759.858 | 509.99 | 100 | 100 | 35.5 | 0 | 509.99 | 2149.868 | 22% |
18% July - 2017 |
Pack-1 (6 Km) - embankment, in progress Km-1, 3, 4, 5, clearing/grubbing and NGC 90% completed. Pack-2 (6 Km) - Km-9, 10, 11 hillside cutting, RW in progress. Pack-3 (6 Km) - embankment in progress Km-16, 17, clearing/grubbing and NGC 80% completed. Pack-4 (6 Km) - clearing/grubbing Km-19, 20, embankment in progress. Pack-5 (4 bridges) - contractor machinery and staff mobilized on site. Design awaited for bridge pile from design consultant. |
No Image |
1282 (OG) |
140624-Dualization of Sherkot Hangu Section of Provincial Highway S-7 (24 Km), District Kohat and Hangu. |
Hangu PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2759.858 | 519.93 | 100 | 261.638 | 261.638 | 261.638 | 781.568 | 2139.928 | 22% |
28% June - 2018 |
Pack-1 (6 Km) - embankment, in progress Km-1, 3, 4, 5, clearing/grubbing and NGC 90% completed. Pack-2 (6 Km) - Km-9, 10, 11 hillside cutting, RW in progress. Pack-3 (6 Km) - embankment in progress Km-16, 17, clearing/grubbing and NGC 80% completed. Pack-4 (6 Km) - clearing/grubbing Km-19, 20, embankment in progress. Pack-5 (4 bridges) - contractor machinery and staff mobilized on site. Design awaited for bridge pile from design consultant. |
No Image |
1282 (OG) |
140624-Dualization of Sherkot Hangu Section of Provincial Highway S-7 (24 Km), District Kohat and Hangu. |
Hangu PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2759.858 | 519.93 | 100 | 261.638 | 261.638 | 261.638 | 781.568 | 2139.928 | 22% |
28% May - 2018 |
Pack-1 (6 Km) - embankment, in progress Km-1, 3, 4, 5, clearing/grubbing and NGC 90% completed. Pack-2 (6 Km) - Km-9, 10, 11 hillside cutting, RW in progress. Pack-3 (6 Km) - embankment in progress Km-16, 17, clearing/grubbing and NGC 80% completed. Pack-4 (6 Km) - clearing/grubbing Km-19, 20, embankment in progress. Pack-5 (4 bridges) - contractor machinery and staff mobilized on site. Design awaited for bridge pile from design consultant. |
No Image |
1282 (OG) |
140624-Dualization of Sherkot Hangu Section of Provincial Highway S-7 (24 Km), District Kohat and Hangu. |
Hangu PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2759.858 | 519.93 | 100 | 236.638 | 236.638 | 236.638 | 756.568 | 2139.928 | 22% |
27% April - 2018 |
Pack-1 (6 Km) - embankment, in progress Km-1, 3, 4, 5, clearing/grubbing and NGC 90% completed. Pack-2 (6 Km) - Km-9, 10, 11 hillside cutting, RW in progress. Pack-3 (6 Km) - embankment in progress Km-16, 17, clearing/grubbing and NGC 80% completed. Pack-4 (6 Km) - clearing/grubbing Km-19, 20, embankment in progress. Pack-5 (4 bridges) - contractor machinery and staff mobilized on site. Design awaited for bridge pile from design consultant. |
No Image |
1282 (OG) |
140624-Dualization of Sherkot Hangu Section of Provincial Highway S-7 (24 Km), District Kohat and Hangu. |
Hangu PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2759.858 | 519.93 | 100 | 236.638 | 236.638 | 236.638 | 756.568 | 2139.928 | 22% |
27% March - 2018 |
Pack-1 (6 Km) - embankment, in progress Km-1, 3, 4, 5, clearing/grubbing and NGC 90% completed. Pack-2 (6 Km) - Km-9, 10, 11 hillside cutting, RW in progress. Pack-3 (6 Km) - embankment in progress Km-16, 17, clearing/grubbing and NGC 80% completed. Pack-4 (6 Km) - clearing/grubbing Km-19, 20, embankment in progress. Pack-5 (4 bridges) - contractor machinery and staff mobilized on site. Design awaited for bridge pile from design consultant. |
No Image |
1282 (OG) |
140624-Dualization of Sherkot Hangu Section of Provincial Highway S-7 (24 Km), District Kohat and Hangu. |
Hangu PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2759.858 | 694.3 | 100 | 236.638 | 236.638 | 236.638 | 930.938 | 1965.558 | 29% |
34% February - 2018 |
Pack-1 (6 Km) - embankment, in progress Km-1, 3, 4, 5, clearing/grubbing and NGC 90% completed. Pack-2 (6 Km) - Km-9, 10, 11 hillside cutting, RW in progress. Pack-3 (6 Km) - embankment in progress Km-16, 17, clearing/grubbing and NGC 80% completed. Pack-4 (6 Km) - clearing/grubbing Km-19, 20, embankment in progress. Pack-5 (4 bridges) - contractor machinery and staff mobilized on site. Design awaited for bridge pile from design consultant. |
No Image |
1282 (OG) |
140624-Dualization of Sherkot Hangu Section of Provincial Highway S-7 (24 Km), District Kohat and Hangu. |
Hangu PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2759.858 | 509.99 | 100 | 261.638 | 236.638 | 236.638 | 746.628 | 2149.868 | 22% |
27% January - 2018 |
Pack-1 (6 Km) - embankment, in progress Km-1, 3, 4, 5, clearing/grubbing and NGC 90% completed. Pack-2 (6 Km) - Km-9, 10, 11 hillside cutting, RW in progress. Pack-3 (6 Km) - embankment in progress Km-16, 17, clearing/grubbing and NGC 80% completed. Pack-4 (6 Km) - clearing/grubbing Km-19, 20, embankment in progress. Pack-5 (4 bridges) - contractor machinery and staff mobilized on site. Design awaited for bridge pile from design consultant. |
No Image |
1282 (OG) |
193169-Exploration & Evaluation of Metallic Minerals Occurrences in FATA (A) BOD/26/12/2017 [FDA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 149.29 | 22.044 | 0 | 0 | 0 | 0 | 22.044 | 0 | - |
- December - 2020 |
No Image | |
1282 (OG) |
193169-Exploration & Evaluation of Metallic Minerals Occurrences in FATA (A) BOD/26/12/2017 [FDA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 149.29 | 22.044 | 0 | 0 | 0 | 0 | 22.044 | 0 | - |
- December - 2020 |
No Image | |
1282 (OG) |
193169-Exploration & Evaluation of Metallic Minerals Occurrences in FATA (A) BOD/26/12/2017 [FDA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 149.29 | 22.044 | 0 | 0 | 0 | 0 | 22.044 | 0 | - |
- October - 2020 |
No Image | |
1282 (OG) |
193169-Exploration & Evaluation of Metallic Minerals Occurrences in FATA (A) BOD/26/12/2017 [FDA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 149.29 | 22.044 | 0 | 0 | 0 | 0 | 22.044 | 0 | - |
- September - 2020 |
No Image | |
1282 (OG) |
193169-Exploration & Evaluation of Metallic Minerals Occurrences in FATA (A) BOD/26/12/2017 [FDA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 149.29 | 22.044 | 0 | 0 | 0 | 0 | 22.044 | 0 | - |
- August - 2020 |
No Image | |
1282 (OG) |
193169-Exploration & Evaluation of Metallic Minerals Occurrences in FATA (A) BOD/26/12/2017 [FDA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 149.29 | 22.044 | 0 | 0 | 0 | 0 | 22.044 | 0 | - |
July - 2020 |
No Image | |
1282 (OG) |
193169-Exploration & Evaluation of Metallic Minerals Occurrences in FATA (A) BOD/26/12/2017 [FDA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 149.29 | 22.044 | 0 | 0 | 0 | 0 | 22.044 | 0 | - |
- May - 2021 |
No Image | |
1282 (OG) |
193169-Exploration & Evaluation of Metallic Minerals Occurrences in FATA (A) BOD/26/12/2017 [FDA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 149.29 | 22.044 | 0 | 0 | 0 | 0 | 22.044 | 0 | - |
- April - 2021 |
No Image | |
1282 (OG) |
193169-Exploration & Evaluation of Metallic Minerals Occurrences in FATA (A) BOD/26/12/2017 [FDA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 149.29 | 22.044 | 0 | 0 | 0 | 0 | 22.044 | 0 | - |
- March - 2021 |
No Image | |
1282 (OG) |
193169-Exploration & Evaluation of Metallic Minerals Occurrences in FATA (A) BOD/26/12/2017 [FDA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 149.29 | 22.044 | 0 | 0 | 0 | 0 | 22.044 | 0 | - |
- February - 2021 |
No Image | |
1282 (OG) |
193169-Exploration & Evaluation of Metallic Minerals Occurrences in FATA (A) BOD/26/12/2017 [FDA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 149.29 | 22.044 | 0 | 0 | 0 | 0 | 22.044 | 0 | - |
- January - 2021 |
No Image | |