Progressive Review for the month(s) of : January - 2018, January - 2021, February - 2018, February - 2021, March - 2018, March - 2021, April - 2018, April - 2021, May - 2018, May - 2021, June - 2018, July - 2017, July - 2020, August - 2017, August - 2020, September - 2017, September - 2020, October - 2017, October - 2020, November - 2017, December - 2017, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1275
(OG)
140829-Improvement of 25 Km leftover portion of Chukiyatan - Barawal - Shahi Road, District Dir Upper.
Dir Upper
PKHA
08-10-15 - - 19-02-15 - 988.52 247.5 70 42.35 14.7 14.7 262.2 671.02 32% 27%
December - 2017
Length 25 Km. Pack-1 - earth work 6.2/8 Km completed. Pack- 2 - earth work 6.2/8 Km completed. Pack-3 and 4 - earth work started.
No Image
1275
(OG)
140829-Improvement of 25 Km leftover portion of Chukiyatan - Barawal - Shahi Road, District Dir Upper.
Dir Upper
PKHA
30-11--1 30-11--1 - 30-11--1 - 988.52 247.5 70 59.85 24.85 24.85 272.35 671.02 32% 28%
November - 2017
Length 25 Km. Pack-1 - earth work 6.2/8 Km completed. Pack- 2 - earth work 6.2/8 Km completed. Pack-3 and 4 - earth work started.
No Image
1275
(OG)
140829-Improvement of 25 Km leftover portion of Chukiyatan - Barawal - Shahi Road, District Dir Upper.
Dir Upper
PKHA
30-11--1 30-11--1 - 30-11--1 - 988.52 247.5 70 70 24.85 24.85 272.35 671.02 32% 28%
October - 2017
Length 25 Km. Pack-1 - earth work 6.2/8 Km completed. Pack- 2 - earth work 6.2/8 Km completed. Pack-3 and 4 - earth work started.
No Image
1275
(OG)
140829-Improvement of 25 Km leftover portion of Chukiyatan - Barawal - Shahi Road, District Dir Upper.
Dir Upper
PKHA
08-10-15 - - 19-02-15 - 988.52 247.5 70 70 24.8 24.8 272.3 671.02 32% 28%
September - 2017
Length 25 Km. Pack-1 - earth work 6.2/8 Km completed. Pack- 2 - earth work 6.2/8 Km completed. Pack-3 and 4 - earth work started.
No Image
1275
(OG)
140829-Improvement of 25 Km leftover portion of Chukiyatan - Barawal - Shahi Road, District Dir Upper.
Dir Upper
PKHA
08-10-15 - - 19-02-15 - 988.52 247.5 70 70 24.85 24.8 272.3 671.02 32% 28%
August - 2017
Length 25 Km. Pack-1 - earth work 6.2/8 Km completed. Pack- 2 - earth work 6.2/8 Km completed. Pack-3 and 4 - earth work started.
No Image
1275
(OG)
140829-Improvement of 25 Km leftover portion of Chukiyatan - Barawal - Shahi Road, District Dir Upper.
Dir Upper
PKHA
08-10-15 - - 19-02-15 - 988.52 247.5 70 70 24.85 0 247.5 671.02 32% 25%
July - 2017
Length 25 Km. Pack-1 - earth work 6.2/8 Km completed. Pack- 2 - earth work 6.2/8 Km completed. Pack-3 and 4 - earth work started.
No Image
1275
(OG)
140829-Improvement of 25 Km leftover portion of Chukiyatan - Barawal - Shahi Road, District Dir Upper.
Dir Upper
PKHA
30-11--1 30-11--1 - 30-11--1 - 988.52 247.5 70 42.35 42.35 42.35 289.85 671.02 32% 29%
June - 2018
Length 25 Km. Pack-1 - earth work 6.2/8 Km completed. Pack- 2 - earth work 6.2/8 Km completed. Pack-3 and 4 - earth work started.
No Image
Package-1 (Barawal Bandi to Jan Bati)
Package-2 (Jan Bati to Shaltalo)
Package-3 (Shaltalo to Marawaro)
Package-4 (Marawaro to Shahi Top)
1275
(OG)
140829-Improvement of 25 Km leftover portion of Chukiyatan - Barawal - Shahi Road, District Dir Upper.
Dir Upper
PKHA
30-11--1 30-11--1 - 30-11--1 - 988.52 247.5 70 70 42.35 42.35 289.85 671.02 32% 29%
May - 2018
Length 25 Km. Pack-1 - earth work 6.2/8 Km completed. Pack- 2 - earth work 6.2/8 Km completed. Pack-3 and 4 - earth work started.
No Image
Package-1 (Barawal Bandi to Jan Bati)
Package-2 (Jan Bati to Shaltalo)
Package-3 (Shaltalo to Marawaro)
Package-4 (Marawaro to Shahi Top)
1275
(OG)
140829-Improvement of 25 Km leftover portion of Chukiyatan - Barawal - Shahi Road, District Dir Upper.
Dir Upper
PKHA
30-11--1 30-11--1 - 30-11--1 - 988.52 247.5 70 70 42.35 42.35 289.85 671.02 32% 29%
April - 2018
Length 25 Km. Pack-1 - earth work 6.2/8 Km completed. Pack- 2 - earth work 6.2/8 Km completed. Pack-3 and 4 - earth work started.
No Image
Package-1 (Barawal Bandi to Jan Bati)
Package-2 (Jan Bati to Shaltalo)
Package-3 (Shaltalo to Marawaro)
Package-4 (Marawaro to Shahi Top)
1275
(OG)
140829-Improvement of 25 Km leftover portion of Chukiyatan - Barawal - Shahi Road, District Dir Upper.
Dir Upper
PKHA
30-11--1 30-11--1 - 30-11--1 - 988.52 247.5 70 70 24.85 24.85 272.35 671.02 32% 28%
March - 2018
Length 25 Km. Pack-1 - earth work 6.2/8 Km completed. Pack- 2 - earth work 6.2/8 Km completed. Pack-3 and 4 - earth work started.
No Image
Package-1 (Barawal Bandi to Jan Bati)
Package-2 (Jan Bati to Shaltalo)
Package-3 (Shaltalo to Marawaro)
Package-4 (Marawaro to Shahi Top)
1275
(OG)
140829-Improvement of 25 Km leftover portion of Chukiyatan - Barawal - Shahi Road, District Dir Upper.
Dir Upper
PKHA
30-11--1 30-11--1 - 30-11--1 - 988.52 247.5 70 70 24.85 24.85 272.35 671.02 32% 28%
February - 2018
Length 25 Km. Pack-1 - earth work 6.2/8 Km completed. Pack- 2 - earth work 6.2/8 Km completed. Pack-3 and 4 - earth work started.
No Image
Package-1 (Barawal Bandi to Jan Bati)
Package-2 (Jan Bati to Shaltalo)
Package-3 (Shaltalo to Marawaro)
Package-4 (Marawaro to Shahi Top)
1275
(OG)
140829-Improvement of 25 Km leftover portion of Chukiyatan - Barawal - Shahi Road, District Dir Upper.
Dir Upper
PKHA
30-11--1 30-11--1 - 30-11--1 - 988.52 247.5 70 42.35 14.7 14.7 262.2 671.02 32% 27%
January - 2018
Length 25 Km. Pack-1 - earth work 6.2/8 Km completed. Pack- 2 - earth work 6.2/8 Km completed. Pack-3 and 4 - earth work started.
No Image
Package-1 (Barawal Bandi to Jan Bati) Package-2 (Jan Bati to Shaltalo) Package-3 (Shaltalo to Marawaro) Package-4 (Marawaro to Shahi Top)
1275
(OG)
190279-Strengthening of Minerals Development Department
Provincial
30-11--1 30-11--1 - 30-11--1 - 19.12 3.823 0 0 0 0 3.823 0 - -
December - 2020
No Image
1275
(OG)
190279-Strengthening of Minerals Development Department
Provincial
30-11--1 30-11--1 - 30-11--1 - 19.12 3.823 0 0 0 0 3.823 0 - -
December - 2020
No Image
1275
(OG)
190279-Strengthening of Minerals Development Department
Provincial
30-11--1 30-11--1 - 30-11--1 - 19.12 3.823 0 0 0 0 3.823 0 - -
October - 2020
No Image
1275
(OG)
190279-Strengthening of Minerals Development Department
Provincial
30-11--1 30-11--1 - 30-11--1 - 19.12 3.823 0 0 0 0 3.823 0 - -
September - 2020
No Image
1275
(OG)
190279-Strengthening of Minerals Development Department
Provincial
30-11--1 30-11--1 - 30-11--1 - 19.12 3.823 0 0 0 0 3.823 0 - -
August - 2020
No Image
1275
(OG)
190279-Strengthening of Minerals Development Department
Provincial
30-11--1 30-11--1 - 30-11--1 - 19.12 3.823 0 0 0 0 3.823 0 -
July - 2020
No Image
1275
(OG)
190279-Strengthening of Minerals Development Department
Provincial
30-11--1 30-11--1 - 30-11--1 - 19.12 3.823 0 0 0 0 3.823 0 - -
May - 2021
No Image
1275
(OG)
190279-Strengthening of Minerals Development Department
Provincial
30-11--1 30-11--1 - 30-11--1 - 19.12 3.823 0 0 0 0 3.823 0 - -
April - 2021
No Image
1275
(OG)
190279-Strengthening of Minerals Development Department
Provincial
30-11--1 30-11--1 - 30-11--1 - 19.12 3.823 0 0 0 0 3.823 0 - -
March - 2021
No Image
1275
(OG)
190279-Strengthening of Minerals Development Department
Provincial
30-11--1 30-11--1 - 30-11--1 - 19.12 3.823 0 0 0 0 3.823 0 - -
February - 2021
No Image
1275
(OG)
190279-Strengthening of Minerals Development Department
Provincial
30-11--1 30-11--1 - 30-11--1 - 19.12 3.823 0 0 0 0 3.823 0 - -
January - 2021
No Image
Pages : 1