Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2018, January - 2021, February - 2018, February - 2021, March - 2018, March - 2021, April - 2018, April - 2021, May - 2018, May - 2021, June - 2018, July - 2017, July - 2020, August - 2017, August - 2020, September - 2017, September - 2020, October - 2017, October - 2020, November - 2017, December - 2017, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1237
(OG)
191634-170150-Rural Work Program in TDPs Return Area of Orakzai Agency. [MA]
Orakzai
30-11--1 30-11--1 - 30-11--1 - 66.8 47.435 19.365 19.365 0 0 47.435 0 - -
December - 2020
No Image
1237
(OG)
191634-170150-Rural Work Program in TDPs Return Area of Orakzai Agency. [MA]
Orakzai
30-11--1 30-11--1 - 30-11--1 - 66.8 47.435 19.365 19.365 0 0 47.435 0 - -
December - 2020
No Image
1237
(OG)
191634-170150-Rural Work Program in TDPs Return Area of Orakzai Agency. [MA]
Orakzai
30-11--1 30-11--1 - 30-11--1 - 66.8 47.435 19.365 19.365 0 0 47.435 0 - -
October - 2020
No Image
1237
(OG)
191634-170150-Rural Work Program in TDPs Return Area of Orakzai Agency. [MA]
Orakzai
30-11--1 30-11--1 - 30-11--1 - 66.8 47.435 19.365 19.365 0 0 47.435 0 - -
September - 2020
No Image
1237
(OG)
191634-170150-Rural Work Program in TDPs Return Area of Orakzai Agency. [MA]
Orakzai
30-11--1 30-11--1 - 30-11--1 - 66.8 47.435 19.365 19.365 0 0 47.435 0 - -
August - 2020
No Image
1237
(OG)
191634-170150-Rural Work Program in TDPs Return Area of Orakzai Agency. [MA]
Orakzai
30-11--1 30-11--1 - 30-11--1 - 66.8 47.435 19.365 0 0 0 47.435 0
July - 2020
No Image
1237
(OG)
191634-170150-Rural Work Program in TDPs Return Area of Orakzai Agency. [MA]
Orakzai
30-11--1 30-11--1 - 30-11--1 - 66.8 47.435 19.365 19.365 0 0 47.435 0 - -
May - 2021
No Image
1237
(OG)
191634-170150-Rural Work Program in TDPs Return Area of Orakzai Agency. [MA]
Orakzai
30-11--1 30-11--1 - 30-11--1 - 66.8 47.435 19.365 19.365 0 0 47.435 0 - -
April - 2021
No Image
1237
(OG)
191634-170150-Rural Work Program in TDPs Return Area of Orakzai Agency. [MA]
Orakzai
30-11--1 30-11--1 - 30-11--1 - 66.8 47.435 19.365 19.365 0 0 47.435 0 - -
March - 2021
No Image
1237
(OG)
191634-170150-Rural Work Program in TDPs Return Area of Orakzai Agency. [MA]
Orakzai
30-11--1 30-11--1 - 30-11--1 - 66.8 47.435 19.365 19.365 0 0 47.435 0 - -
February - 2021
No Image
1237
(OG)
191634-170150-Rural Work Program in TDPs Return Area of Orakzai Agency. [MA]
Orakzai
30-11--1 30-11--1 - 30-11--1 - 66.8 47.435 19.365 19.365 0 0 47.435 0 - -
January - 2021
No Image
1237
(New)
170625-Construction of 5Km road & its drains from Swabi Interchange to Swabi University (New Campus) Swabi.
Swabi
- - - 15-09-17 - 80 0 9.084 6.813 0 0 0 70.916 11% -
December - 2017
Tender from pre-qualified contractors called on 09/01/2018.
No Image
1237
(New)
170625-Construction of 5Km road & its drains from Swabi Interchange to Swabi University (New Campus) Swabi.
Swabi
- - - - Line Deptt 80 0 9.084 9.084 0 0 0 0 - -
September - 2017
Approved. AA awaited.
No Image
1237
(New)
170625-Construction of 5Km road & its drains from Swabi Interchange to Swabi University (New Campus) Swabi.
Swabi
- - - - Line Deptt 80 0 9.084 9.084 0 0 0 0 - -
August - 2017
PC-I/DCE submitted Chief Infra. Pre-PDWP held on 07/08/2017.
No Image
1237
(New)
170625-Construction of 5Km road & its drains from Swabi Interchange to Swabi University (New Campus) Swabi.
Swabi
- - - - Line Deptt 80 0 9.084 9.084 0 0 0 0 - -
July - 2017
PC-I/DCE submitted Chief Infra. Pre-PDWP held on 07/08/2017.
No Image
1237
(New)
170625-Construction of 5Km road & its drains from Swabi Interchange to Swabi University (New Campus) Swabi.
Swabi
30-11--1 30-11--1 - 30-11--1 - 80 0 9.084 6.813 0 0 0 70.916 11% -
November - 2017
Pre-qualification approval under process.
No Image
1237
(New)
170625-Construction of 5Km road & its drains from Swabi Interchange to Swabi University (New Campus) Swabi.
Swabi
30-11--1 30-11--1 - 30-11--1 - 80 0 9.084 9.084 0 0 0 70.916 11% -
October - 2017
Pre-qualification called on 17/10/2017, evaluation under process.
No Image
1237
(New)
170625-Construction of 5Km road & its drains from Swabi Interchange to Swabi University (New Campus) Swabi.
Swabi
30-11--1 30-11--1 - 30-11--1 - 80 0 9.084 6.8 6.8 6.8 6.8 70.916 11% 9%
June - 2018
Length 5 Km - earth work 50% completed.
No Image
Swabi 5 Km
1237
(New)
170625-Construction of 5Km road & its drains from Swabi Interchange to Swabi University (New Campus) Swabi.
Swabi
30-11--1 30-11--1 - 30-11--1 - 80 0 9.084 6.813 6.813 6.8 6.8 70.916 11% 9%
May - 2018
Length 5 Km - work order issued. Rs.80 m demanded.
No Image
Swabi 5 Km
1237
(New)
170625-Construction of 5Km road & its drains from Swabi Interchange to Swabi University (New Campus) Swabi.
Swabi
30-11--1 30-11--1 - 30-11--1 - 80 0 9.084 6.813 0 0 0 70.916 11% -
April - 2018
Length 5 Km - work order issued. Rs.80 m demanded.
No Image
Swabi 5 Km
1237
(New)
170625-Construction of 5Km road & its drains from Swabi Interchange to Swabi University (New Campus) Swabi.
Swabi
30-11--1 30-11--1 - 30-11--1 - 80 0 9.084 6.813 0 0 0 70.916 11% -
March - 2018
Length 5 Km - work order issued.
No Image
Swabi 5 Km
1237
(New)
170625-Construction of 5Km road & its drains from Swabi Interchange to Swabi University (New Campus) Swabi.
Swabi
30-11--1 30-11--1 - 30-11--1 - 80 0 9.084 6.813 0 0 0 70.916 11% -
February - 2018
Work order issued.
No Image
Swabi 5 Km
1237
(New)
170625-Construction of 5Km road & its drains from Swabi Interchange to Swabi University (New Campus) Swabi.
Swabi
30-11--1 30-11--1 - 30-11--1 - 80 0 9.084 6.813 0 0 0 70.916 11% -
January - 2018
Tender from pre-qualified contractors called on 09/01/2018, approval under process.
No Image
Pages : 1