Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2018, January - 2021, February - 2018, February - 2021, March - 2018, March - 2021, April - 2018, April - 2021, May - 2018, May - 2021, June - 2018, July - 2017, July - 2020, August - 2017, August - 2020, September - 2017, September - 2020, October - 2017, October - 2020, November - 2017, December - 2017, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1219
(OG)
160189-Improvement and widening of Suraj Gali Hattar road (6.50 Kms), District Haripur.
Haripur
- - - 23-12-16 - 116.536 0 40 35 19.2 24.749 24.749 76.536 34% 21%
December - 2017
Length 6.5 Km- Earth work, structure work started.
No Image
1219
(OG)
160189-Improvement and widening of Suraj Gali Hattar road (6.50 Kms), District Haripur.
Haripur
- - - 23-12-16 - 116.536 0 40 40 14.75 8 8 76.536 34% 7%
September - 2017
Earth work, structure work started.
No Image
1219
(OG)
160189-Improvement and widening of Suraj Gali Hattar road (6.50 Kms), District Haripur.
Haripur
- - - 23-12-16 - 116.536 0 40 40 14.75 7.39 7.39 76.536 34% 6%
August - 2017
Earth work, structure work started.
No Image
1219
(OG)
160189-Improvement and widening of Suraj Gali Hattar road (6.50 Kms), District Haripur.
Haripur
- - - 23-12-16 - 116.536 0 40 40 14.2 0 0 76.536 34% -
July - 2017
Work started.
No Image
1219
(OG)
160189-Improvement and widening of Suraj Gali Hattar road (6.50 Kms), District Haripur.
Haripur
30-11--1 30-11--1 - 30-11--1 - 116.536 0 40 40 24.2 18.557 18.557 76.536 34% 16%
November - 2017
length 6.5 km- Earth work, structure work started.
No Image
1219
(OG)
160189-Improvement and widening of Suraj Gali Hattar road (6.50 Kms), District Haripur.
Haripur
30-11--1 30-11--1 - 30-11--1 - 116.536 0 40 40 14.75 14.75 14.75 76.536 34% 13%
October - 2017
Earth work, structure work started.
No Image
1219
(OG)
160189-Improvement and widening of Suraj Gali Hattar road (6.50 Kms), District Haripur.
Haripur
30-11--1 30-11--1 - 30-11--1 - 116.536 0 40 45 45 44.2 44.2 76.536 34% 38%
June - 2018
Length 6.5 Km - 80% earth work, 60% structure work completed.
No Image
Haripur
1219
(OG)
160189-Improvement and widening of Suraj Gali Hattar road (6.50 Kms), District Haripur.
Haripur
30-11--1 30-11--1 - 30-11--1 - 116.536 0 40 45 45 44.2 44.2 76.536 34% 38%
May - 2018
Length 6.5 Km - 80% earth work, 60% structure work completed.
No Image
Haripur
1219
(OG)
160189-Improvement and widening of Suraj Gali Hattar road (6.50 Kms), District Haripur.
Haripur
30-11--1 30-11--1 - 30-11--1 - 116.536 0 40 35 35 34.2 34.2 76.536 34% 29%
April - 2018
Length 6.5 Km - 80% earth work, 60% structure work completed.
No Image
Haripur
1219
(OG)
160189-Improvement and widening of Suraj Gali Hattar road (6.50 Kms), District Haripur.
Haripur
30-11--1 30-11--1 - 30-11--1 - 116.536 0 40 29.2 29.2 24.749 24.749 76.536 34% 21%
March - 2018
Length 6.5 Km - 80% earth work, 60% structure work completed.
No Image
Haripur
1219
(OG)
160189-Improvement and widening of Suraj Gali Hattar road (6.50 Kms), District Haripur.
Haripur
30-11--1 30-11--1 - 30-11--1 - 116.536 0 40 35 24.75 24.749 24.749 76.536 34% 21%
February - 2018
Length 6.5 Km - earth work, structure work started.
ADP's Images
Haripur
1219
(OG)
160189-Improvement and widening of Suraj Gali Hattar road (6.50 Kms), District Haripur.
Haripur
30-11--1 30-11--1 - 30-11--1 - 116.536 0 40 35 24.75 24.749 24.749 76.536 34% 21%
January - 2018
Length 6.5 Km - earth work, structure work started.
No Image
1219
(New)
190401-Construction of Slaughter Houses in Selected Tehsils of Khyber Pakhtunkhwa
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 300 0 30 30 0 0 0 0 - -
December - 2020
No Image
1219
(New)
190401-Construction of Slaughter Houses in Selected Tehsils of Khyber Pakhtunkhwa
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 300 0 30 30 0 0 0 0 - -
December - 2020
No Image
1219
(New)
190401-Construction of Slaughter Houses in Selected Tehsils of Khyber Pakhtunkhwa
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 300 0 30 30 0 0 0 0 - -
October - 2020
No Image
1219
(New)
190401-Construction of Slaughter Houses in Selected Tehsils of Khyber Pakhtunkhwa
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 300 0 30 30 0 0 0 0 - -
September - 2020
No Image
1219
(New)
190401-Construction of Slaughter Houses in Selected Tehsils of Khyber Pakhtunkhwa
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 300 0 30 30 0 0 0 0 - -
August - 2020
No Image
1219
(New)
190401-Construction of Slaughter Houses in Selected Tehsils of Khyber Pakhtunkhwa
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 300 0 30 0 0 0 0 0 - -
July - 2020
No Image
1219
(New)
190401-Construction of Slaughter Houses in Selected Tehsils of Khyber Pakhtunkhwa
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 300 0 30 30 0 0 0 0 - -
May - 2021
No Image
1219
(New)
190401-Construction of Slaughter Houses in Selected Tehsils of Khyber Pakhtunkhwa
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 300 0 30 30 0 0 0 0 - -
April - 2021
No Image
1219
(New)
190401-Construction of Slaughter Houses in Selected Tehsils of Khyber Pakhtunkhwa
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 300 0 30 30 0 0 0 0 - -
March - 2021
No Image
1219
(New)
190401-Construction of Slaughter Houses in Selected Tehsils of Khyber Pakhtunkhwa
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 300 0 30 30 0 0 0 0 - -
February - 2021
No Image
1219
(New)
190401-Construction of Slaughter Houses in Selected Tehsils of Khyber Pakhtunkhwa
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 300 0 30 30 0 0 0 0 - -
January - 2021
No Image
Pages : 1