Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1277 (OG) |
140619-Widening / Dualization of Muree Chowk - Thandiani Chowk and Nawasher Link Road District Abbottabad. |
Abbottabad PKHA |
29-12-15 | - | - | 07-01-15 | - | 983.904 | 454.5 | 55 | 33.4 | 19.575 | 19.575 | 474.075 | 474.404 | 52% |
48% December - 2017 |
Length 7.1 Km - Pack-1, 2 and 3 - work started. Shifting of utilities in progress. |
No Image |
1277 (OG) |
140619-Widening / Dualization of Muree Chowk - Thandiani Chowk and Nawasher Link Road District Abbottabad. |
Abbottabad PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 983.904 | 454.5 | 55 | 41.3 | 19.525 | 19.525 | 474.025 | 474.404 | 52% |
48% November - 2017 |
Length 7.1 Km - Pack-1, 2 and 3 - work started. Shifting of utilities in progress. |
No Image |
1277 (OG) |
140619-Widening / Dualization of Muree Chowk - Thandiani Chowk and Nawasher Link Road District Abbottabad. |
Abbottabad PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 983.904 | 454.5 | 55 | 55 | 19.525 | 19.525 | 474.025 | 474.404 | 52% |
48% October - 2017 |
Length 7.1 Km - Pack-1, 2 and 3 - work started. Shifting of utilities in progress. |
No Image |
1277 (OG) |
140619-Widening / Dualization of Muree Chowk - Thandiani Chowk and Nawasher Link Road District Abbottabad. |
Abbottabad PKHA |
29-12-15 | - | - | 07-01-15 | - | 983.904 | 454.5 | 55 | 55 | 19.525 | 19.525 | 474.025 | 474.404 | 52% |
48% September - 2017 |
Length 7.1 Km - Pack-1, 2 and 3 - work started. Shifting of utilities in progress. |
No Image |
1277 (OG) |
140619-Widening / Dualization of Muree Chowk - Thandiani Chowk and Nawasher Link Road District Abbottabad. |
Abbottabad PKHA |
29-12-15 | - | - | 07-01-15 | - | 983.904 | 454.5 | 55 | 55 | 19.525 | 19.525 | 474.025 | 474.404 | 52% |
48% August - 2017 |
Length 7.1 Km - Pack-1, 2 and 3 - work started. Shifting of utilities in progress. |
No Image |
1277 (OG) |
140619-Widening / Dualization of Muree Chowk - Thandiani Chowk and Nawasher Link Road District Abbottabad. |
Abbottabad PKHA |
29-12-15 | - | - | 07-01-15 | - | 983.904 | 454.5 | 55 | 55 | 19.525 | 0 | 454.5 | 474.404 | 52% |
46% July - 2017 |
Length 7.1 Km - Pack-1, 2 and 3 - work started. Shifting of utilities in progress. |
No Image |
1277 (OG) |
140619-Widening / Dualization of Muree Chowk - Thandiani Chowk and Nawasher Link Road District Abbottabad. |
Abbottabad PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 983.904 | 472.5 | 55 | 33.4 | 33.4 | 33.4 | 505.9 | 456.404 | 54% |
51% June - 2018 |
Length 7.1 Km - Pack-1, 2 and 3 - work started. Shifting of utilities in progress. |
No Image |
Package-1
Package-2
Package-3 | |||||||||||||||||||
1277 (OG) |
140619-Widening / Dualization of Muree Chowk - Thandiani Chowk and Nawasher Link Road District Abbottabad. |
Abbottabad PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 983.904 | 472.5 | 55 | 55 | 33.4 | 33.4 | 505.9 | 456.404 | 54% |
51% May - 2018 |
Length 7.1 Km - Pack-1, 2 and 3 - work started. Shifting of utilities in progress. |
No Image |
Package-1
Package-2
Package-3 | |||||||||||||||||||
1277 (OG) |
140619-Widening / Dualization of Muree Chowk - Thandiani Chowk and Nawasher Link Road District Abbottabad. |
Abbottabad PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 983.904 | 472.5 | 55 | 55 | 33.4 | 33.4 | 505.9 | 456.404 | 54% |
51% April - 2018 |
Length 7.1 Km - Pack-1, 2 and 3 - work started. Shifting of utilities in progress. |
No Image |
Package-1
Package-2
Package-3 | |||||||||||||||||||
1277 (OG) |
140619-Widening / Dualization of Muree Chowk - Thandiani Chowk and Nawasher Link Road District Abbottabad. |
Abbottabad PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 983.904 | 472.5 | 55 | 55 | 19.525 | 19.525 | 492.025 | 456.404 | 54% |
50% March - 2018 |
Length 7.1 Km - Pack-1, 2 and 3 - work started. Shifting of utilities in progress. |
No Image |
Package-1
Package-2
Package-3 | |||||||||||||||||||
1277 (OG) |
140619-Widening / Dualization of Muree Chowk - Thandiani Chowk and Nawasher Link Road District Abbottabad. |
Abbottabad PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 983.904 | 592.5 | 55 | 55 | 19.525 | 19.525 | 612.025 | 336.404 | 66% |
62% February - 2018 |
Length 7.1 Km - Pack-1, 2 and 3 - work started. Shifting of utilities in progress. |
No Image |
Package-1
Package-2
Package-3 | |||||||||||||||||||
1277 (OG) |
140619-Widening / Dualization of Muree Chowk - Thandiani Chowk and Nawasher Link Road District Abbottabad. |
Abbottabad PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 983.904 | 454.5 | 55 | 33.4 | 19.575 | 19.575 | 474.075 | 474.404 | 52% |
48% January - 2018 |
Length 7.1 Km - Pack-1, 2 and 3 - work started. Shifting of utilities in progress. |
No Image |
Package-1 Package-2 Package-3 | |||||||||||||||||||
1277 (OG) |
193160-Exploration & Development of Copper in N.W.Agency. (A) BOD/12/06/2007 [FDA] |
North Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 172.722 | 146.133 | 0 | 0 | 0 | 0 | 146.133 | 0 | - |
- December - 2020 |
No Image | |
1277 (OG) |
193160-Exploration & Development of Copper in N.W.Agency. (A) BOD/12/06/2007 [FDA] |
North Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 172.722 | 146.133 | 0 | 0 | 0 | 0 | 146.133 | 0 | - |
- December - 2020 |
No Image | |
1277 (OG) |
193160-Exploration & Development of Copper in N.W.Agency. (A) BOD/12/06/2007 [FDA] |
North Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 172.722 | 146.133 | 0 | 0 | 0 | 0 | 146.133 | 0 | - |
- October - 2020 |
No Image | |
1277 (OG) |
193160-Exploration & Development of Copper in N.W.Agency. (A) BOD/12/06/2007 [FDA] |
North Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 172.722 | 146.133 | 0 | 0 | 0 | 0 | 146.133 | 0 | - |
- September - 2020 |
No Image | |
1277 (OG) |
193160-Exploration & Development of Copper in N.W.Agency. (A) BOD/12/06/2007 [FDA] |
North Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 172.722 | 146.133 | 0 | 0 | 0 | 0 | 146.133 | 0 | - |
- August - 2020 |
No Image | |
1277 (OG) |
193160-Exploration & Development of Copper in N.W.Agency. (A) BOD/12/06/2007 [FDA] |
North Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 172.722 | 146.133 | 0 | 0 | 0 | 0 | 146.133 | 0 | - |
- May - 2021 |
No Image | |
1277 (OG) |
193160-Exploration & Development of Copper in N.W.Agency. (A) BOD/12/06/2007 [FDA] |
North Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 172.722 | 146.133 | 0 | 0 | 0 | 0 | 146.133 | 0 | - |
- April - 2021 |
No Image | |
1277 (OG) |
193160-Exploration & Development of Copper in N.W.Agency. (A) BOD/12/06/2007 [FDA] |
North Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 172.722 | 146.133 | 0 | 0 | 0 | 0 | 146.133 | 0 | - |
- March - 2021 |
No Image | |
1277 (OG) |
193160-Exploration & Development of Copper in N.W.Agency. (A) BOD/12/06/2007 [FDA] |
North Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 172.722 | 146.133 | 0 | 0 | 0 | 0 | 146.133 | 0 | - |
- February - 2021 |
No Image | |
1277 (OG) |
193160-Exploration & Development of Copper in N.W.Agency. (A) BOD/12/06/2007 [FDA] |
North Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 172.722 | 146.133 | 0 | 0 | 0 | 0 | 146.133 | 0 | - |
- January - 2021 |
No Image | |
1277 (OG) |
193160-Exploration & Development of Copper in N.W.Agency. (A) BOD/12/06/2007 [FDA] |
North Wazirstan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 172.722 | 146.133 | 0 | 0 | 0 | 0 | 146.133 | 0 | - |
July - 2020 |
No Image | |
Pages : 1 |