Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1204 (OG) |
151073-Improvement/Rehabilitation of road from Swargali to Boi with Link Bangara Chowk to Kanair Kass (3 Km), Abbottabad. |
Abbottabad |
- | 30-06-18 | - | 09-06-17 | - | 30 | 7.25 | 27.5 | 27.5 | 20.626 | 14.057 | 21.307 | 0 | 100% |
71% December - 2017 |
3 Km - ready for BT. |
No Image |
1204 (OG) |
151073-Improvement/Rehabilitation of road from Swargali to Boi with Link Bangara Chowk to Kanair Kass (3 Km), Abbottabad. |
Abbottabad |
- | 30-06-18 | - | 09-06-17 | - | 30 | 7.25 | 27.5 | 27.5 | 13.751 | 5.84 | 13.09 | 0 | 100% |
44% September - 2017 |
3 Km - ready for BT. |
No Image |
1204 (OG) |
151073-Improvement/Rehabilitation of road from Swargali to Boi with Link Bangara Chowk to Kanair Kass (3 Km), Abbottabad. |
Abbottabad |
- | 30-06-18 | - | 09-06-17 | - | 30 | 7.25 | 27.5 | 27.5 | 13.751 | 5.84 | 13.09 | 0 | 100% |
44% August - 2017 |
3 Km - work started. |
No Image |
1204 (OG) |
151073-Improvement/Rehabilitation of road from Swargali to Boi with Link Bangara Chowk to Kanair Kass (3 Km), Abbottabad. |
Abbottabad |
- | 30-06-18 | - | 09-06-17 | - | 30 | 7.25 | 27.5 | 27.5 | 9.763 | 0 | 7.25 | 0 | 100% |
24% July - 2017 |
3 Km - work started. |
No Image |
1204 (OG) |
151073-Improvement/Rehabilitation of road from Swargali to Boi with Link Bangara Chowk to Kanair Kass (3 Km), Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 30 | 7.25 | 27.5 | 27.5 | 20.626 | 5.84 | 13.09 | 0 | 100% |
44% November - 2017 |
3 Km - ready for BT. |
No Image |
1204 (OG) |
151073-Improvement/Rehabilitation of road from Swargali to Boi with Link Bangara Chowk to Kanair Kass (3 Km), Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 30 | 7.25 | 27.5 | 27.5 | 13.751 | 5.84 | 13.09 | 0 | 100% |
44% October - 2017 |
3 Km - ready for BT. |
No Image |
1204 (OG) |
151073-Improvement/Rehabilitation of road from Swargali to Boi with Link Bangara Chowk to Kanair Kass (3 Km), Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 30 | 7.25 | 27.5 | 27.5 | 27.5 | 14.057 | 21.307 | 0 | 100% |
71% June - 2018 |
Completed (3 Km). |
No Image |
Abbottabad | |||||||||||||||||||
1204 (OG) |
151073-Improvement/Rehabilitation of road from Swargali to Boi with Link Bangara Chowk to Kanair Kass (3 Km), Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 30 | 7.25 | 27.5 | 27.5 | 27.501 | 14.057 | 21.307 | 0 | 100% |
71% May - 2018 |
3 Km -Completed. |
No Image |
Abbottabad | |||||||||||||||||||
1204 (OG) |
151073-Improvement/Rehabilitation of road from Swargali to Boi with Link Bangara Chowk to Kanair Kass (3 Km), Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 30 | 7.25 | 27.5 | 27.5 | 27.501 | 14.057 | 21.307 | 0 | 100% |
71% April - 2018 |
3 Km - ready for BT. |
No Image |
Abbottabad | |||||||||||||||||||
1204 (OG) |
151073-Improvement/Rehabilitation of road from Swargali to Boi with Link Bangara Chowk to Kanair Kass (3 Km), Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 30 | 7.25 | 27.5 | 27.5 | 27.501 | 14.057 | 21.307 | 0 | 100% |
71% March - 2018 |
3 Km - ready for BT. |
No Image |
Abbottabad | |||||||||||||||||||
1204 (OG) |
151073-Improvement/Rehabilitation of road from Swargali to Boi with Link Bangara Chowk to Kanair Kass (3 Km), Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 30 | 7.25 | 27.5 | 27.5 | 20.626 | 14.057 | 21.307 | 0 | 100% |
71% February - 2018 |
3 Km - ready for BT. |
No Image |
Abbottabad | |||||||||||||||||||
1204 (OG) |
151073-Improvement/Rehabilitation of road from Swargali to Boi with Link Bangara Chowk to Kanair Kass (3 Km), Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 30 | 7.25 | 27.5 | 27.5 | 20.626 | 14.057 | 21.307 | 0 | 100% |
71% January - 2018 |
3 Km - ready for BT. |
No Image |
1204 (OG) |
190423-Provision for Electrification works. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 0 | 50 | 50 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
No Image | |
1204 (OG) |
190423-Provision for Electrification works. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 0 | 50 | 50 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
No Image | |
1204 (OG) |
190423-Provision for Electrification works. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 0 | 50 | 50 | 0 | 0 | 0 | 0 | - |
- October - 2020 |
No Image | |
1204 (OG) |
190423-Provision for Electrification works. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 0 | 50 | 50 | 0 | 0 | 0 | 0 | - |
- September - 2020 |
No Image | |
1204 (OG) |
190423-Provision for Electrification works. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 0 | 50 | 50 | 0 | 0 | 0 | 0 | - |
- August - 2020 |
No Image | |
1204 (OG) |
190423-Provision for Electrification works. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 0 | 50 | 0 | 0 | 0 | 0 | 0 |
- July - 2020 |
No Image | ||
1204 (OG) |
190423-Provision for Electrification works. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 0 | 50 | 50 | 0 | 0 | 0 | 0 | - |
- May - 2021 |
No Image | |
1204 (OG) |
190423-Provision for Electrification works. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 0 | 50 | 50 | 0 | 0 | 0 | 0 | - |
- April - 2021 |
No Image | |
1204 (OG) |
190423-Provision for Electrification works. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 0 | 50 | 50 | 0 | 0 | 0 | 0 | - |
- March - 2021 |
No Image | |
1204 (OG) |
190423-Provision for Electrification works. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 0 | 50 | 50 | 0 | 0 | 0 | 0 | - |
- February - 2021 |
No Image | |
1204 (OG) |
190423-Provision for Electrification works. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 0 | 50 | 50 | 0 | 0 | 0 | 0 | - |
- January - 2021 |
No Image | |