Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1231 (OG) |
191633-170185-Execution of Rural Works Program / Improvement of Sewerage System in Mir Ali/ Miranshah in District North Waziristan. [MA] |
North Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 82.1 | 33.48 | 48.62 | 48.62 | 0 | 0 | 33.48 | 0 | - |
- December - 2020 |
No Image | |
1231 (OG) |
191633-170185-Execution of Rural Works Program / Improvement of Sewerage System in Mir Ali/ Miranshah in District North Waziristan. [MA] |
North Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 82.1 | 33.48 | 48.62 | 48.62 | 0 | 0 | 33.48 | 0 | - |
- December - 2020 |
No Image | |
1231 (OG) |
191633-170185-Execution of Rural Works Program / Improvement of Sewerage System in Mir Ali/ Miranshah in District North Waziristan. [MA] |
North Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 82.1 | 33.48 | 48.62 | 48.62 | 0 | 0 | 33.48 | 0 | - |
- October - 2020 |
No Image | |
1231 (OG) |
191633-170185-Execution of Rural Works Program / Improvement of Sewerage System in Mir Ali/ Miranshah in District North Waziristan. [MA] |
North Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 82.1 | 33.48 | 48.62 | 48.62 | 0 | 0 | 33.48 | 0 | - |
- September - 2020 |
No Image | |
1231 (OG) |
191633-170185-Execution of Rural Works Program / Improvement of Sewerage System in Mir Ali/ Miranshah in District North Waziristan. [MA] |
North Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 82.1 | 33.48 | 48.62 | 48.62 | 0 | 0 | 33.48 | 0 | - |
- August - 2020 |
No Image | |
1231 (OG) |
191633-170185-Execution of Rural Works Program / Improvement of Sewerage System in Mir Ali/ Miranshah in District North Waziristan. [MA] |
North Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 82.1 | 33.48 | 48.62 | 48.62 | 0 | 0 | 33.48 | 0 | - |
- May - 2021 |
No Image | |
1231 (OG) |
191633-170185-Execution of Rural Works Program / Improvement of Sewerage System in Mir Ali/ Miranshah in District North Waziristan. [MA] |
North Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 82.1 | 33.48 | 48.62 | 48.62 | 0 | 0 | 33.48 | 0 | - |
- April - 2021 |
No Image | |
1231 (OG) |
191633-170185-Execution of Rural Works Program / Improvement of Sewerage System in Mir Ali/ Miranshah in District North Waziristan. [MA] |
North Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 82.1 | 33.48 | 48.62 | 48.62 | 0 | 0 | 33.48 | 0 | - |
- March - 2021 |
No Image | |
1231 (OG) |
191633-170185-Execution of Rural Works Program / Improvement of Sewerage System in Mir Ali/ Miranshah in District North Waziristan. [MA] |
North Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 82.1 | 33.48 | 48.62 | 48.62 | 0 | 0 | 33.48 | 0 | - |
- February - 2021 |
No Image | |
1231 (OG) |
191633-170185-Execution of Rural Works Program / Improvement of Sewerage System in Mir Ali/ Miranshah in District North Waziristan. [MA] |
North Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 82.1 | 33.48 | 48.62 | 48.62 | 0 | 0 | 33.48 | 0 | - |
- January - 2021 |
No Image | |
1231 (OG) |
191633-170185-Execution of Rural Works Program / Improvement of Sewerage System in Mir Ali/ Miranshah in District North Waziristan. [MA] |
North Wazirstan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 82.1 | 33.48 | 48.62 | 0 | 0 | 0 | 33.48 | 0 |
July - 2020 |
No Image | ||
1231 (New) |
170658-Const of internal roads in PK-10, Distt. Peshawar. |
Peshawar HW |
- | - | - | 15-09-17 | - | 200 | 0 | 100 | 100 | 25 | 0 | 0 | 100 | 50% |
- December - 2017 |
Internal Roads 20 km - Work started. |
No Image |
1231 (New) |
170658-Const of internal roads in PK-10, Distt. Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 0 | 100 | 100 | 25 | 0 | 0 | 100 | 50% |
- November - 2017 |
Technical bids of contractor will be opened on 20/12/2017. |
No Image |
1231 (New) |
170658-Const of internal roads in PK-10, Distt. Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 0 | 100 | 100 | 0 | 0 | 0 | 100 | 50% |
- October - 2017 |
Technical bids of contractor approved. Court stay on financial bid opening. |
No Image |
1231 (New) |
170658-Const of internal roads in PK-10, Distt. Peshawar. |
Peshawar HW |
- | - | - | - | Line Deptt | 200 | 0 | 100 | 100 | 0 | 0 | 0 | 0 | - |
- September - 2017 |
PC-I/DCE for Rs.200 m submitted to Chief Infra P&D on 31/07/2017. Pre-PDWP held. Tender floated. |
No Image |
1231 (New) |
170658-Const of internal roads in PK-10, Distt. Peshawar. |
Peshawar HW |
- | - | - | - | Line Deptt | 200 | 0 | 100 | 100 | 0 | 0 | 0 | 0 | - |
- August - 2017 |
PC-I/DCE for Rs.200 m submitted to Chief Infra P&D on 31/07/2017. Pre-PDWP held. |
No Image |
1231 (New) |
170658-Const of internal roads in PK-10, Distt. Peshawar. |
Peshawar HW |
- | - | - | - | Line Deptt | 200 | 0 | 100 | 100 | 0 | 0 | 0 | 0 | - |
- July - 2017 |
PC-I/DCE for Rs.200 m submitted to Chief Infra P&D on 31/07/2017. |
No Image |
1231 (New) |
170658-Const of internal roads in PK-10, Distt. Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 0 | 100 | 100 | 100 | 100 | 100 | 100 | 50% |
50% June - 2018 |
Internal roads 20 Km - structure work in progress. |
No Image |
1) Construction of road from Jazz Tower Imdad Mir Koroona Talatan Ghalib Khel road and link road to BHU Ghali Khel 2.30 Km
2) Construction of road from Aza Khel to Naak Band 3 Km
3) Rehabilitation of road from Nawab Chowk Khanow UC Sherkara 2.90 Km
4) Construction of Sam No.1 road taking off from Zangali Canal to GPS Garhi Ghulam Muhammad 2.80 Km
5) Construction of Garhi Mumtaz road taking off from Hazar Khwani Canal 2 Km
6) Rehabilitation/construction of Kulu Daag Lara road at Badabera 2 Km
7) Improvement/rehabilitation of Ghaz Chowk to Rural Health Center Aza Khel Village 1 Km
8) Construction of road from Banat Kalay to Major House Mair Surizai 1.20 Km | |||||||||||||||||||
1231 (New) |
170658-Const of internal roads in PK-10, Distt. Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 0 | 100 | 100 | 100 | 75 | 75 | 100 | 50% |
38% May - 2018 |
Internal roads 20 Km - structure work in progress. |
No Image |
1) Construction of road from Jazz Tower Imdad Mir Koroona Talatan Ghalib Khel road and link road to BHU Ghali Khel 2.30 Km
2) Construction of road from Aza Khel to Naak Band 3 Km
3) Rehabilitation of road from Nawab Chowk Khanow UC Sherkara 2.90 Km
4) Construction of Sam No.1 road taking off from Zangali Canal to GPS Garhi Ghulam Muhammad 2.80 Km
5) Construction of Garhi Mumtaz road taking off from Hazar Khwani Canal 2 Km
6) Rehabilitation/construction of Kulu Daag Lara road at Badabera 2 Km
7) Improvement/rehabilitation of Ghaz Chowk to Rural Health Center Aza Khel Village 1 Km
8) Construction of road from Banat Kalay to Major House Mair Surizai 1.20 Km | |||||||||||||||||||
1231 (New) |
170658-Const of internal roads in PK-10, Distt. Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 0 | 100 | 100 | 100 | 67.968 | 67.968 | 100 | 50% |
34% April - 2018 |
Internal roads 20 Km - structure work in progress. |
No Image |
1) Construction of road from Jazz Tower Imdad Mir Koroona Talatan Ghalib Khel road and link road to BHU Ghali Khel 2.30 Km
2) Construction of road from Aza Khel to Naak Band 3 Km
3) Rehabilitation of road from Nawab Chowk Khanow UC Sherkara 2.90 Km
4) Construction of Sam No.1 road taking off from Zangali Canal to GPS Garhi Ghulam Muhammad 2.80 Km
5) Construction of Garhi Mumtaz road taking off from Hazar Khwani Canal 2 Km
6) Rehabilitation/construction of Kulu Daag Lara road at Badabera 2 Km
7) Improvement/rehabilitation of Ghaz Chowk to Rural Health Center Aza Khel Village 1 Km
8) Construction of road from Banat Kalay to Major House Mair Surizai 1.20 Km | |||||||||||||||||||
1231 (New) |
170658-Const of internal roads in PK-10, Distt. Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 0 | 100 | 100 | 75 | 54.59 | 54.59 | 100 | 50% |
27% March - 2018 |
Internal roads 20 Km - sub base completed, base course and structure work in progress. |
No Image |
1) Construction of road from Jazz Tower Imdad Mir Koroona Talatan Ghalib Khel road and link road to BHU Ghali Khel 2.30 Km
2) Construction of road from Aza Khel to Naak Band 3 Km
3) Rehabilitation of road from Nawab Chowk Khanow UC Sherkara 2.90 Km
4) Construction of Sam No.1 road taking off from Zangali Canal to GPS Garhi Ghulam Muhammad 2.80 Km
5) Construction of Garhi Mumtaz road taking off from Hazar Khwani Canal 2 Km
6) Rehabilitation/construction of Kulu Daag Lara road at Badabera 2 Km
7) Improvement/rehabilitation of Ghaz Chowk to Rural Health Center Aza Khel Village 1 Km
8) Construction of road from Banat Kalay to Major House Mair Surizai 1.20 Km | |||||||||||||||||||
1231 (New) |
170658-Const of internal roads in PK-10, Distt. Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 0 | 100 | 100 | 25 | 25 | 25 | 100 | 50% |
13% February - 2018 |
Internal Roads 20 Km - sub base completed, base course and structure work in progress. |
No Image |
1) Construction of road from Jazz Tower Imdad Mir Koroona Talatan Ghalib Khel road and link road to BHU Ghali Khel 2.30 Km
2) Construction of road from Aza Khel to Naak Band 3 Km
3) Rehabilitation of road from Nawab Chowk Khanow UC Sherkara 2.90 Km
4) Construction of Sam No.1 road taking off from Zangali Canal to GPS Garhi Ghulam Muhammad 2.80 Km
5) Construction of Garhi Mumtaz road taking off from Hazar Khwani Canal 2 Km
6) Rehabilitation/construction of Kulu Daag Lara road at Badabera 2 Km
7) Improvement/rehabilitation of Ghaz Chowk to Rural Health Center Aza Khel Village 1 Km
8) Construction of road from Banat Kalay to Major House Mair Surizai 1.20 Km | |||||||||||||||||||
1231 (New) |
170658-Const of internal roads in PK-10, Distt. Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 0 | 100 | 100 | 25 | 25 | 25 | 100 | 50% |
13% January - 2018 |
Internal Roads 20 Km - work started. |
No Image |
Pages : 1 |