Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1200 (OG) |
150865-Improvement, BT and pavement of Tajwal to Bagan road (2 Km), Tajwl to Nawansher road (1.50 Km), Kundla Passala road (1.25 Km), Machana to Batangi road (1.90 Km), Serian to Keri Raiki road (0.90 Km), Taror road (2 Km), Shakara to Choprra road (2 Km), Pirkot road (1.80 Km), Topla road (0.75 Km), Kalabin Suka Kass road (1.325 Km), Naimli Maira road (16 Km), Sherabad Bara Hotar road i/c link road to Noormang (4 Km), Samalati Tajwal road (2.50 Km), Baragali Kassala road (2 Km), Bermigali Jhansa road (0.75 Km), Mochi Dhara Dorah Jaswara road (1.20 Km), Tatreela road (0.70 Km), Danna Bagan to Danna Kaghian road (0.60 Km), Mohar Khurd to Mohar Kalan road (0.70 Km), Gali Banian road (1 Km), Upper Mohar road (0.80 Km), Morti Keri Sarafali road (0.85 Km), Gather road (1.20 Km), District Abbottabad. |
Abbottabad |
03-03-16 | - | - | 30-11-17 | - | 700 | 78.894 | 20 | 27.1 | 17.1 | 17.1 | 95.994 | 601.106 | 14% |
14% December - 2017 |
10/10 units in progress. Summary approved. |
No Image |
1200 (OG) |
150865-Construction / Rehabilitation of road from BHU Tajwal to Nawansher, Machana to Batangi, Serrian to Keri Raiki, Taror, Shakra to Choprra Nawansher Pirkot to Tupla road Kala Ban, Shukka Kas road, Abbottabad. |
Abbottabad |
03-03-16 | - | - | - | - | 200 | 78.894 | 20 | 20 | 7.1 | 7.1 | 85.994 | 101.106 | 49% |
43% September - 2017 |
10/10 units in progress. Revised PC-I/DCE for Rs.700 m submitted to P&D. |
No Image |
1200 (OG) |
150865-Construction / Rehabilitation of road from BHU Tajwal to Nawansher, Machana to Batangi, Serrian to Keri Raiki, Taror, Shakra to Choprra Nawansher Pirkot to Tupla road Kala Ban, Shukka Kas road, Abbottabad. |
Abbottabad |
03-03-16 | - | - | - | - | 200 | 78.894 | 20 | 20 | 7.1 | 7.1 | 85.994 | 101.106 | 49% |
43% August - 2017 |
10/10 units in progress. Revised PC-I/DCE for Rs.700 m submitted to P&D. |
No Image |
1200 (OG) |
150865-Construction / Rehabilitation of road from BHU Tajwal to Nawansher, Machana to Batangi, Serrian to Keri Raiki, Taror, Shakra to Choprra Nawansher Pirkot to Tupla road Kala Ban, Shukka Kas road, Abbottabad. |
Abbottabad |
03-03-16 | - | - | - | - | 200 | 78.894 | 20 | 20 | 7.1 | 0 | 78.894 | 101.106 | 49% |
39% July - 2017 |
10/10 units in progress. Revised PC-I/DCE for Rs.700 m submitted to P&D. |
No Image |
1200 (OG) |
150865-Improvement, BT and pavement of Tajwal to Bagan road (2 Km), Tajwl to Nawansher road (1.50 Km), Kundla Passala road (1.25 Km), Machana to Batangi road (1.90 Km), Serian to Keri Raiki road (0.90 Km), Taror road (2 Km), Shakara to Choprra road (2 Km), Pirkot road (1.80 Km), Topla road (0.75 Km), Kalabin Suka Kass road (1.325 Km), Naimli Maira road (16 Km), Sherabad Bara Hotar road i/c link road to Noormang (4 Km), Samalati Tajwal road (2.50 Km), Baragali Kassala road (2 Km), Bermigali Jhansa road (0.75 Km), Mochi Dhara Dorah Jaswara road (1.20 Km), Tatreela road (0.70 Km), Danna Bagan to Danna Kaghian road (0.60 Km), Mohar Khurd to Mohar Kalan road (0.70 Km), Gali Banian road (1 Km), Upper Mohar road (0.80 Km), Morti Keri Sarafali road (0.85 Km), Gather road (1.20 Km), District Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 78.894 | 20 | 27.1 | 17.1 | 17.1 | 95.994 | 101.106 | 49% |
48% November - 2017 |
10/10 units in progress. Revised PC-I/DCE for Rs.700 m submitted to SOR .Summary approved. |
No Image |
1200 (OG) |
150865-Improvement, BT and pavement of Tajwal to Bagan road (2 Km), Tajwl to Nawansher road (1.50 Km), Kundla Passala road (1.25 Km), Machana to Batangi road (1.90 Km), Serian to Keri Raiki road (0.90 Km), Taror road (2 Km), Shakara to Choprra road (2 Km), Pirkot road (1.80 Km), Topla road (0.75 Km), Kalabin Suka Kass road (1.325 Km), Naimli Maira road (16 Km), Sherabad Bara Hotar road i/c link road to Noormang (4 Km), Samalati Tajwal road (2.50 Km), Baragali Kassala road (2 Km), Bermigali Jhansa road (0.75 Km), Mochi Dhara Dorah Jaswara road (1.20 Km), Tatreela road (0.70 Km), Danna Bagan to Danna Kaghian road (0.60 Km), Mohar Khurd to Mohar Kalan road (0.70 Km), Gali Banian road (1 Km), Upper Mohar road (0.80 Km), Morti Keri Sarafali road (0.85 Km), Gather road (1.20 Km), District Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 78.894 | 20 | 20 | 7.1 | 7.1 | 85.994 | 101.106 | 49% |
43% October - 2017 |
10/10 units in progress. Revised PC-I/DCE for Rs.700 m submitted to SOR on 01/11/2017. Summary approved. |
No Image |
1200 (OG) |
150865-Improvement, BT and pavement of Tajwal to Bagan road (2 Km), Tajwl to Nawansher road (1.50 Km), Kundla Passala road (1.25 Km), Machana to Batangi road (1.90 Km), Serian to Keri Raiki road (0.90 Km), Taror road (2 Km), Shakara to Choprra road (2 Km), Pirkot road (1.80 Km), Topla road (0.75 Km), Kalabin Suka Kass road (1.325 Km), Naimli Maira road (16 Km), Sherabad Bara Hotar road i/c link road to Noormang (4 Km), Samalati Tajwal road (2.50 Km), Baragali Kassala road (2 Km), Bermigali Jhansa road (0.75 Km), Mochi Dhara Dorah Jaswara road (1.20 Km), Tatreela road (0.70 Km), Danna Bagan to Danna Kaghian road (0.60 Km), Mohar Khurd to Mohar Kalan road (0.70 Km), Gali Banian road (1 Km), Upper Mohar road (0.80 Km), Morti Keri Sarafali road (0.85 Km), Gather road (1.20 Km), District Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 700 | 78.894 | 20 | 34.058 | 34.058 | 34.058 | 112.952 | 601.106 | 14% |
16% June - 2018 |
(Original scope) 11/11 units in progress. Revised scope (additional 15 units) - work order issued. |
No Image |
1) Improvement/widening and BT of Tajwal to Bagan road (2 Km)
2) Improvement/widening and BT fo Taror road
3) Improvement/widening and BT of Nowshera to Pir Kot road (1.80 Km)
4) Improvement/widening and BT of Nowshera road Tajwal to Nowshera road (1.20 Km)
5) Improvement/widening and BT of Kundla Passala road
6) Improvement/widening and pavement of Machana to Batangi road (1.50 Km)
7) Improvement/widening and BT of Serian to Kari Raiki road (0.700 Km)
8) Improvement/widening and BT of Shakra to Chopra road (2 Km)
9) Improvement/widening and BT of Topla road (0.700 Km)
10) Improvement/widening and pavement of Kalabin Suka Kass road (1.50 Km) | |||||||||||||||||||
1200 (OG) |
150865-Improvement, BT and pavement of Tajwal to Bagan road (2 Km), Tajwl to Nawansher road (1.50 Km), Kundla Passala road (1.25 Km), Machana to Batangi road (1.90 Km), Serian to Keri Raiki road (0.90 Km), Taror road (2 Km), Shakara to Choprra road (2 Km), Pirkot road (1.80 Km), Topla road (0.75 Km), Kalabin Suka Kass road (1.325 Km), Naimli Maira road (16 Km), Sherabad Bara Hotar road i/c link road to Noormang (4 Km), Samalati Tajwal road (2.50 Km), Baragali Kassala road (2 Km), Bermigali Jhansa road (0.75 Km), Mochi Dhara Dorah Jaswara road (1.20 Km), Tatreela road (0.70 Km), Danna Bagan to Danna Kaghian road (0.60 Km), Mohar Khurd to Mohar Kalan road (0.70 Km), Gali Banian road (1 Km), Upper Mohar road (0.80 Km), Morti Keri Sarafali road (0.85 Km), Gather road (1.20 Km), District Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 700 | 78.894 | 20 | 34.058 | 34.058 | 34.058 | 112.952 | 601.106 | 14% |
16% May - 2018 |
(Original scope) 11/11 units in progress. Revised scope (additional 15 units) - work order issued. |
No Image |
1) Improvement/widening and BT of Tajwal to Bagan road (2 Km)
2) Improvement/widening and BT fo Taror road
3) Improvement/widening and BT of Nowshera to Pir Kot road (1.80 Km)
4) Improvement/widening and BT of Nowshera road Tajwal to Nowshera road (1.20 Km)
5) Improvement/widening and BT of Kundla Passala road
6) Improvement/widening and pavement of Machana to Batangi road (1.50 Km)
7) Improvement/widening and BT of Serian to Kari Raiki road (0.700 Km)
8) Improvement/widening and BT of Shakra to Chopra road (2 Km)
9) Improvement/widening and BT of Topla road (0.700 Km)
10) Improvement/widening and pavement of Kalabin Suka Kass road (1.50 Km) | |||||||||||||||||||
1200 (OG) |
150865-Improvement, BT and pavement of Tajwal to Bagan road (2 Km), Tajwl to Nawansher road (1.50 Km), Kundla Passala road (1.25 Km), Machana to Batangi road (1.90 Km), Serian to Keri Raiki road (0.90 Km), Taror road (2 Km), Shakara to Choprra road (2 Km), Pirkot road (1.80 Km), Topla road (0.75 Km), Kalabin Suka Kass road (1.325 Km), Naimli Maira road (16 Km), Sherabad Bara Hotar road i/c link road to Noormang (4 Km), Samalati Tajwal road (2.50 Km), Baragali Kassala road (2 Km), Bermigali Jhansa road (0.75 Km), Mochi Dhara Dorah Jaswara road (1.20 Km), Tatreela road (0.70 Km), Danna Bagan to Danna Kaghian road (0.60 Km), Mohar Khurd to Mohar Kalan road (0.70 Km), Gali Banian road (1 Km), Upper Mohar road (0.80 Km), Morti Keri Sarafali road (0.85 Km), Gather road (1.20 Km), District Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 700 | 78.894 | 20 | 34.058 | 34.058 | 34.058 | 112.952 | 601.106 | 14% |
16% April - 2018 |
(Original scope) 11/11 units in progress. Revised scope (additional 15 units) - work order issued. |
No Image |
1) Improvement/widening and BT of Tajwal to Bagan road (2 Km)
2) Improvement/widening and BT fo Taror road
3) Improvement/widening and BT of Nowshera to Pir Kot road (1.80 Km)
4) Improvement/widening and BT of Nowshera road Tajwal to Nowshera road (1.20 Km)
5) Improvement/widening and BT of Kundla Passala road
6) Improvement/widening and pavement of Machana to Batangi road (1.50 Km)
7) Improvement/widening and BT of Serian to Kari Raiki road (0.700 Km)
8) Improvement/widening and BT of Shakra to Chopra road (2 Km)
9) Improvement/widening and BT of Topla road (0.700 Km)
10) Improvement/widening and pavement of Kalabin Suka Kass road (1.50 Km) | |||||||||||||||||||
1200 (OG) |
150865-Improvement, BT and pavement of Tajwal to Bagan road (2 Km), Tajwl to Nawansher road (1.50 Km), Kundla Passala road (1.25 Km), Machana to Batangi road (1.90 Km), Serian to Keri Raiki road (0.90 Km), Taror road (2 Km), Shakara to Choprra road (2 Km), Pirkot road (1.80 Km), Topla road (0.75 Km), Kalabin Suka Kass road (1.325 Km), Naimli Maira road (16 Km), Sherabad Bara Hotar road i/c link road to Noormang (4 Km), Samalati Tajwal road (2.50 Km), Baragali Kassala road (2 Km), Bermigali Jhansa road (0.75 Km), Mochi Dhara Dorah Jaswara road (1.20 Km), Tatreela road (0.70 Km), Danna Bagan to Danna Kaghian road (0.60 Km), Mohar Khurd to Mohar Kalan road (0.70 Km), Gali Banian road (1 Km), Upper Mohar road (0.80 Km), Morti Keri Sarafali road (0.85 Km), Gather road (1.20 Km), District Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 700 | 78.894 | 20 | 34.058 | 34.058 | 31.368 | 110.262 | 601.106 | 14% |
16% March - 2018 |
(Original scope) 11/11 units in progress. Revised scope (additional 15 units) - work order issued. |
No Image |
1) Improvement/widening and BT of Tajwal to Bagan road (2 Km)
2) Improvement/widening and BT fo Taror road
3) Improvement/widening and BT of Nowshera to Pir Kot road (1.80 Km)
4) Improvement/widening and BT of Nowshera road Tajwal to Nowshera road (1.20 Km)
5) Improvement/widening and BT of Kundla Passala road
6) Improvement/widening and pavement of Machana to Batangi road (1.50 Km)
7) Improvement/widening and BT of Serian to Kari Raiki road (0.700 Km)
8) Improvement/widening and BT of Shakra to Chopra road (2 Km)
9) Improvement/widening and BT of Topla road (0.700 Km)
10) Improvement/widening and pavement of Kalabin Suka Kass road (1.50 Km) | |||||||||||||||||||
1200 (OG) |
150865-Improvement, BT and pavement of Tajwal to Bagan road (2 Km), Tajwl to Nawansher road (1.50 Km), Kundla Passala road (1.25 Km), Machana to Batangi road (1.90 Km), Serian to Keri Raiki road (0.90 Km), Taror road (2 Km), Shakara to Choprra road (2 Km), Pirkot road (1.80 Km), Topla road (0.75 Km), Kalabin Suka Kass road (1.325 Km), Naimli Maira road (16 Km), Sherabad Bara Hotar road i/c link road to Noormang (4 Km), Samalati Tajwal road (2.50 Km), Baragali Kassala road (2 Km), Bermigali Jhansa road (0.75 Km), Mochi Dhara Dorah Jaswara road (1.20 Km), Tatreela road (0.70 Km), Danna Bagan to Danna Kaghian road (0.60 Km), Mohar Khurd to Mohar Kalan road (0.70 Km), Gali Banian road (1 Km), Upper Mohar road (0.80 Km), Morti Keri Sarafali road (0.85 Km), Gather road (1.20 Km), District Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 700 | 78.894 | 20 | 31.368 | 31.368 | 31.368 | 110.262 | 601.106 | 14% |
16% February - 2018 |
(original Scope ) 11/11 units in progress. Revised Scope ( additional 15 units ) Work order issued. |
No Image |
1) Improvement/widening and BT of Tajwal to Bagan road (2 Km)
2) Improvement/widening and BT fo Taror road
3) Improvement/widening and BT of Nowshera to Pir Kot road (1.80 Km)
4) Improvement/widening and BT of Nowshera road Tajwal to Nowshera road (1.20 Km)
5) Improvement/widening and BT of Kundla Passala road
6) Improvement/widening and pavement of Machana to Batangi road (1.50 Km)
7) Improvement/widening and BT of Serian to Kari Raiki road (0.700 Km)
8) Improvement/widening and BT of Shakra to Chopra road (2 Km)
9) Improvement/widening and BT of Topla road (0.700 Km)
10) Improvement/widening and pavement of Kalabin Suka Kass road (1.50 Km) | |||||||||||||||||||
1200 (OG) |
150865-Improvement, BT and pavement of Tajwal to Bagan road (2 Km), Tajwl to Nawansher road (1.50 Km), Kundla Passala road (1.25 Km), Machana to Batangi road (1.90 Km), Serian to Keri Raiki road (0.90 Km), Taror road (2 Km), Shakara to Choprra road (2 Km), Pirkot road (1.80 Km), Topla road (0.75 Km), Kalabin Suka Kass road (1.325 Km), Naimli Maira road (16 Km), Sherabad Bara Hotar road i/c link road to Noormang (4 Km), Samalati Tajwal road (2.50 Km), Baragali Kassala road (2 Km), Bermigali Jhansa road (0.75 Km), Mochi Dhara Dorah Jaswara road (1.20 Km), Tatreela road (0.70 Km), Danna Bagan to Danna Kaghian road (0.60 Km), Mohar Khurd to Mohar Kalan road (0.70 Km), Gali Banian road (1 Km), Upper Mohar road (0.80 Km), Morti Keri Sarafali road (0.85 Km), Gather road (1.20 Km), District Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 700 | 78.894 | 20 | 27.1 | 17.1 | 17.1 | 95.994 | 601.106 | 14% |
14% January - 2018 |
10/10 units in progress. Summary approved. |
No Image |
1200 (OG) |
180606-Communication / Mass Awareness /Publicity of Schemes |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 7.5 | 0 | 0 | 0 | 0 | 7.5 | 0 | - |
- December - 2020 |
No Image | |
1200 (OG) |
180606-Communication / Mass Awareness /Publicity of Schemes |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 7.5 | 0 | 0 | 0 | 0 | 7.5 | 0 | - |
- December - 2020 |
No Image | |
1200 (OG) |
180606-Communication / Mass Awareness /Publicity of Schemes |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 7.5 | 0 | 0 | 0 | 0 | 7.5 | 0 | - |
- October - 2020 |
No Image | |
1200 (OG) |
180606-Communication / Mass Awareness /Publicity of Schemes |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 7.5 | 0 | 0 | 0 | 0 | 7.5 | 0 | - |
- September - 2020 |
No Image | |
1200 (OG) |
180606-Communication / Mass Awareness /Publicity of Schemes |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 7.5 | 0 | 0 | 0 | 0 | 7.5 | 0 | - |
- August - 2020 |
No Image | |
1200 (OG) |
180606-Communication / Mass Awareness /Publicity of Schemes |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 7.5 | 0 | 0 | 0 | 0 | 7.5 | 0 | - |
- July - 2020 |
No Image | |
1200 (OG) |
180606-Communication / Mass Awareness /Publicity of Schemes |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 7.5 | 0 | 0 | 0 | 0 | 7.5 | 0 | - |
- May - 2021 |
No Image | |
1200 (OG) |
180606-Communication / Mass Awareness /Publicity of Schemes |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 7.5 | 0 | 0 | 0 | 0 | 7.5 | 0 | - |
- April - 2021 |
No Image | |
1200 (OG) |
180606-Communication / Mass Awareness /Publicity of Schemes |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 7.5 | 0 | 0 | 0 | 0 | 7.5 | 0 | - |
- March - 2021 |
No Image | |
1200 (OG) |
180606-Communication / Mass Awareness /Publicity of Schemes |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 7.5 | 0 | 0 | 0 | 0 | 7.5 | 0 | - |
- February - 2021 |
No Image | |
1200 (OG) |
180606-Communication / Mass Awareness /Publicity of Schemes |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 7.5 | 0 | 0 | 0 | 0 | 7.5 | 0 | - |
- January - 2021 |
No Image | |