Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1232 (New) |
170580-Construction of roads in PK-17 a) 205 Km road from Mill Pump Nowshera to Sattibad UC Mera Pang,b) 2 Km road from Nowshera to Karoona UC Dheri Zardad, c) 2.5 Km road from Prang Majokay to faqir abad Majokay MC-II, District Charsadda. |
Charsadda |
- | - | - | 15-09-17 | - | 105.593 | 0 | 10 | 10 | 2.5 | 0 | 0 | 95.593 | 9% |
- December - 2017 |
NIT Delayd due to decsion of PDWP regarding procurement as per alloactions. Decsion on summary awaited. |
No Image |
1232 (New) |
170580-Construction of roads in PK-17 a) 205 Km road from Mill Pump Nowshera to Sattibad UC Mera Pang,b) 2 Km road from Nowshera to Karoona UC Dheri Zardad, c) 2.5 Km road from Prang Majokay to faqir abad Majokay MC-II, District Charsadda. |
Charsadda |
- | - | - | - | Line Deptt | 200 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- September - 2017 |
PC-I/DCE for Rs.108.757 m approved. AA awaited. |
No Image |
1232 (New) |
170580-Construction of roads in PK-17 a) 205 Km road from Mill Pump Nowshera to Sattibad UC Mera Pang,b) 2 Km road from Nowshera to Karoona UC Dheri Zardad, c) 2.5 Km road from Prang Majokay to faqir abad Majokay MC-II, District Charsadda. |
Charsadda |
- | - | - | - | Line Deptt | 200 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- August - 2017 |
PC-I/DCE for Rs.108.757 m submitted to SOR on 12/07/2017. Pre-PDWP held on 07/08/2017. |
No Image |
1232 (New) |
170580-Construction of roads in PK-17 a) 205 Km road from Mill Pump Nowshera to Sattibad UC Mera Pang,b) 2 Km road from Nowshera to Karoona UC Dheri Zardad, c) 2.5 Km road from Prang Majokay to faqir abad Majokay MC-II, District Charsadda. |
Charsadda |
- | - | - | - | Line Deptt | 200 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- July - 2017 |
PC-I/DCE for Rs.108.757 m submitted to SOR on 12/07/2017. Pre-PDWP held on 07/08/2017. |
No Image |
1232 (New) |
170580-Construction of roads in PK-17 a) 205 Km road from Mill Pump Nowshera to Sattibad UC Mera Pang,b) 2 Km road from Nowshera to Karoona UC Dheri Zardad, c) 2.5 Km road from Prang Majokay to faqir abad Majokay MC-II, District Charsadda. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 105.593 | 0 | 10 | 10 | 2.5 | 0 | 0 | 95.593 | 9% |
- November - 2017 |
NIT Delayd due to decsion of PDWP regarding procurement as per alloactions. Decsion on summary awaited. |
No Image |
1232 (New) |
170580-Construction of roads in PK-17 a) 205 Km road from Mill Pump Nowshera to Sattibad UC Mera Pang,b) 2 Km road from Nowshera to Karoona UC Dheri Zardad, c) 2.5 Km road from Prang Majokay to faqir abad Majokay MC-II, District Charsadda. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 105.593 | 0 | 10 | 10 | 0 | 0 | 0 | 95.593 | 9% |
- October - 2017 |
Pre-qualification of opened on 01/11/2017. |
No Image |
1232 (New) |
170580-Construction of roads in PK-17 a) 205 Km road from Mill Pump Nowshera to Sattibad UC Mera Pang,b) 2 Km road from Nowshera to Karoona UC Dheri Zardad, c) 2.5 Km road from Prang Majokay to faqir abad Majokay MC-II, District Charsadda. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 105.593 | 0 | 10 | 17.94 | 17.94 | 17.94 | 17.94 | 95.593 | 9% |
17% June - 2018 |
3 units - Length 7.5 Km - width 24 ft. Earth Work in progress |
No Image |
a. 205 Km road from Mill Pump Nowshera to Sattibad UC Mera Pang,
b) 2 Km road from Nowshera to Karoona UC Dheri Zardad,
c) 2.5 Km road from Prang Majokay to faqir abad Majokay MC-II, | |||||||||||||||||||
1232 (New) |
170580-Construction of roads in PK-17 a) 205 Km road from Mill Pump Nowshera to Sattibad UC Mera Pang,b) 2 Km road from Nowshera to Karoona UC Dheri Zardad, c) 2.5 Km road from Prang Majokay to faqir abad Majokay MC-II, District Charsadda. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 105.593 | 0 | 10 | 21.653 | 21.653 | 2.011 | 2.011 | 95.593 | 9% |
2% May - 2018 |
3 units - Length 7.5 Km - width 24 ft. Earth Work in progress |
No Image |
a. 205 Km road from Mill Pump Nowshera to Sattibad UC Mera Pang,
b) 2 Km road from Nowshera to Karoona UC Dheri Zardad,
c) 2.5 Km road from Prang Majokay to faqir abad Majokay MC-II, | |||||||||||||||||||
1232 (New) |
170580-Construction of roads in PK-17 a) 205 Km road from Mill Pump Nowshera to Sattibad UC Mera Pang,b) 2 Km road from Nowshera to Karoona UC Dheri Zardad, c) 2.5 Km road from Prang Majokay to faqir abad Majokay MC-II, District Charsadda. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 105.593 | 0 | 10 | 21.653 | 21.653 | 2.011 | 2.011 | 95.593 | 9% |
2% April - 2018 |
3 units - Length 7.5 Km - width 24 ft. Earth Work in progress |
No Image |
a. 205 Km road from Mill Pump Nowshera to Sattibad UC Mera Pang,
b) 2 Km road from Nowshera to Karoona UC Dheri Zardad,
c) 2.5 Km road from Prang Majokay to faqir abad Majokay MC-II, | |||||||||||||||||||
1232 (New) |
170580-Construction of roads in PK-17 a) 205 Km road from Mill Pump Nowshera to Sattibad UC Mera Pang,b) 2 Km road from Nowshera to Karoona UC Dheri Zardad, c) 2.5 Km road from Prang Majokay to faqir abad Majokay MC-II, District Charsadda. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 105.593 | 0 | 10 | 18.963 | 18.963 | 0 | 0 | 95.593 | 9% |
- March - 2018 |
3 units - Length 7.5 Km - width 24 ft. Earth Work in progress |
No Image |
a. 205 Km road from Mill Pump Nowshera to Sattibad UC Mera Pang,
b) 2 Km road from Nowshera to Karoona UC Dheri Zardad,
c) 2.5 Km road from Prang Majokay to faqir abad Majokay MC-II, | |||||||||||||||||||
1232 (New) |
170580-Construction of roads in PK-17 a) 205 Km road from Mill Pump Nowshera to Sattibad UC Mera Pang,b) 2 Km road from Nowshera to Karoona UC Dheri Zardad, c) 2.5 Km road from Prang Majokay to faqir abad Majokay MC-II, District Charsadda. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 105.593 | 0 | 10 | 18.963 | 18.963 | 0 | 0 | 95.593 | 9% |
- February - 2018 |
3 units- length 7.5 km - width 24 ft . Work started on alll 3 units |
No Image |
a. 205 Km road from Mill Pump Nowshera to Sattibad UC Mera Pang,
b) 2 Km road from Nowshera to Karoona UC Dheri Zardad,
c) 2.5 Km road from Prang Majokay to faqir abad Majokay MC-II, | |||||||||||||||||||
1232 (New) |
170580-Construction of roads in PK-17 a) 205 Km road from Mill Pump Nowshera to Sattibad UC Mera Pang,b) 2 Km road from Nowshera to Karoona UC Dheri Zardad, c) 2.5 Km road from Prang Majokay to faqir abad Majokay MC-II, District Charsadda. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 105.593 | 0 | 10 | 10 | 2.5 | 0 | 0 | 95.593 | 9% |
- January - 2018 |
NIT Delayd due to decsion of PDWP regarding procurement as per alloactions. Decsion on summary awaited. |
No Image |
Charsadda | |||||||||||||||||||
1232 (OG) |
191608-180371 - Constr: & B/Topping of farm to Market road in Lower District Kurram. [MA] |
Kurram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50 | 13.537 | 36.463 | 36.463 | 0 | 0 | 13.537 | 0 | - |
- December - 2020 |
No Image | |
1232 (OG) |
191608-180371 - Constr: & B/Topping of farm to Market road in Lower District Kurram. [MA] |
Kurram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50 | 13.537 | 36.463 | 36.463 | 0 | 0 | 13.537 | 0 | - |
- December - 2020 |
No Image | |
1232 (OG) |
191608-180371 - Constr: & B/Topping of farm to Market road in Lower District Kurram. [MA] |
Kurram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50 | 13.537 | 36.463 | 36.463 | 0 | 0 | 13.537 | 0 | - |
- October - 2020 |
No Image | |
1232 (OG) |
191608-180371 - Constr: & B/Topping of farm to Market road in Lower District Kurram. [MA] |
Kurram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50 | 13.537 | 36.463 | 36.463 | 0 | 0 | 13.537 | 0 | - |
- September - 2020 |
No Image | |
1232 (OG) |
191608-180371 - Constr: & B/Topping of farm to Market road in Lower District Kurram. [MA] |
Kurram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50 | 13.537 | 36.463 | 36.463 | 0 | 0 | 13.537 | 0 | - |
- August - 2020 |
No Image | |
1232 (OG) |
191608-180371 - Constr: & B/Topping of farm to Market road in Lower District Kurram. [MA] |
Kurram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50 | 13.537 | 36.463 | 0 | 0 | 0 | 13.537 | 0 |
July - 2020 |
No Image | ||
1232 (OG) |
191608-180371 - Constr: & B/Topping of farm to Market road in Lower District Kurram. [MA] |
Kurram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50 | 13.537 | 36.463 | 36.463 | 0 | 0 | 13.537 | 0 | - |
- May - 2021 |
No Image | |
1232 (OG) |
191608-180371 - Constr: & B/Topping of farm to Market road in Lower District Kurram. [MA] |
Kurram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50 | 13.537 | 36.463 | 36.463 | 0 | 0 | 13.537 | 0 | - |
- April - 2021 |
No Image | |
1232 (OG) |
191608-180371 - Constr: & B/Topping of farm to Market road in Lower District Kurram. [MA] |
Kurram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50 | 13.537 | 36.463 | 36.463 | 0 | 0 | 13.537 | 0 | - |
- March - 2021 |
No Image | |
1232 (OG) |
191608-180371 - Constr: & B/Topping of farm to Market road in Lower District Kurram. [MA] |
Kurram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50 | 13.537 | 36.463 | 36.463 | 0 | 0 | 13.537 | 0 | - |
- February - 2021 |
No Image | |
1232 (OG) |
191608-180371 - Constr: & B/Topping of farm to Market road in Lower District Kurram. [MA] |
Kurram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50 | 13.537 | 36.463 | 36.463 | 0 | 0 | 13.537 | 0 | - |
- January - 2021 |
No Image | |
Pages : 1 |