Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2021, January - 2018, February - 2021, February - 2018, March - 2018, March - 2021, April - 2018, April - 2021, May - 2018, May - 2021, June - 2018, July - 2020, July - 2017, August - 2020, August - 2017, September - 2020, September - 2017, October - 2020, October - 2017, November - 2017, December - 2020, December - 2017,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1281
(OG)
193168-Exploration & Evaluation of Dimension and Decorative Stones in FATA (A) BOD/26/12/2017 [FDA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 109 22.532 0 0 0 0 22.532 0 - -
December - 2020
No Image
1281
(OG)
193168-Exploration & Evaluation of Dimension and Decorative Stones in FATA (A) BOD/26/12/2017 [FDA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 109 22.532 0 0 0 0 22.532 0 - -
December - 2020
No Image
1281
(OG)
193168-Exploration & Evaluation of Dimension and Decorative Stones in FATA (A) BOD/26/12/2017 [FDA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 109 22.532 0 0 0 0 22.532 0 - -
October - 2020
No Image
1281
(OG)
193168-Exploration & Evaluation of Dimension and Decorative Stones in FATA (A) BOD/26/12/2017 [FDA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 109 22.532 0 0 0 0 22.532 0 - -
September - 2020
No Image
1281
(OG)
193168-Exploration & Evaluation of Dimension and Decorative Stones in FATA (A) BOD/26/12/2017 [FDA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 109 22.532 0 0 0 0 22.532 0 - -
August - 2020
No Image
1281
(OG)
193168-Exploration & Evaluation of Dimension and Decorative Stones in FATA (A) BOD/26/12/2017 [FDA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 109 22.532 0 0 0 0 22.532 0 -
July - 2020
No Image
1281
(OG)
193168-Exploration & Evaluation of Dimension and Decorative Stones in FATA (A) BOD/26/12/2017 [FDA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 109 22.532 0 0 0 0 22.532 0 - -
May - 2021
No Image
1281
(OG)
193168-Exploration & Evaluation of Dimension and Decorative Stones in FATA (A) BOD/26/12/2017 [FDA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 109 22.532 0 0 0 0 22.532 0 - -
April - 2021
No Image
1281
(OG)
193168-Exploration & Evaluation of Dimension and Decorative Stones in FATA (A) BOD/26/12/2017 [FDA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 109 22.532 0 0 0 0 22.532 0 - -
March - 2021
No Image
1281
(OG)
193168-Exploration & Evaluation of Dimension and Decorative Stones in FATA (A) BOD/26/12/2017 [FDA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 109 22.532 0 0 0 0 22.532 0 - -
February - 2021
No Image
1281
(OG)
193168-Exploration & Evaluation of Dimension and Decorative Stones in FATA (A) BOD/26/12/2017 [FDA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 109 22.532 0 0 0 0 22.532 0 - -
January - 2021
No Image
1281
(OG)
130198-Establishment of Axle Load Control Regime on Provincial Highways at 5-Stations.
Provincial
PKHA
21-11-15 - - 17-04-14 - 498.16 140.75 20 12.1 7.1 7.1 147.85 337.41 32% 30%
December - 2017
8 weight station as per revised PC-I. Work started at 5 Nos sites. Work order issued for 3 additional sites.
No Image
1281
(OG)
130198-Establishment of Axle Load Control Regime on Provincial Highways at 5-Stations.
Provincial
PKHA
30-11--1 30-11--1 - 30-11--1 - 498.16 140.75 20 17 7.1 7.1 147.85 337.41 32% 30%
November - 2017
8 weight station as per revised PC-I. Work started at 5 Nos sites. Work order issued for 3 additional sites.
No Image
1281
(OG)
130198-Establishment of Axle Load Control Regime on Provincial Highways at 5-Stations.
Provincial
PKHA
30-11--1 30-11--1 - 30-11--1 - 498.16 140.75 20 20 7.1 7.1 147.85 337.41 32% 30%
October - 2017
8 weight station as per revised PC-I. Work started at 5 Nos sites. Work order issued for 3 additional sites.
No Image
1281
(OG)
130198-Establishment of Axle Load Control Regime on Provincial Highways at 5-Stations.
Provincial
PKHA
21-11-15 - - 17-04-14 - 498.16 140.75 20 20 7.1 7.1 147.85 337.41 32% 30%
September - 2017
8 weight station as per revised PC-I. Work started at 5 Nos sites. Work order issued for 3 additional sites.
No Image
1281
(OG)
130198-Establishment of Axle Load Control Regime on Provincial Highways at 5-Stations.
Provincial
PKHA
21-11-15 - - 17-04-14 - 498.16 140.75 20 20 7.1 7.1 147.85 337.41 32% 30%
August - 2017
8 weight station as per revised PC-I. Work started at 5 Nos sites. Work order issued for 3 additional sites.
No Image
1281
(OG)
130198-Establishment of Axle Load Control Regime on Provincial Highways at 5-Stations.
Provincial
PKHA
21-11-15 - - 17-04-14 - 498.16 140.75 20 20 7.1 0 140.75 337.41 32% 28%
July - 2017
8 weight station as per revised PC-I. Work started at 5 Nos sites. Work order issued for 3 additional sites.
No Image
1281
(OG)
130198-Establishment of Axle Load Control Regime on Provincial Highways at 5-Stations.
Provincial
PKHA
30-11--1 30-11--1 - 30-11--1 - 498.16 140.75 20 12.1 12.1 12.1 152.85 337.41 32% 31%
June - 2018
8 weight station as per revised PC-I. Work started at 5 Nos sites. Work order issued for 3 additional sites.
No Image
1281
(OG)
130198-Establishment of Axle Load Control Regime on Provincial Highways at 5-Stations.
Provincial
PKHA
30-11--1 30-11--1 - 30-11--1 - 498.16 140.75 20 20 12.1 12.1 152.85 337.41 32% 31%
May - 2018
8 weight station as per revised PC-I. Work started at 5 Nos sites. Work order issued for 3 additional sites.
No Image
1281
(OG)
130198-Establishment of Axle Load Control Regime on Provincial Highways at 5-Stations.
Provincial
PKHA
30-11--1 30-11--1 - 30-11--1 - 498.16 140.75 20 20 12.1 12.1 152.85 337.41 32% 31%
April - 2018
8 weight station as per revised PC-I. Work started at 5 Nos sites. Work order issued for 3 additional sites.
No Image
1281
(OG)
130198-Establishment of Axle Load Control Regime on Provincial Highways at 5-Stations.
Provincial
PKHA
30-11--1 30-11--1 - 30-11--1 - 498.16 140.75 20 20 7.1 7.1 147.85 337.41 32% 30%
March - 2018
8 weight station as per revised PC-I. Work started at 5 Nos sites. Work order issued for 3 additional sites.
No Image
1281
(OG)
130198-Establishment of Axle Load Control Regime on Provincial Highways at 5-Stations.
Provincial
PKHA
30-11--1 30-11--1 - 30-11--1 - 498.16 140.75 20 20 7.1 7.1 147.85 337.41 32% 30%
February - 2018
8 weight station as per revised PC-I. Work started at 5 Nos sites. Work order issued for 3 additional sites.
No Image
1281
(OG)
130198-Establishment of Axle Load Control Regime on Provincial Highways at 5-Stations.
Provincial
PKHA
30-11--1 30-11--1 - 30-11--1 - 498.16 140.75 20 12.1 7.1 7.1 147.85 337.41 32% 30%
January - 2018
8 weight station as per revised PC-I. Work started at 5 Nos sites. Work order issued for 3 additional sites.
No Image
Pages : 1