Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1228 (New) |
170571-Improvement / Rehabilitation of Black Topped road from Gurguri Bypass road to Manji Khel via Gurguri Bazar Tehsil Banda Daud Shah PK-40 (205 Km), District Karak. |
Karak |
28-11-17 | - | - | 18-07-17 | - | 42.134 | 0 | 5 | 5 | 1.25 | 1.25 | 1.25 | 37.134 | 12% |
3% December - 2017 |
Length 2.51 Km - work strated. |
No Image |
1228 (New) |
170571-Improvement / Rehabilitation of Black Topped road from Gurguri Bypass road to Manji Khel via Gurguri Bazar Tehsil Banda Daud Shah PK-40 (205 Km), District Karak. |
Karak |
- | - | - | 18-07-17 | - | 42.134 | 0 | 5 | 5 | 0 | 0 | 0 | 37.134 | 12% |
- September - 2017 |
Technical proposal of contractor submitted to CE. |
No Image |
1228 (New) |
170571-Improvement / Rehabilitation of Black Topped road from Gurguri Bypass road to Manji Khel via Gurguri Bazar Tehsil Banda Daud Shah PK-40 (205 Km), District Karak. |
Karak |
- | - | - | 18-07-17 | - | 42.134 | 0 | 5 | 5 | 0 | 0 | 0 | 37.134 | 12% |
- August - 2017 |
Procurement under process. |
No Image |
1228 (New) |
170571-Improvement / Rehabilitation of Black Topped road from Gurguri Bypass road to Manji Khel via Gurguri Bazar Tehsil Banda Daud Shah PK-40 (205 Km), District Karak. |
Karak |
- | - | - | - | Line Deptt | 42.134 | 0 | 5 | 5 | 0 | 0 | 0 | 0 | - |
- July - 2017 |
Approved. AA Awaited. |
No Image |
1228 (New) |
170571-Improvement / Rehabilitation of Black Topped road from Gurguri Bypass road to Manji Khel via Gurguri Bazar Tehsil Banda Daud Shah PK-40 (205 Km), District Karak. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 42.134 | 0 | 5 | 5 | 1.25 | 0 | 0 | 37.134 | 12% |
- November - 2017 |
Work strated |
No Image |
1228 (New) |
170571-Improvement / Rehabilitation of Black Topped road from Gurguri Bypass road to Manji Khel via Gurguri Bazar Tehsil Banda Daud Shah PK-40 (205 Km), District Karak. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 42.134 | 0 | 5 | 5 | 0 | 0 | 0 | 37.134 | 12% |
- October - 2017 |
Tender approval under process. |
No Image |
1228 (New) |
170571-Improvement / Rehabilitation of Black Topped road from Gurguri Bypass road to Manji Khel via Gurguri Bazar Tehsil Banda Daud Shah PK-40 (205 Km), District Karak. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 42.134 | 0 | 5 | 1.25 | 1.25 | 1.25 | 1.25 | 37.134 | 12% |
3% June - 2018 |
Length 2.51 Km (width 12 ft) - work strated. |
No Image |
Karak | |||||||||||||||||||
1228 (New) |
170571-Improvement / Rehabilitation of Black Topped road from Gurguri Bypass road to Manji Khel via Gurguri Bazar Tehsil Banda Daud Shah PK-40 (205 Km), District Karak. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 42.134 | 0 | 5 | 5 | 5 | 1.25 | 1.25 | 37.134 | 12% |
3% May - 2018 |
Length 2.51 Km (width 12 ft) - work strated. |
No Image |
Karak | |||||||||||||||||||
1228 (New) |
170571-Improvement / Rehabilitation of Black Topped road from Gurguri Bypass road to Manji Khel via Gurguri Bazar Tehsil Banda Daud Shah PK-40 (205 Km), District Karak. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 42.134 | 0 | 5 | 5 | 5 | 1.25 | 1.25 | 37.134 | 12% |
3% April - 2018 |
Length 2.51 Km (width 12 ft) - work strated. Rs.10 m demanded. |
No Image |
Karak | |||||||||||||||||||
1228 (New) |
170571-Improvement / Rehabilitation of Black Topped road from Gurguri Bypass road to Manji Khel via Gurguri Bazar Tehsil Banda Daud Shah PK-40 (205 Km), District Karak. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 42.134 | 0 | 5 | 5 | 5 | 1.25 | 1.25 | 37.134 | 12% |
3% March - 2018 |
Length 2.51 Km (width -12 ft ) - work strated. |
No Image |
Karak | |||||||||||||||||||
1228 (New) |
170571-Improvement / Rehabilitation of Black Topped road from Gurguri Bypass road to Manji Khel via Gurguri Bazar Tehsil Banda Daud Shah PK-40 (205 Km), District Karak. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 42.134 | 0 | 5 | 5 | 1.25 | 1.25 | 1.25 | 37.134 | 12% |
3% February - 2018 |
Length 2.51 Km (width -12 ft ) - work strated. |
No Image |
Karak | |||||||||||||||||||
1228 (New) |
170571-Improvement / Rehabilitation of Black Topped road from Gurguri Bypass road to Manji Khel via Gurguri Bazar Tehsil Banda Daud Shah PK-40 (205 Km), District Karak. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 42.134 | 0 | 5 | 5 | 1.25 | 1.25 | 1.25 | 37.134 | 12% |
3% January - 2018 |
Length 2.51 Km - work strated. |
No Image |
Karak | |||||||||||||||||||
1228 (OG) |
191640-170313-Rural Works Program in District South Waziristan. [MA] |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 86.2 | 0 | 86.2 | 86.2 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
No Image | |
1228 (OG) |
191640-170313-Rural Works Program in District South Waziristan. [MA] |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 86.2 | 0 | 86.2 | 86.2 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
No Image | |
1228 (OG) |
191640-170313-Rural Works Program in District South Waziristan. [MA] |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 86.2 | 0 | 86.2 | 86.2 | 0 | 0 | 0 | 0 | - |
- October - 2020 |
No Image | |
1228 (OG) |
191640-170313-Rural Works Program in District South Waziristan. [MA] |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 86.2 | 0 | 86.2 | 86.2 | 0 | 0 | 0 | 0 | - |
- September - 2020 |
No Image | |
1228 (OG) |
191640-170313-Rural Works Program in District South Waziristan. [MA] |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 86.2 | 0 | 86.2 | 86.2 | 0 | 0 | 0 | 0 | - |
- August - 2020 |
No Image | |
1228 (OG) |
191640-170313-Rural Works Program in District South Waziristan. [MA] |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 86.2 | 0 | 86.2 | 86.2 | 0 | 0 | 0 | 0 | - |
- May - 2021 |
No Image | |
1228 (OG) |
191640-170313-Rural Works Program in District South Waziristan. [MA] |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 86.2 | 0 | 86.2 | 86.2 | 0 | 0 | 0 | 0 | - |
- April - 2021 |
No Image | |
1228 (OG) |
191640-170313-Rural Works Program in District South Waziristan. [MA] |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 86.2 | 0 | 86.2 | 86.2 | 0 | 0 | 0 | 0 | - |
- March - 2021 |
No Image | |
1228 (OG) |
191640-170313-Rural Works Program in District South Waziristan. [MA] |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 86.2 | 0 | 86.2 | 86.2 | 0 | 0 | 0 | 0 | - |
- February - 2021 |
No Image | |
1228 (OG) |
191640-170313-Rural Works Program in District South Waziristan. [MA] |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 86.2 | 0 | 86.2 | 86.2 | 0 | 0 | 0 | 0 | - |
- January - 2021 |
No Image | |
1228 (OG) |
191640-170313-Rural Works Program in District South Waziristan. [MA] |
South Wazirstan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 86.2 | 0 | 86.2 | 0 | 0 | 0 | 0 | 0 |
- July - 2020 |
No Image | ||