Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1211 (OG) |
150686-Construction of roads (a) Mohari to Akhun Bandi Bridge (b) Durnian to Thipra to Mirupur Kahal road (c) Talhad village road and (d) Badshaia to Rehana Maira road District Haripur. |
Haripur |
25-12-15 | - | - | 10-09-15 | - | 150 | 131.917 | 10 | 13 | 8 | 7.238 | 139.155 | 8.083 | 95% |
93% December - 2017 |
Length 13.3 Km - earth work and structure work in progress. Revised PC-I/DCE for Rs.184 m submitted to SOR on 11/08/2017. Pre-PDWP held. Referred to DG M&E. |
No Image |
1211 (OG) |
150686-Construction of roads (a) Mohari to Akhun Bandi Bridge (b) Durnian to Thipra to Mirupur Kahal road (c) Talhad village road and (d) Badshaia to Rehana Maira road District Haripur. |
Haripur |
25-12-15 | - | - | 10-09-15 | - | 150 | 131.917 | 10 | 10 | 8 | 3.5 | 135.417 | 8.083 | 95% |
90% September - 2017 |
Length 13.3 Km - earth work and structure work in progress. Revised PC-I/DCE for Rs.184 m submitted to SOR on 11/08/2017. Pre-PDWP held. Referred to DG M&E. |
No Image |
1211 (OG) |
150686-Construction of roads (a) Mohari to Akhun Bandi Bridge (b) Durnian to Thipra to Mirupur Kahal road (c) Talhad village road and (d) Badshaia to Rehana Maira road District Haripur. |
Haripur |
25-12-15 | - | - | 10-09-15 | - | 150 | 131.917 | 10 | 10 | 3.55 | 3.5 | 135.417 | 8.083 | 95% |
90% August - 2017 |
Length 13.3 Km - earth work and structure work in progress. Revised PC-I/DCE for Rs.184 m submitted to SOR on 11/08/2017. |
No Image |
1211 (OG) |
150686-Construction of roads (a) Mohari to Akhun Bandi Bridge (b) Durnian to Thipra to Mirupur Kahal road (c) Talhad village road and (d) Badshaia to Rehana Maira road District Haripur. |
Haripur |
25-12-15 | - | - | 10-09-15 | - | 150 | 131.917 | 10 | 10 | 3.55 | 0 | 131.917 | 8.083 | 95% |
88% July - 2017 |
Length 13.3 Km - earth work and structure work in progress. |
No Image |
1211 (OG) |
150686-Construction of roads (a) Mohari to Akhun Bandi Bridge (b) Durnian to Thipra to Mirupur Kahal road (c) Talhad village road and (d) Badshaia to Rehana Maira road District Haripur. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 131.917 | 10 | 13 | 8 | 7.188 | 139.105 | 8.083 | 95% |
93% November - 2017 |
Length 13.3 Km - earth work and structure work in progress. Revised PC-I/DCE for Rs.184 m submitted to SOR on 11/08/2017. Pre-PDWP held. Referred to DG M&E. |
No Image |
1211 (OG) |
150686-Construction of roads (a) Mohari to Akhun Bandi Bridge (b) Durnian to Thipra to Mirupur Kahal road (c) Talhad village road and (d) Badshaia to Rehana Maira road District Haripur. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 131.917 | 10 | 10 | 8 | 3.5 | 135.417 | 8.083 | 95% |
90% October - 2017 |
Length 13.3 Km - earth work and structure work in progress. Revised PC-I/DCE for Rs.184 m submitted to SOR on 11/08/2017. Pre-PDWP held. Referred to DG M&E. |
No Image |
1211 (OG) |
150686-Construction of roads (a) Mohari to Akhun Bandi Bridge (b) Durnian to Thipra to Mirupur Kahal road (c) Talhad village road and (d) Badshaia to Rehana Maira road District Haripur. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 184 | 131.917 | 10 | 28.495 | 28.495 | 14.508 | 146.425 | 42.083 | 77% |
80% June - 2018 |
Length 13.3 Km width 12 ft - earth work and structure work in progress. |
No Image |
Haripur | |||||||||||||||||||
1211 (OG) |
150686-Construction of roads (a) Mohari to Akhun Bandi Bridge (b) Durnian to Thipra to Mirupur Kahal road (c) Talhad village road and (d) Badshaia to Rehana Maira road District Haripur. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 184 | 131.917 | 10 | 28.495 | 28.495 | 14.508 | 146.425 | 42.083 | 77% |
80% May - 2018 |
Length 13.3 Km width 12 ft - earth work and structure work in progress. |
No Image |
Haripur | |||||||||||||||||||
1211 (OG) |
150686-Construction of roads (a) Mohari to Akhun Bandi Bridge (b) Durnian to Thipra to Mirupur Kahal road (c) Talhad village road and (d) Badshaia to Rehana Maira road District Haripur. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 184 | 131.917 | 10 | 28.495 | 28.495 | 10.446 | 142.363 | 42.083 | 77% |
77% April - 2018 |
Length 13.3 Km width 12 ft - earth work and structure work in progress. |
No Image |
Haripur | |||||||||||||||||||
1211 (OG) |
150686-Construction of roads (a) Mohari to Akhun Bandi Bridge (b) Durnian to Thipra to Mirupur Kahal road (c) Talhad village road and (d) Badshaia to Rehana Maira road District Haripur. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 131.917 | 10 | 28.495 | 28.495 | 7.238 | 139.155 | 8.083 | 95% |
93% March - 2018 |
Length 13.3 Km width 12 ft - earth work and structure work in progress. Revised PC-I/DCE for Rs.184 m submitted to SOR on 11/08/2017. Pre-PDWP held. Referred to DG M&E. Discussed in PDWP meeting. Deffered due to non - implementation on decision of M&E reports. |
No Image |
Haripur | |||||||||||||||||||
1211 (OG) |
150686-Construction of roads (a) Mohari to Akhun Bandi Bridge (b) Durnian to Thipra to Mirupur Kahal road (c) Talhad village road and (d) Badshaia to Rehana Maira road District Haripur. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 131.917 | 10 | 25.805 | 25.805 | 7.238 | 139.155 | 8.083 | 95% |
93% February - 2018 |
Length 13.3 Km width 12 ft- earth work and structure work in progress. Revised PC-I/DCE for Rs.184 m submitted to SOR on 11/08/2017. Pre-PDWP held. Referred to DG M&E. Discussed in PDWP meeting . Deffered due to non - implementation on desicuion of M&E Reports |
No Image |
Haripur | |||||||||||||||||||
1211 (OG) |
150686-Construction of roads (a) Mohari to Akhun Bandi Bridge (b) Durnian to Thipra to Mirupur Kahal road (c) Talhad village road and (d) Badshaia to Rehana Maira road District Haripur. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 131.917 | 10 | 25.805 | 25.805 | 7.238 | 139.155 | 8.083 | 95% |
93% January - 2018 |
Length 13.3 Km - earth work and structure work in progress. Revised PC-I/DCE for Rs.184 m submitted to SOR on 11/08/2017. Pre-PDWP held. Referred to DG M&E. |
No Image |
1211 (New) |
200299-Development Works in UC 36,42, 43, 44, 48, 64, 65, 66, 69, 70, 71, 80, 92, Peshawar |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 200 | 0 | 5 | 5 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
No Image | |
1211 (New) |
200299-Development Works in UC 36,42, 43, 44, 48, 64, 65, 66, 69, 70, 71, 80, 92, Peshawar |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 200 | 0 | 5 | 5 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
No Image | |
1211 (New) |
200299-Development Works in UC 36,42, 43, 44, 48, 64, 65, 66, 69, 70, 71, 80, 92, Peshawar |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 200 | 0 | 5 | 5 | 0 | 0 | 0 | 0 | - |
- October - 2020 |
No Image | |
1211 (New) |
200299-Development Works in UC 36,42, 43, 44, 48, 64, 65, 66, 69, 70, 71, 80, 92, Peshawar |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 200 | 0 | 5 | 5 | 0 | 0 | 0 | 0 | - |
- September - 2020 |
No Image | |
1211 (New) |
200299-Development Works in UC 36,42, 43, 44, 48, 64, 65, 66, 69, 70, 71, 80, 92, Peshawar |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 200 | 0 | 5 | 5 | 0 | 0 | 0 | 0 | - |
- August - 2020 |
No Image | |
1211 (New) |
200299-Development Works in UC 36,42, 43, 44, 48, 64, 65, 66, 69, 70, 71, 80, 92, Peshawar |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 200 | 0 | 5 | 0 | 0 | 0 | 0 | 0 |
- July - 2020 |
No Image | ||
1211 (New) |
200299-Development Works in UC 36,42, 43, 44, 48, 64, 65, 66, 69, 70, 71, 80, 92, Peshawar |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 200 | 0 | 5 | 5 | 0 | 0 | 0 | 0 | - |
- May - 2021 |
No Image | |
1211 (New) |
200299-Development Works in UC 36,42, 43, 44, 48, 64, 65, 66, 69, 70, 71, 80, 92, Peshawar |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 200 | 0 | 5 | 5 | 0 | 0 | 0 | 0 | - |
- April - 2021 |
No Image | |
1211 (New) |
200299-Development Works in UC 36,42, 43, 44, 48, 64, 65, 66, 69, 70, 71, 80, 92, Peshawar |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 200 | 0 | 5 | 5 | 0 | 0 | 0 | 0 | - |
- March - 2021 |
No Image | |
1211 (New) |
200299-Development Works in UC 36,42, 43, 44, 48, 64, 65, 66, 69, 70, 71, 80, 92, Peshawar |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 200 | 0 | 5 | 5 | 0 | 0 | 0 | 0 | - |
- February - 2021 |
No Image | |
1211 (New) |
200299-Development Works in UC 36,42, 43, 44, 48, 64, 65, 66, 69, 70, 71, 80, 92, Peshawar |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 200 | 0 | 5 | 5 | 0 | 0 | 0 | 0 | - |
- January - 2021 |
No Image | |
Pages : 1 |