Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1205 (OG) |
160626-F/S, Design and Construction of Makhnial road from Changla to Islamabad. |
Abbottabad |
- | - | - | 28-03-17 | - | 667 | 0 | 5 | 4.275 | 1.25 | 0 | 0 | 662 | 1% |
- December - 2017 |
Tender postponed. May be excuted by FWO. Negotiation with World Bank also in progress. |
No Image |
1205 (OG) |
160626-F/S, Design and Construction of Makhnial road from Changla to Islamabad. |
Abbottabad |
- | - | - | 28-03-17 | - | 667 | 0 | 5 | 5 | 0 | 0 | 0 | 662 | 1% |
- September - 2017 |
Tender postponed. May be excuted by FWO. Negotiation with World Bank also in progress. |
No Image |
1205 (OG) |
160626-F/S, Design and Construction of Makhnial road from Changla to Islamabad. |
Abbottabad |
- | - | - | 28-03-17 | - | 667 | 0 | 5 | 5 | 0 | 0 | 0 | 662 | 1% |
- August - 2017 |
Tender postponed. May be excuted by FWO. Negotiation with World Bank also in progress. |
No Image |
1205 (OG) |
160626-F/S, Design and Construction of Makhnial road from Changla to Islamabad. |
Abbottabad |
- | - | - | 28-03-17 | - | 667 | 0 | 5 | 5 | 0 | 0 | 0 | 662 | 1% |
- July - 2017 |
Pre-qualification of contractor under proces. Will be sponsered by World Bank. DCE for Rs.1985 m under process. |
No Image |
1205 (OG) |
160626-F/S, Design and Construction of Makhnial road from Changla to Islamabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 667 | 0 | 5 | 5 | 1.25 | 0 | 0 | 662 | 1% |
- November - 2017 |
Tender postponed. May be excuted by FWO. Negotiation with World Bank also in progress. |
No Image |
1205 (OG) |
160626-F/S, Design and Construction of Makhnial road from Changla to Islamabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 667 | 0 | 5 | 5 | 0 | 0 | 0 | 662 | 1% |
- October - 2017 |
Tender postponed. May be excuted by FWO. Negotiation with World Bank also in progress. |
No Image |
1205 (OG) |
160626-F/S, Design and Construction of Makhnial road from Changla to Islamabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 497 | 0 | 2.5 | 0.525 | 0.525 | 0.525 | 0.525 | 494.5 | 1% |
0% June - 2018 |
Abbottabad componenet - May be executed by FWO. Negotiation with World Bank also in progress. |
No Image |
Abbottabad | |||||||||||||||||||
1205 (OG) |
160626-F/S, Design and Construction of Makhnial road from Changla to Islamabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 497 | 0 | 2.5 | 2.5 | 0.525 | 0.525 | 0.525 | 494.5 | 1% |
0% May - 2018 |
Abbottabad componenet - May be executed by FWO. Negotiation with World Bank also in progress. |
No Image |
Abbottabad | |||||||||||||||||||
1205 (OG) |
160626-F/S, Design and Construction of Makhnial road from Changla to Islamabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 497 | 0 | 2.5 | 2.5 | 0.525 | 0.525 | 0.525 | 494.5 | 1% |
0% April - 2018 |
Abbottabad componenet - May be executed by FWO. Negotiation with World Bank also in progress. |
No Image |
Abbottabad | |||||||||||||||||||
1205 (OG) |
160626-F/S, Design and Construction of Makhnial road from Changla to Islamabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 497 | 0 | 2.5 | 2.5 | 0.525 | 0.525 | 0.525 | 494.5 | 1% |
0% March - 2018 |
Abbottabad componenet - May be executed by FWO. Negotiation with World Bank also in progress. |
No Image |
Abbottabad | |||||||||||||||||||
1205 (OG) |
160626-F/S, Design and Construction of Makhnial road from Changla to Islamabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 667 | 0 | 5 | 4.275 | 1.25 | 0 | 0 | 662 | 1% |
- February - 2018 |
Abbottabad Componenet - May be excuted by FWO. Negotiation with World Bank also in progress.
Haripur Componenet (Rs. 170 M ) - Tender approval in progress. |
No Image |
Abbottabad | |||||||||||||||||||
1205 (OG) |
160626-F/S, Design and Construction of Makhnial road from Changla to Islamabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 667 | 0 | 5 | 4.275 | 1.25 | 0 | 0 | 662 | 1% |
- January - 2018 |
Tender postponed. May be excuted by FWO. Negotiation with World Bank also in progress. |
No Image |
1205 (OG) |
160626-F/S, Design and Construction of Makhnial road from Changla to Islamabad. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 170 | 0 | 11.25 | 11.25 | 11.25 | 11.25 | 11.25 | 158.75 | 7% |
7% June - 2018 |
Work in progress. |
No Image |
Haripur | |||||||||||||||||||
1205 (OG) |
160626-F/S, Design and Construction of Makhnial road from Changla to Islamabad. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 170 | 0 | 2.5 | 10 | 10 | 9.914 | 9.914 | 167.5 | 1% |
6% May - 2018 |
Work in progress. |
No Image |
Haripur | |||||||||||||||||||
1205 (OG) |
160626-F/S, Design and Construction of Makhnial road from Changla to Islamabad. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 170 | 0 | 2.5 | 10 | 10 | 9.914 | 9.914 | 167.5 | 1% |
6% April - 2018 |
Work in progress. |
No Image |
Haripur | |||||||||||||||||||
1205 (OG) |
160626-F/S, Design and Construction of Makhnial road from Changla to Islamabad. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 170 | 0 | 2.5 | 2.5 | 0 | 0 | 0 | 167.5 | 1% |
- March - 2018 |
Haripur component (Rs.170 m) - Tender approval under process. |
No Image |
Haripur | |||||||||||||||||||
1205 (OG) |
160626-F/S, Design and Construction of Makhnial road from Changla to Islamabad. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 667 | 0 | 5 | 0 | 14.275 | 0 | 0 | 662 | 1% |
- June - 2018 |
No Image | |
1205 (OG) |
160626-F/S, Design and Construction of Makhnial road from Changla to Islamabad. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 667 | 0 | 5 | 0 | 0 | 0 | 0 | 662 | 1% |
- May - 2018 |
No Image | |
1205 (OG) |
160626-F/S, Design and Construction of Makhnial road from Changla to Islamabad. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 667 | 0 | 5 | 0 | 0 | 0 | 0 | 662 | 1% |
- April - 2018 |
No Image | |
1205 (OG) |
160626-F/S, Design and Construction of Makhnial road from Changla to Islamabad. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 667 | 0 | 5 | 0 | 0 | 0 | 0 | 662 | 1% |
- March - 2018 |
No Image | |
1205 (New) |
200253-Special Development Pakage for Backward Areas of District Tank |
Tank |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 100 | 0 | 40 | 40 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
No Image | |
1205 (New) |
200253-Special Development Pakage for Backward Areas of District Tank |
Tank |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 100 | 0 | 40 | 40 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
No Image | |
1205 (New) |
200253-Special Development Pakage for Backward Areas of District Tank |
Tank |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 100 | 0 | 40 | 40 | 0 | 0 | 0 | 0 | - |
- October - 2020 |
No Image | |
Establishment of GGPS Umar Hayat Koroona Kanazai | |||||||||||||||||||
1205 (New) |
200253-Special Development Pakage for Backward Areas of District Tank |
Tank |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 100 | 0 | 40 | 40 | 0 | 0 | 0 | 0 | - |
- September - 2020 |
No Image | |
Establishment of GGPS Umar Hayat Koroona Kanazai | |||||||||||||||||||
1205 (New) |
200253-Special Development Pakage for Backward Areas of District Tank |
Tank |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 100 | 0 | 40 | 40 | 0 | 0 | 0 | 0 | - |
- August - 2020 |
No Image | |
1205 (New) |
200253-Special Development Pakage for Backward Areas of District Tank |
Tank |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 100 | 0 | 40 | 0 | 0 | 0 | 0 | 0 |
- July - 2020 |
No Image | ||
1205 (New) |
200253-Special Development Pakage for Backward Areas of District Tank |
Tank |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 100 | 0 | 40 | 40 | 0 | 0 | 0 | 0 | - |
- May - 2021 |
No Image | |
1205 (New) |
200253-Special Development Pakage for Backward Areas of District Tank |
Tank |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 100 | 0 | 40 | 40 | 0 | 0 | 0 | 0 | - |
- April - 2021 |
No Image | |
1205 (New) |
200253-Special Development Pakage for Backward Areas of District Tank |
Tank |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 100 | 0 | 40 | 40 | 0 | 0 | 0 | 0 | - |
- March - 2021 |
No Image | |
1205 (New) |
200253-Special Development Pakage for Backward Areas of District Tank |
Tank |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 100 | 0 | 40 | 40 | 0 | 0 | 0 | 0 | - |
- February - 2021 |
No Image | |
1205 (New) |
200253-Special Development Pakage for Backward Areas of District Tank |
Tank |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 100 | 0 | 40 | 40 | 0 | 0 | 0 | 0 | - |
- January - 2021 |
No Image | |
Pages : 1 |