Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1219 (OG) |
160189-Improvement and widening of Suraj Gali Hattar road (6.50 Kms), District Haripur. |
Haripur |
- | - | - | 23-12-16 | - | 116.536 | 0 | 40 | 35 | 19.2 | 24.749 | 24.749 | 76.536 | 34% |
21% December - 2017 |
Length 6.5 Km- Earth work, structure work started. |
No Image |
1219 (OG) |
160189-Improvement and widening of Suraj Gali Hattar road (6.50 Kms), District Haripur. |
Haripur |
- | - | - | 23-12-16 | - | 116.536 | 0 | 40 | 40 | 14.75 | 8 | 8 | 76.536 | 34% |
7% September - 2017 |
Earth work, structure work started. |
No Image |
1219 (OG) |
160189-Improvement and widening of Suraj Gali Hattar road (6.50 Kms), District Haripur. |
Haripur |
- | - | - | 23-12-16 | - | 116.536 | 0 | 40 | 40 | 14.75 | 7.39 | 7.39 | 76.536 | 34% |
6% August - 2017 |
Earth work, structure work started. |
No Image |
1219 (OG) |
160189-Improvement and widening of Suraj Gali Hattar road (6.50 Kms), District Haripur. |
Haripur |
- | - | - | 23-12-16 | - | 116.536 | 0 | 40 | 40 | 14.2 | 0 | 0 | 76.536 | 34% |
- July - 2017 |
Work started. |
No Image |
1219 (OG) |
160189-Improvement and widening of Suraj Gali Hattar road (6.50 Kms), District Haripur. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 116.536 | 0 | 40 | 40 | 24.2 | 18.557 | 18.557 | 76.536 | 34% |
16% November - 2017 |
length 6.5 km- Earth work, structure work started. |
No Image |
1219 (OG) |
160189-Improvement and widening of Suraj Gali Hattar road (6.50 Kms), District Haripur. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 116.536 | 0 | 40 | 40 | 14.75 | 14.75 | 14.75 | 76.536 | 34% |
13% October - 2017 |
Earth work, structure work started. |
No Image |
1219 (OG) |
160189-Improvement and widening of Suraj Gali Hattar road (6.50 Kms), District Haripur. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 116.536 | 0 | 40 | 45 | 45 | 44.2 | 44.2 | 76.536 | 34% |
38% June - 2018 |
Length 6.5 Km - 80% earth work, 60% structure work completed. |
No Image |
Haripur | |||||||||||||||||||
1219 (OG) |
160189-Improvement and widening of Suraj Gali Hattar road (6.50 Kms), District Haripur. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 116.536 | 0 | 40 | 45 | 45 | 44.2 | 44.2 | 76.536 | 34% |
38% May - 2018 |
Length 6.5 Km - 80% earth work, 60% structure work completed. |
No Image |
Haripur | |||||||||||||||||||
1219 (OG) |
160189-Improvement and widening of Suraj Gali Hattar road (6.50 Kms), District Haripur. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 116.536 | 0 | 40 | 35 | 35 | 34.2 | 34.2 | 76.536 | 34% |
29% April - 2018 |
Length 6.5 Km - 80% earth work, 60% structure work completed. |
No Image |
Haripur | |||||||||||||||||||
1219 (OG) |
160189-Improvement and widening of Suraj Gali Hattar road (6.50 Kms), District Haripur. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 116.536 | 0 | 40 | 29.2 | 29.2 | 24.749 | 24.749 | 76.536 | 34% |
21% March - 2018 |
Length 6.5 Km - 80% earth work, 60% structure work completed. |
No Image |
Haripur | |||||||||||||||||||
1219 (OG) |
160189-Improvement and widening of Suraj Gali Hattar road (6.50 Kms), District Haripur. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 116.536 | 0 | 40 | 35 | 24.75 | 24.749 | 24.749 | 76.536 | 34% |
21% February - 2018 |
Length 6.5 Km - earth work, structure work started. |
ADP's Images |
Haripur | |||||||||||||||||||
1219 (OG) |
160189-Improvement and widening of Suraj Gali Hattar road (6.50 Kms), District Haripur. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 116.536 | 0 | 40 | 35 | 24.75 | 24.749 | 24.749 | 76.536 | 34% |
21% January - 2018 |
Length 6.5 Km - earth work, structure work started. |
No Image |
1219 (New) |
190401-Construction of Slaughter Houses in Selected Tehsils of Khyber Pakhtunkhwa |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 300 | 0 | 30 | 30 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
No Image | |
1219 (New) |
190401-Construction of Slaughter Houses in Selected Tehsils of Khyber Pakhtunkhwa |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 300 | 0 | 30 | 30 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
No Image | |
1219 (New) |
190401-Construction of Slaughter Houses in Selected Tehsils of Khyber Pakhtunkhwa |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 300 | 0 | 30 | 30 | 0 | 0 | 0 | 0 | - |
- October - 2020 |
No Image | |
1219 (New) |
190401-Construction of Slaughter Houses in Selected Tehsils of Khyber Pakhtunkhwa |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 300 | 0 | 30 | 30 | 0 | 0 | 0 | 0 | - |
- September - 2020 |
No Image | |
1219 (New) |
190401-Construction of Slaughter Houses in Selected Tehsils of Khyber Pakhtunkhwa |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 300 | 0 | 30 | 30 | 0 | 0 | 0 | 0 | - |
- August - 2020 |
No Image | |
1219 (New) |
190401-Construction of Slaughter Houses in Selected Tehsils of Khyber Pakhtunkhwa |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 300 | 0 | 30 | 0 | 0 | 0 | 0 | 0 | - |
- July - 2020 |
No Image | |
1219 (New) |
190401-Construction of Slaughter Houses in Selected Tehsils of Khyber Pakhtunkhwa |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 300 | 0 | 30 | 30 | 0 | 0 | 0 | 0 | - |
- May - 2021 |
No Image | |
1219 (New) |
190401-Construction of Slaughter Houses in Selected Tehsils of Khyber Pakhtunkhwa |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 300 | 0 | 30 | 30 | 0 | 0 | 0 | 0 | - |
- April - 2021 |
No Image | |
1219 (New) |
190401-Construction of Slaughter Houses in Selected Tehsils of Khyber Pakhtunkhwa |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 300 | 0 | 30 | 30 | 0 | 0 | 0 | 0 | - |
- March - 2021 |
No Image | |
1219 (New) |
190401-Construction of Slaughter Houses in Selected Tehsils of Khyber Pakhtunkhwa |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 300 | 0 | 30 | 30 | 0 | 0 | 0 | 0 | - |
- February - 2021 |
No Image | |
1219 (New) |
190401-Construction of Slaughter Houses in Selected Tehsils of Khyber Pakhtunkhwa |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 300 | 0 | 30 | 30 | 0 | 0 | 0 | 0 | - |
- January - 2021 |
No Image | |
Pages : 1 |