Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1210 (OG) |
150222-Construction of BT road from Makhnial to Danna Ferozpur Road, District Haripur. |
Haripur |
18-05-16 | 30-06-18 | - | 28-08-15 | - | 48.291 | 35.762 | 7.5 | 7.5 | 3.751 | 3.75 | 39.512 | 5.029 | 90% |
82% December - 2017 |
Length 2 Km - 1.8 Km completed. NOC for remaining portion awaited from Forest Deptt. |
No Image |
1210 (OG) |
150222-Construction of BT road from Makhnial to Danna Ferozpur Road, District Haripur. |
Haripur |
18-05-16 | 30-06-18 | - | 28-08-15 | - | 48.291 | 35.762 | 7.5 | 7.5 | 3.751 | 0 | 35.762 | 5.029 | 90% |
74% September - 2017 |
Length 2 Km - 1.8 Km completed. NOC for remaining portion awaited from Forest Dept. |
No Image |
1210 (OG) |
150222-Construction of BT road from Makhnial to Danna Ferozpur Road, District Haripur. |
Haripur |
18-05-16 | 30-06-18 | - | 28-08-15 | - | 48.291 | 35.762 | 7.5 | 7.5 | 2.663 | 0 | 35.762 | 5.029 | 90% |
74% August - 2017 |
Length 2 Km - subtantially complted. |
No Image |
1210 (OG) |
150222-Construction of BT road from Makhnial to Danna Ferozpur Road, District Haripur. |
Haripur |
18-05-16 | 30-06-18 | - | 28-08-15 | - | 48.291 | 35.762 | 7.5 | 7.5 | 2.663 | 0 | 35.762 | 5.029 | 90% |
74% July - 2017 |
Length 2 Km - earth work 90% completed, structure work in progress. |
No Image |
1210 (OG) |
150222-Construction of BT road from Makhnial to Danna Ferozpur Road, District Haripur. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 48.291 | 35.762 | 7.5 | 7.5 | 3.751 | 3.75 | 39.512 | 5.029 | 90% |
82% November - 2017 |
Length 2 Km - 1.8 Km completed. NOC for remaining portion awaited from Forest Dept. |
No Image |
1210 (OG) |
150222-Construction of BT road from Makhnial to Danna Ferozpur Road, District Haripur. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 48.291 | 35.762 | 7.5 | 7.5 | 3.751 | 0 | 35.762 | 5.029 | 90% |
74% October - 2017 |
Length 2 Km - 1.8 Km completed. NOC for remaining portion awaited from Forest Dept. |
No Image |
1210 (OG) |
150222-Construction of BT road from Makhnial to Danna Ferozpur Road, District Haripur. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 48.291 | 35.762 | 7.5 | 7.5 | 7.5 | 7.5 | 43.262 | 5.029 | 90% |
90% June - 2018 |
Length 2 Km width - 1.8 Km completed. NOC for remaining portion awaited from Forest Deptt. |
No Image |
2 Km, Haripur | |||||||||||||||||||
1210 (OG) |
150222-Construction of BT road from Makhnial to Danna Ferozpur Road, District Haripur. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 48.291 | 35.762 | 7.5 | 7.5 | 7.5 | 7.5 | 43.262 | 5.029 | 90% |
90% May - 2018 |
Length 2 Km width - 1.8 Km completed. NOC for remaining portion awaited from Forest Deptt. |
No Image |
2 Km, Haripur | |||||||||||||||||||
1210 (OG) |
150222-Construction of BT road from Makhnial to Danna Ferozpur Road, District Haripur. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 48.291 | 35.762 | 7.5 | 7.5 | 7.5 | 3.75 | 39.512 | 5.029 | 90% |
82% April - 2018 |
Length 2 Km width - 1.8 Km completed. NOC for remaining portion awaited from Forest Deptt. |
No Image |
2 Km, Haripur | |||||||||||||||||||
1210 (OG) |
150222-Construction of BT road from Makhnial to Danna Ferozpur Road, District Haripur. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 48.291 | 35.762 | 7.5 | 7.5 | 3.751 | 3.75 | 39.512 | 5.029 | 90% |
82% March - 2018 |
Length 2 Km width - 1.8 Km completed. NOC for remaining portion awaited from Forest Deptt. |
No Image |
2 Km, Haripur | |||||||||||||||||||
1210 (OG) |
150222-Construction of BT road from Makhnial to Danna Ferozpur Road, District Haripur. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 48.291 | 35.762 | 7.5 | 7.5 | 3.751 | 3.75 | 39.512 | 5.029 | 90% |
82% February - 2018 |
Length 2 Km width - 1.8 Km completed. NOC for remaining portion awaited from Forest Deptt. |
No Image |
2 Km, Haripur | |||||||||||||||||||
1210 (OG) |
150222-Construction of BT road from Makhnial to Danna Ferozpur Road, District Haripur. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 48.291 | 35.762 | 7.5 | 7.5 | 3.751 | 3.75 | 39.512 | 5.029 | 90% |
82% January - 2018 |
Length 2 Km - 1.8 Km completed. NOC for remaining portion awaited from Forest Deptt. |
No Image |
1210 (New) |
200251-F/S for Establishment of Park at Peshawar |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 100 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
No Image | |
1210 (New) |
200251-F/S for Establishment of Park at Peshawar |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 100 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
No Image | |
1210 (New) |
200251-F/S for Establishment of Park at Peshawar |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 100 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- October - 2020 |
No Image | |
1210 (New) |
200251-F/S for Establishment of Park at Peshawar |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 100 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- September - 2020 |
No Image | |
1210 (New) |
200251-F/S for Establishment of Park at Peshawar |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 100 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- August - 2020 |
No Image | |
1210 (New) |
200251-F/S for Establishment of Park at Peshawar |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 100 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- July - 2020 |
No Image | |
1210 (New) |
200251-F/S for Establishment of Park at Peshawar |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 100 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- May - 2021 |
No Image | |
1210 (New) |
200251-F/S for Establishment of Park at Peshawar |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 100 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- April - 2021 |
No Image | |
1210 (New) |
200251-F/S for Establishment of Park at Peshawar |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 100 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- March - 2021 |
No Image | |
1210 (New) |
200251-F/S for Establishment of Park at Peshawar |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 100 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- February - 2021 |
No Image | |
1210 (New) |
200251-F/S for Establishment of Park at Peshawar |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 100 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- January - 2021 |
No Image | |