Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1275 (OG) |
140829-Improvement of 25 Km leftover portion of Chukiyatan - Barawal - Shahi Road, District Dir Upper. |
Dir Upper PKHA |
08-10-15 | - | - | 19-02-15 | - | 988.52 | 247.5 | 70 | 42.35 | 14.7 | 14.7 | 262.2 | 671.02 | 32% |
27% December - 2017 |
Length 25 Km. Pack-1 - earth work 6.2/8 Km completed. Pack- 2 - earth work 6.2/8 Km completed. Pack-3 and 4 - earth work started. |
No Image |
1275 (OG) |
140829-Improvement of 25 Km leftover portion of Chukiyatan - Barawal - Shahi Road, District Dir Upper. |
Dir Upper PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 988.52 | 247.5 | 70 | 59.85 | 24.85 | 24.85 | 272.35 | 671.02 | 32% |
28% November - 2017 |
Length 25 Km. Pack-1 - earth work 6.2/8 Km completed. Pack- 2 - earth work 6.2/8 Km completed. Pack-3 and 4 - earth work started. |
No Image |
1275 (OG) |
140829-Improvement of 25 Km leftover portion of Chukiyatan - Barawal - Shahi Road, District Dir Upper. |
Dir Upper PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 988.52 | 247.5 | 70 | 70 | 24.85 | 24.85 | 272.35 | 671.02 | 32% |
28% October - 2017 |
Length 25 Km. Pack-1 - earth work 6.2/8 Km completed. Pack- 2 - earth work 6.2/8 Km completed. Pack-3 and 4 - earth work started. |
No Image |
1275 (OG) |
140829-Improvement of 25 Km leftover portion of Chukiyatan - Barawal - Shahi Road, District Dir Upper. |
Dir Upper PKHA |
08-10-15 | - | - | 19-02-15 | - | 988.52 | 247.5 | 70 | 70 | 24.8 | 24.8 | 272.3 | 671.02 | 32% |
28% September - 2017 |
Length 25 Km. Pack-1 - earth work 6.2/8 Km completed. Pack- 2 - earth work 6.2/8 Km completed. Pack-3 and 4 - earth work started. |
No Image |
1275 (OG) |
140829-Improvement of 25 Km leftover portion of Chukiyatan - Barawal - Shahi Road, District Dir Upper. |
Dir Upper PKHA |
08-10-15 | - | - | 19-02-15 | - | 988.52 | 247.5 | 70 | 70 | 24.85 | 24.8 | 272.3 | 671.02 | 32% |
28% August - 2017 |
Length 25 Km. Pack-1 - earth work 6.2/8 Km completed. Pack- 2 - earth work 6.2/8 Km completed. Pack-3 and 4 - earth work started. |
No Image |
1275 (OG) |
140829-Improvement of 25 Km leftover portion of Chukiyatan - Barawal - Shahi Road, District Dir Upper. |
Dir Upper PKHA |
08-10-15 | - | - | 19-02-15 | - | 988.52 | 247.5 | 70 | 70 | 24.85 | 0 | 247.5 | 671.02 | 32% |
25% July - 2017 |
Length 25 Km. Pack-1 - earth work 6.2/8 Km completed. Pack- 2 - earth work 6.2/8 Km completed. Pack-3 and 4 - earth work started. |
No Image |
1275 (OG) |
140829-Improvement of 25 Km leftover portion of Chukiyatan - Barawal - Shahi Road, District Dir Upper. |
Dir Upper PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 988.52 | 247.5 | 70 | 42.35 | 42.35 | 42.35 | 289.85 | 671.02 | 32% |
29% June - 2018 |
Length 25 Km. Pack-1 - earth work 6.2/8 Km completed. Pack- 2 - earth work 6.2/8 Km completed. Pack-3 and 4 - earth work started. |
No Image |
Package-1 (Barawal Bandi to Jan Bati)
Package-2 (Jan Bati to Shaltalo)
Package-3 (Shaltalo to Marawaro)
Package-4 (Marawaro to Shahi Top) | |||||||||||||||||||
1275 (OG) |
140829-Improvement of 25 Km leftover portion of Chukiyatan - Barawal - Shahi Road, District Dir Upper. |
Dir Upper PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 988.52 | 247.5 | 70 | 70 | 42.35 | 42.35 | 289.85 | 671.02 | 32% |
29% May - 2018 |
Length 25 Km. Pack-1 - earth work 6.2/8 Km completed. Pack- 2 - earth work 6.2/8 Km completed. Pack-3 and 4 - earth work started. |
No Image |
Package-1 (Barawal Bandi to Jan Bati)
Package-2 (Jan Bati to Shaltalo)
Package-3 (Shaltalo to Marawaro)
Package-4 (Marawaro to Shahi Top) | |||||||||||||||||||
1275 (OG) |
140829-Improvement of 25 Km leftover portion of Chukiyatan - Barawal - Shahi Road, District Dir Upper. |
Dir Upper PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 988.52 | 247.5 | 70 | 70 | 42.35 | 42.35 | 289.85 | 671.02 | 32% |
29% April - 2018 |
Length 25 Km. Pack-1 - earth work 6.2/8 Km completed. Pack- 2 - earth work 6.2/8 Km completed. Pack-3 and 4 - earth work started. |
No Image |
Package-1 (Barawal Bandi to Jan Bati)
Package-2 (Jan Bati to Shaltalo)
Package-3 (Shaltalo to Marawaro)
Package-4 (Marawaro to Shahi Top) | |||||||||||||||||||
1275 (OG) |
140829-Improvement of 25 Km leftover portion of Chukiyatan - Barawal - Shahi Road, District Dir Upper. |
Dir Upper PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 988.52 | 247.5 | 70 | 70 | 24.85 | 24.85 | 272.35 | 671.02 | 32% |
28% March - 2018 |
Length 25 Km. Pack-1 - earth work 6.2/8 Km completed. Pack- 2 - earth work 6.2/8 Km completed. Pack-3 and 4 - earth work started. |
No Image |
Package-1 (Barawal Bandi to Jan Bati)
Package-2 (Jan Bati to Shaltalo)
Package-3 (Shaltalo to Marawaro)
Package-4 (Marawaro to Shahi Top) | |||||||||||||||||||
1275 (OG) |
140829-Improvement of 25 Km leftover portion of Chukiyatan - Barawal - Shahi Road, District Dir Upper. |
Dir Upper PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 988.52 | 247.5 | 70 | 70 | 24.85 | 24.85 | 272.35 | 671.02 | 32% |
28% February - 2018 |
Length 25 Km. Pack-1 - earth work 6.2/8 Km completed. Pack- 2 - earth work 6.2/8 Km completed. Pack-3 and 4 - earth work started. |
No Image |
Package-1 (Barawal Bandi to Jan Bati)
Package-2 (Jan Bati to Shaltalo)
Package-3 (Shaltalo to Marawaro)
Package-4 (Marawaro to Shahi Top) | |||||||||||||||||||
1275 (OG) |
140829-Improvement of 25 Km leftover portion of Chukiyatan - Barawal - Shahi Road, District Dir Upper. |
Dir Upper PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 988.52 | 247.5 | 70 | 42.35 | 14.7 | 14.7 | 262.2 | 671.02 | 32% |
27% January - 2018 |
Length 25 Km. Pack-1 - earth work 6.2/8 Km completed. Pack- 2 - earth work 6.2/8 Km completed. Pack-3 and 4 - earth work started. |
No Image |
Package-1 (Barawal Bandi to Jan Bati) Package-2 (Jan Bati to Shaltalo) Package-3 (Shaltalo to Marawaro) Package-4 (Marawaro to Shahi Top) | |||||||||||||||||||
1275 (OG) |
190279-Strengthening of Minerals Development Department |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 19.12 | 3.823 | 0 | 0 | 0 | 0 | 3.823 | 0 | - |
- December - 2020 |
No Image | |
1275 (OG) |
190279-Strengthening of Minerals Development Department |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 19.12 | 3.823 | 0 | 0 | 0 | 0 | 3.823 | 0 | - |
- December - 2020 |
No Image | |
1275 (OG) |
190279-Strengthening of Minerals Development Department |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 19.12 | 3.823 | 0 | 0 | 0 | 0 | 3.823 | 0 | - |
- October - 2020 |
No Image | |
1275 (OG) |
190279-Strengthening of Minerals Development Department |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 19.12 | 3.823 | 0 | 0 | 0 | 0 | 3.823 | 0 | - |
- September - 2020 |
No Image | |
1275 (OG) |
190279-Strengthening of Minerals Development Department |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 19.12 | 3.823 | 0 | 0 | 0 | 0 | 3.823 | 0 | - |
- August - 2020 |
No Image | |
1275 (OG) |
190279-Strengthening of Minerals Development Department |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 19.12 | 3.823 | 0 | 0 | 0 | 0 | 3.823 | 0 | - |
July - 2020 |
No Image | |
1275 (OG) |
190279-Strengthening of Minerals Development Department |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 19.12 | 3.823 | 0 | 0 | 0 | 0 | 3.823 | 0 | - |
- May - 2021 |
No Image | |
1275 (OG) |
190279-Strengthening of Minerals Development Department |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 19.12 | 3.823 | 0 | 0 | 0 | 0 | 3.823 | 0 | - |
- April - 2021 |
No Image | |
1275 (OG) |
190279-Strengthening of Minerals Development Department |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 19.12 | 3.823 | 0 | 0 | 0 | 0 | 3.823 | 0 | - |
- March - 2021 |
No Image | |
1275 (OG) |
190279-Strengthening of Minerals Development Department |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 19.12 | 3.823 | 0 | 0 | 0 | 0 | 3.823 | 0 | - |
- February - 2021 |
No Image | |
1275 (OG) |
190279-Strengthening of Minerals Development Department |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 19.12 | 3.823 | 0 | 0 | 0 | 0 | 3.823 | 0 | - |
- January - 2021 |
No Image | |
Pages : 1 |