Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1273 (OG) |
140623-Construction of road from Balambat Timergara to Kalpani Maidan Link road District Dir Lower. |
Dir Lower PKHA |
04-09-15 | - | - | 07-01-15 | - | 318.69 | 192.5 | 30 | 25.65 | 10.65 | 10.65 | 203.15 | 96.19 | 70% |
64% December - 2017 |
Pack-1 - earth work 90% completed, structure work in progress. Pack-2 - earth work 85% completed, structure work in progress. |
No Image |
1273 (OG) |
140623-Construction of road from Balambat Timergara to Kalpani Maidan Link road District Dir Lower. |
Dir Lower PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 318.69 | 192.5 | 30 | 30 | 10.65 | 10.65 | 203.15 | 96.19 | 70% |
64% November - 2017 |
Pack-1 - earth work 90% completed, structure work in progress. Pack-2 - earth work 85% completed, structure work in progress. |
No Image |
1273 (OG) |
140623-Construction of road from Balambat Timergara to Kalpani Maidan Link road District Dir Lower. |
Dir Lower PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 318.69 | 192.5 | 30 | 30 | 10.65 | 10.65 | 203.15 | 96.19 | 70% |
64% October - 2017 |
Pack-1 - earth work 90% completed, structure work in progress. Pack-2 - earth work 85% completed, structure work in progress. |
No Image |
1273 (OG) |
140623-Construction of road from Balambat Timergara to Kalpani Maidan Link road District Dir Lower. |
Dir Lower PKHA |
04-09-15 | - | - | 07-01-15 | - | 318.69 | 192.5 | 30 | 30 | 10.65 | 10.65 | 203.15 | 96.19 | 70% |
64% September - 2017 |
Pack-1 - earth work 90% completed, structure work in progress. Pack-2 - earth work 85% completed, structure work in progress. |
No Image |
1273 (OG) |
140623-Construction of road from Balambat Timergara to Kalpani Maidan Link road District Dir Lower. |
Dir Lower PKHA |
04-09-15 | - | - | 07-01-15 | - | 318.69 | 192.5 | 30 | 30 | 10.65 | 10.65 | 203.15 | 96.19 | 70% |
64% August - 2017 |
Pack-1 - earth work 90% completed, structure work in progress. Pack-2 - earth work 85% completed, structure work in progress. |
No Image |
1273 (OG) |
140623-Construction of road from Balambat Timergara to Kalpani Maidan Link road District Dir Lower. |
Dir Lower PKHA |
04-09-15 | - | - | 07-01-15 | - | 318.69 | 192.5 | 30 | 30 | 10.65 | 0 | 192.5 | 96.19 | 70% |
60% July - 2017 |
Pack-1 - earth work 90% completed, structure work in progress. Pack-2 - earth work 85% completed, structure work in progress. |
No Image |
1273 (OG) |
140623-Construction of road from Balambat Timergara to Kalpani Maidan Link road District Dir Lower. |
Dir Lower PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 689.999 | 192.5 | 30 | 25.65 | 25.65 | 25.65 | 218.15 | 467.499 | 32% |
32% June - 2018 |
Pack-1 - earth work 90% completed, structure work in progress. Pack-2 - earth work 85% completed, structure work in progress. PC-II for Rs.25.250 m approved in DDWP-I on 07/05/2018. |
No Image |
Package-1
Package-2 | |||||||||||||||||||
1273 (OG) |
140623-Construction of road from Balambat Timergara to Kalpani Maidan Link road District Dir Lower. |
Dir Lower PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 689.999 | 192.5 | 30 | 30 | 25.65 | 25.65 | 218.15 | 467.499 | 32% |
32% May - 2018 |
Pack-1 - earth work 90% completed, structure work in progress. Pack-2 - earth work 85% completed, structure work in progress. PC-II for Rs.25.250 m approved in DDWP-I on 07/05/2018. |
No Image |
Package-1
Package-2 | |||||||||||||||||||
1273 (OG) |
140623-Construction of road from Balambat Timergara to Kalpani Maidan Link road District Dir Lower. |
Dir Lower PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 689.999 | 192.5 | 30 | 30 | 25.65 | 25.65 | 218.15 | 467.499 | 32% |
32% April - 2018 |
Pack-1 - earth work 90% completed, structure work in progress. Pack-2 - earth work 85% completed, structure work in progress. |
No Image |
Package-1
Package-2 | |||||||||||||||||||
1273 (OG) |
140623-Construction of road from Balambat Timergara to Kalpani Maidan Link road District Dir Lower. |
Dir Lower PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 689.999 | 192.5 | 30 | 30 | 10.65 | 10.65 | 203.15 | 467.499 | 32% |
29% March - 2018 |
Pack-1 - earth work 90% completed, structure work in progress. Pack-2 - earth work 85% completed, structure work in progress. Approved for Rs.689.999 m in PDWP on 08/02/2018. |
No Image |
Package-1
Package-2 | |||||||||||||||||||
1273 (OG) |
140623-Construction of road from Balambat Timergara to Kalpani Maidan Link road District Dir Lower. |
Dir Lower PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 689.999 | 208.915 | 30 | 30 | 10.65 | 10.65 | 219.565 | 451.084 | 35% |
32% February - 2018 |
Pack-1 - earth work 90% completed, structure work in progress. Pack-2 - earth work 85% completed, structure work in progress. Approved for Rs.689.999 m in PDWP on 08/02/2018. |
No Image |
Package-1
Package-2 | |||||||||||||||||||
1273 (OG) |
140623-Construction of road from Balambat Timergara to Kalpani Maidan Link road District Dir Lower. |
Dir Lower PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 318.69 | 192.5 | 30 | 25.65 | 10.65 | 10.65 | 203.15 | 96.19 | 70% |
64% January - 2018 |
Pack-1 - earth work 90% completed, structure work in progress. Pack-2 - earth work 85% completed, structure work in progress. |
No Image |
Package-1 Package-2 | |||||||||||||||||||
1273 (OG) |
160041-Establishment of Mining Cadastral System, |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 168.468 | 55.847 | 0 | 0 | 0 | 0 | 55.847 | 0 | - |
- December - 2020 |
No Image | |
1273 (OG) |
160041-Establishment of Mining Cadastral System, |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 168.468 | 55.847 | 0 | 0 | 0 | 0 | 55.847 | 0 | - |
- December - 2020 |
No Image | |
1273 (OG) |
160041-Establishment of Mining Cadastral System, |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 168.468 | 55.847 | 0 | 0 | 0 | 0 | 55.847 | 0 | - |
- October - 2020 |
No Image | |
1273 (OG) |
160041-Establishment of Mining Cadastral System, |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 168.468 | 55.847 | 0 | 0 | 0 | 0 | 55.847 | 0 | - |
- September - 2020 |
No Image | |
1273 (OG) |
160041-Establishment of Mining Cadastral System, |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 168.468 | 55.847 | 0 | 0 | 0 | 0 | 55.847 | 0 | - |
- August - 2020 |
No Image | |
1273 (OG) |
160041-Establishment of Mining Cadastral System, |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 168.468 | 55.847 | 0 | 0 | 0 | 0 | 55.847 | 0 | - |
July - 2020 |
No Image | |
1273 (OG) |
160041-Establishment of Mining Cadastral System, |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 168.468 | 55.847 | 0 | 0 | 0 | 0 | 55.847 | 0 | - |
- May - 2021 |
No Image | |
1273 (OG) |
160041-Establishment of Mining Cadastral System, |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 168.468 | 55.847 | 0 | 0 | 0 | 0 | 55.847 | 0 | - |
- April - 2021 |
No Image | |
1273 (OG) |
160041-Establishment of Mining Cadastral System, |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 168.468 | 55.847 | 0 | 0 | 0 | 0 | 55.847 | 0 | - |
- March - 2021 |
No Image | |
1273 (OG) |
160041-Establishment of Mining Cadastral System, |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 168.468 | 55.847 | 0 | 0 | 0 | 0 | 55.847 | 0 | - |
- February - 2021 |
No Image | |
1273 (OG) |
160041-Establishment of Mining Cadastral System, |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 168.468 | 55.847 | 0 | 0 | 0 | 0 | 55.847 | 0 | - |
- January - 2021 |