Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1274 (OG) |
90397-F/S and Construction of road from Chukiathan to Sheringal and Patrak by FHA (36 Km) Dir Upper. |
Dir Upper PKHA |
31-01-11 | - | - | 07-01-15 | - | 1798.521 | 1659.087 | 40 | 24.2 | 14.2 | 14.2 | 1673.287 | 99.434 | 94% |
93% December - 2017 |
Length 32 Km - earth work 70%, sub-base 50%, WBM 50% completed, asphalt wearing course 1 Km completed. |
No Image |
1) Package-1 Km-0 to 9 (9 Kms)
2) Package-2 Km-9 to 16 (7 Kms)
3) Package-3 Km-17 to 24 (7 Kms)
4) Package-4 Km-24 to 31+797 m (7.8 Kms)
5) Package-5 3 Nos bridges | |||||||||||||||||||
1274 (OG) |
90397-F/S and Construction of road from Chukiathan to Sheringal and Patrak by FHA (36 Km) Dir Upper. |
Dir Upper PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1798.521 | 1659.087 | 40 | 40 | 14.2 | 14.2 | 1673.287 | 99.434 | 94% |
93% November - 2017 |
Length 32 Km - earth work 70%, sub-base 50%, WBM 50% completed, asphalt wearing course 1 Km completed. |
No Image |
1) Package-1 Km-0 to 9 (9 Kms)
2) Package-2 Km-9 to 16 (7 Kms)
3) Package-3 Km-17 to 24 (7 Kms)
4) Package-4 Km-24 to 31+797 m (7.8 Kms)
5) Package-5 3 Nos bridges | |||||||||||||||||||
1274 (OG) |
90397-F/S and Construction of road from Chukiathan to Sheringal and Patrak by FHA (36 Km) Dir Upper. |
Dir Upper PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1798.521 | 1659.087 | 40 | 40 | 14.2 | 14.2 | 1673.287 | 99.434 | 94% |
93% October - 2017 |
Length 32 Km - earth work 70%, sub-base 50%, WBM 50% completed, asphalt wearing course 1 Km completed. |
No Image |
1) Package-1 Km-0 to 9 (9 Kms)
2) Package-2 Km-9 to 16 (7 Kms)
3) Package-3 Km-17 to 24 (7 Kms)
4) Package-4 Km-24 to 31+797 m (7.8 Kms)
5) Package-5 3 Nos bridges | |||||||||||||||||||
1274 (OG) |
90397-F/S and Construction of road from Chukiathan to Sheringal and Patrak by FHA (36 Km) Dir Upper. |
Dir Upper PKHA |
31-01-11 | - | - | 07-01-15 | - | 1798.521 | 1659.087 | 40 | 40 | 14.2 | 14.2 | 1673.287 | 99.434 | 94% |
93% September - 2017 |
Length 32 Km - earth work 70%, sub-base 50%, WBM 50% completed, asphalt wearing course 1 Km completed. |
No Image |
1) Package-1 Km-0 to 9 (9 Kms)
2) Package-2 Km-9 to 16 (7 Kms)
3) Package-3 Km-17 to 24 (7 Kms)
4) Package-4 Km-24 to 31+797 m (7.8 Kms)
5) Package-5 3 Nos bridges | |||||||||||||||||||
1274 (OG) |
90397-F/S and Construction of road from Chukiathan to Sheringal and Patrak by FHA (36 Km) Dir Upper. |
Dir Upper PKHA |
31-01-11 | - | - | 07-01-15 | - | 1798.521 | 1659.087 | 40 | 40 | 14.2 | 14.2 | 1673.287 | 99.434 | 94% |
93% August - 2017 |
Length 32 Km - earth work 70%, sub-base 50%, WBM 50% completed, asphalt wearing course 1 Km completed. |
No Image |
1) Package-1 Km-0 to 9 (9 Kms)
2) Package-2 Km-9 to 16 (7 Kms)
3) Package-3 Km-17 to 24 (7 Kms)
4) Package-4 Km-24 to 31+797 m (7.8 Kms)
5) Package-5 3 Nos bridges | |||||||||||||||||||
1274 (OG) |
90397-F/S and Construction of road from Chukiathan to Sheringal and Patrak by FHA (36 Km) Dir Upper. |
Dir Upper PKHA |
31-01-11 | - | - | 07-01-15 | - | 1798.521 | 1659.087 | 40 | 40 | 14.2 | 0 | 1659.087 | 99.434 | 94% |
92% July - 2017 |
Length 32 Km - earth work 70%, sub-base 50%, WBM 50% completed, asphalt wearing course 1 Km completed. |
No Image |
1) Package-1 Km-0 to 9 (9 Kms)
2) Package-2 Km-9 to 16 (7 Kms)
3) Package-3 Km-17 to 24 (7 Kms)
4) Package-4 Km-24 to 31+797 m (7.8 Kms)
5) Package-5 3 Nos bridges | |||||||||||||||||||
1274 (OG) |
90397-F/S and Construction of road from Chukiathan to Sheringal and Patrak by FHA (36 Km) Dir Upper. |
Dir Upper PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1798.521 | 1659.087 | 40 | 24.2 | 24.2 | 24.2 | 1683.287 | 99.434 | 94% |
94% June - 2018 |
Length 32 Km - earth work 70%, sub-base 50%, WBM 50% completed, asphalt wearing course 1 Km completed. |
No Image |
1) Package-1 Km-0 to 9 (9 Km)
2) Package-2 Km-9 to 16 (7 Km)
3) Package-3 Km-17 to 24 (7 Km)
4) Package-4 Km-24 to 31+797 m (7.8 Km)
5) Package-5 3 Nos bridges | |||||||||||||||||||
1274 (OG) |
90397-F/S and Construction of road from Chukiathan to Sheringal and Patrak by FHA (36 Km) Dir Upper. |
Dir Upper PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1798.521 | 1659.087 | 40 | 40 | 24.2 | 24.2 | 1683.287 | 99.434 | 94% |
94% May - 2018 |
Length 32 Km - earth work 70%, sub-base 50%, WBM 50% completed, asphalt wearing course 1 Km completed. |
No Image |
1) Package-1 Km-0 to 9 (9 Km)
2) Package-2 Km-9 to 16 (7 Km)
3) Package-3 Km-17 to 24 (7 Km)
4) Package-4 Km-24 to 31+797 m (7.8 Km)
5) Package-5 3 Nos bridges | |||||||||||||||||||
1274 (OG) |
90397-F/S and Construction of road from Chukiathan to Sheringal and Patrak by FHA (36 Km) Dir Upper. |
Dir Upper PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1798.521 | 1659.087 | 40 | 40 | 24.2 | 24.2 | 1683.287 | 99.434 | 94% |
94% April - 2018 |
Length 32 Km - earth work 70%, sub-base 50%, WBM 50% completed, asphalt wearing course 1 Km completed. |
No Image |
1) Package-1 Km-0 to 9 (9 Km)
2) Package-2 Km-9 to 16 (7 Km)
3) Package-3 Km-17 to 24 (7 Km)
4) Package-4 Km-24 to 31+797 m (7.8 Km)
5) Package-5 3 Nos bridges | |||||||||||||||||||
1274 (OG) |
90397-F/S and Construction of road from Chukiathan to Sheringal and Patrak by FHA (36 Km) Dir Upper. |
Dir Upper PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1798.521 | 1659.087 | 40 | 40 | 14.2 | 14.2 | 1673.287 | 99.434 | 94% |
93% March - 2018 |
Length 32 Km - earth work 70%, sub-base 50%, WBM 50% completed, asphalt wearing course 1 Km completed. |
No Image |
1) Package-1 Km-0 to 9 (9 Km)
2) Package-2 Km-9 to 16 (7 Km)
3) Package-3 Km-17 to 24 (7 Km)
4) Package-4 Km-24 to 31+797 m (7.8 Km)
5) Package-5 3 Nos bridges | |||||||||||||||||||
1274 (OG) |
90397-F/S and Construction of road from Chukiathan to Sheringal and Patrak by FHA (36 Km) Dir Upper. |
Dir Upper PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1798.521 | 1659.087 | 40 | 40 | 14.2 | 14.2 | 1673.287 | 99.434 | 94% |
93% February - 2018 |
Length 32 Km - earth work 70%, sub-base 50%, WBM 50% completed, asphalt wearing course 1 Km completed. |
No Image |
1) Package-1 Km-0 to 9 (9 Km)
2) Package-2 Km-9 to 16 (7 Km)
3) Package-3 Km-17 to 24 (7 Km)
4) Package-4 Km-24 to 31+797 m (7.8 Km)
5) Package-5 3 Nos bridges | |||||||||||||||||||
1274 (OG) |
90397-F/S and Construction of road from Chukiathan to Sheringal and Patrak by FHA (36 Km) Dir Upper. |
Dir Upper PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1798.521 | 1659.087 | 40 | 24.2 | 14.2 | 14.2 | 1673.287 | 99.434 | 94% |
93% January - 2018 |
Length 32 Km - earth work 70%, sub-base 50%, WBM 50% completed, asphalt wearing course 1 Km completed. |
No Image |
1) Package-1 Km-0 to 9 (9 Kms) 2) Package-2 Km-9 to 16 (7 Kms) 3) Package-3 Km-17 to 24 (7 Kms) 4) Package-4 Km-24 to 31+797 m (7.8 Kms) 5) Package-5 3 Nos bridges | |||||||||||||||||||
1274 (OG) |
170143-Geological Mapping of Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 397.231 | 3.794 | 0 | 0 | 0 | 0 | 3.794 | 0 | - |
- December - 2020 |
No Image | |
1274 (OG) |
170143-Geological Mapping of Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 397.231 | 3.794 | 0 | 0 | 0 | 0 | 3.794 | 0 | - |
- December - 2020 |
No Image | |
1274 (OG) |
170143-Geological Mapping of Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 397.231 | 3.794 | 0 | 0 | 0 | 0 | 3.794 | 0 | - |
- October - 2020 |
No Image | |
1274 (OG) |
170143-Geological Mapping of Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 397.231 | 3.794 | 0 | 0 | 0 | 0 | 3.794 | 0 | - |
- September - 2020 |
No Image | |
1274 (OG) |
170143-Geological Mapping of Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 397.231 | 3.794 | 0 | 0 | 0 | 0 | 3.794 | 0 | - |
- August - 2020 |
No Image | |
1274 (OG) |
170143-Geological Mapping of Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 397.231 | 3.794 | 0 | 0 | 0 | 0 | 3.794 | 0 | - |
July - 2020 |
No Image | |
1274 (OG) |
170143-Geological Mapping of Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 397.231 | 3.794 | 0 | 0 | 0 | 0 | 3.794 | 0 | - |
- May - 2021 |
No Image | |
1274 (OG) |
170143-Geological Mapping of Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 397.231 | 3.794 | 0 | 0 | 0 | 0 | 3.794 | 0 | - |
- April - 2021 |
No Image | |
1274 (OG) |
170143-Geological Mapping of Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 397.231 | 3.794 | 0 | 0 | 0 | 0 | 3.794 | 0 | - |
- March - 2021 |
No Image | |
1274 (OG) |
170143-Geological Mapping of Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 397.231 | 3.794 | 0 | 0 | 0 | 0 | 3.794 | 0 | - |
- February - 2021 |
No Image | |
1274 (OG) |
170143-Geological Mapping of Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 397.231 | 3.794 | 0 | 0 | 0 | 0 | 3.794 | 0 | - |
- January - 2021 |
No Image | |