Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1189 (OG) |
140785-Improvement and Blacktopping of Butti to Lower Surjal and Dana - 10 Km, District Abbottabad. |
Abbottabad |
- | 30-06-18 | - | 28-03-17 | - | 65 | 0 | 63.478 | 63.478 | 31.739 | 25.853 | 25.853 | 1.522 | 98% |
40% December - 2017 |
2 Packages - earth work completed. Sub base in progress. Site disputed by locals regarding land. Site disputed. |
No Image |
1189 (OG) |
140785-Improvement and Blacktopping of Butti to Lower Surjal and Dana - 10 Km, District Abbottabad. |
Abbottabad |
- | 30-06-18 | - | 28-03-17 | - | 65 | 0 | 63.478 | 63.478 | 31.739 | 22.535 | 22.535 | 1.522 | 98% |
35% September - 2017 |
2 Packages - earth work completed. Sub base in progress. |
No Image |
1189 (OG) |
140785-Improvement and Blacktopping of Butti to Lower Surjal and Dana - 10 Km, District Abbottabad. |
Abbottabad |
- | 30-06-18 | - | 28-03-17 | - | 65 | 0 | 63.478 | 63.478 | 31.739 | 0 | 0 | 1.522 | 98% |
- August - 2017 |
Work started. |
No Image |
1189 (OG) |
140785-Improvement and Blacktopping of Butti to Lower Surjal and Dana - 10 Km, District Abbottabad. |
Abbottabad |
- | 30-06-18 | - | 28-03-17 | - | 65 | 0 | 63.478 | 63.478 | 22.535 | 0 | 0 | 1.522 | 98% |
- July - 2017 |
Work started. |
No Image |
1189 (OG) |
140785-Improvement and Blacktopping of Butti to Lower Surjal and Dana - 10 Km, District Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 65 | 0 | 63.478 | 63.478 | 31.739 | 25.853 | 25.853 | 1.522 | 98% |
40% November - 2017 |
2 Packages - earth work completed. Sub base in progress. Site disputed by locals regarding land. Site disputed. |
No Image |
1189 (OG) |
140785-Improvement and Blacktopping of Butti to Lower Surjal and Dana - 10 Km, District Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 65 | 0 | 63.478 | 63.478 | 31.739 | 22.535 | 22.535 | 1.522 | 98% |
35% October - 2017 |
2 Packages - earth work completed. Sub base in progress. Site disputed by locals regarding land. |
No Image |
1189 (OG) |
140785-Improvement and Blacktopping of Butti to Lower Surjal and Dana - 10 Km, District Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 65 | 0 | 63.478 | 31.705 | 31.705 | 31.705 | 31.705 | 1.522 | 98% |
49% June - 2018 |
2 Packages - earth work completed. Sub base in progress. Site disputed by locals regarding land. |
No Image |
1) Package-1 - 0+00 - 2+00 (2 Km)
2) Package-2 - 2.2+00 - 3+500 (1.50 Km) | |||||||||||||||||||
1189 (OG) |
140785-Improvement and Blacktopping of Butti to Lower Surjal and Dana - 10 Km, District Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 65 | 0 | 63.478 | 63.478 | 63.478 | 31.705 | 31.705 | 1.522 | 98% |
49% May - 2018 |
2 Packages - earth work completed. Sub base in progress.
Site disputed by locals regarding land. |
No Image |
1) Package-1 - 0+00 - 2+00 (2 Km)
2) Package-2 - 2.2+00 - 3+500 (1.50 Km) | |||||||||||||||||||
1189 (OG) |
140785-Improvement and Blacktopping of Butti to Lower Surjal and Dana - 10 Km, District Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 65 | 0 | 63.478 | 63.478 | 63.478 | 31.705 | 31.705 | 1.522 | 98% |
49% April - 2018 |
2 Packages - earth work completed. Sub base in progress.
Site disputed by locals regarding land. |
No Image |
1) Package-1 - 0+00 - 2+00 (2 Km)
2) Package-2 - 2.2+00 - 3+500 (1.50 Km) | |||||||||||||||||||
1189 (OG) |
140785-Improvement and Blacktopping of Butti to Lower Surjal and Dana - 10 Km, District Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 65 | 0 | 63.478 | 63.478 | 31.739 | 25.853 | 25.853 | 1.522 | 98% |
40% March - 2018 |
2 Packages - earth work completed. Sub base in progress. Site disputed by locals regarding land. Site disputed. |
No Image |
1) Package-1 - 0+00 - 2+00 (2 Km)
2) Package-2 - 2.2+00 - 3+500 (1.50 Km) | |||||||||||||||||||
1189 (OG) |
140785-Improvement and Blacktopping of Butti to Lower Surjal and Dana - 10 Km, District Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 65 | 0 | 63.478 | 63.478 | 31.739 | 25.853 | 25.853 | 1.522 | 98% |
40% February - 2018 |
2 Packages - earth work completed. Sub base in progress. Site disputed by locals regarding land. Site disputed. |
No Image |
1) Package-1 - 0+00 - 2+00 (2 Km)
2) Package-2 - 2.2+00 - 3+500 (1.50 Km) | |||||||||||||||||||
1189 (OG) |
140785-Improvement and Blacktopping of Butti to Lower Surjal and Dana - 10 Km, District Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 65 | 0 | 63.478 | 63.478 | 31.739 | 25.853 | 25.853 | 1.522 | 98% |
40% January - 2018 |
2 Packages - earth work completed. Sub base in progress. Site disputed by locals regarding land. Site disputed. |
No Image |
1189 (OG) |
130382-Improvment of Water Supply, Sewerage/ Drainage System in Selected Districts of KP |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 14.983 | 0 | 0 | 0 | 0 | 0 | 0 | 14.983 | - |
- October - 2020 |
Work in progress. |
No Image |
1) Construction of Street Pavement/Culverts/D | |||||||||||||||||||
1189 (OG) |
130382-Improvment of Water Supply, Sewerage/ Drainage System in Selected Districts of KP |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 14.983 | 0 | 0 | 0 | 0 | 0 | 0 | 14.983 | - |
- September - 2020 |
Work in progress. |
No Image |
1) Construction of Street Pavement/Culverts/D | |||||||||||||||||||
1189 (OG) |
130382-Improvment of Water Supply, Sewerage/ Drainage System in Selected Districts of KP |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 14.983 | 0 | 0 | 0 | 0 | 0 | 0 | 14.983 | - |
- August - 2020 |
Work in progress. |
No Image |
1) Construction of Street Pavement/Culverts/D | |||||||||||||||||||
1189 (OG) |
130382-Improvment of Water Supply, Sewerage/ Drainage System in Selected Districts of KP |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 14.983 | 0 | 0 | 0 | 0 | 0 | 0 | 14.983 | - |
- July - 2020 |
Work in progress. |
No Image |
1) Construction of Street Pavement/Culverts/D | |||||||||||||||||||
1189 (OG) |
130382-Improvment of Water Supply, Sewerage/ Drainage System in Selected Districts of KP |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 14.983 | 7.949 | 0 | 0 | 0 | 0 | 7.949 | 7.034 | - |
53% May - 2021 |
Work in progress. |
No Image |
1) Construction of Street Pavement/Culverts/D | |||||||||||||||||||
1189 (OG) |
130382-Improvment of Water Supply, Sewerage/ Drainage System in Selected Districts of KP |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 14.983 | 7.949 | 0 | 0 | 0 | 0 | 7.949 | 7.034 | - |
53% April - 2021 |
Work in progress. |
No Image |
1) Construction of Street Pavement/Culverts/D | |||||||||||||||||||
1189 (OG) |
130382-Improvment of Water Supply, Sewerage/ Drainage System in Selected Districts of KP |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 14.983 | 7.949 | 0 | 0 | 0 | 0 | 7.949 | 7.034 | - |
53% March - 2021 |
Work in progress. |
No Image |
1) Construction of Street Pavement/Culverts/D | |||||||||||||||||||
1189 (OG) |
130382-Improvment of Water Supply, Sewerage/ Drainage System in Selected Districts of KP |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 14.983 | 7.949 | 0 | 0 | 0 | 0 | 7.949 | 7.034 | - |
53% February - 2021 |
Work in progress. |
No Image |
1) Construction of Street Pavement/Culverts/D | |||||||||||||||||||
1189 (OG) |
130382-Improvment of Water Supply, Sewerage/ Drainage System in Selected Districts of KP |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 14.983 | 7.949 | 0 | 0 | 0 | 0 | 7.949 | 7.034 | - |
53% January - 2021 |
Work in progress. |
No Image |
1) Construction of Street Pavement/Culverts/D | |||||||||||||||||||
1189 (New) |
190397-Improvement of Ring Road Sourthern Section. |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 1000 | 0 | 64 | 64 | 0 | 0 | 0 | 0 | - |
- December - 2019 |
No Image | |
1189 (New) |
190397-Improvement of Ring Road Sourthern Section. |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 1000 | 0 | 64 | 64 | 0 | 0 | 0 | 0 | - |
- November - 2019 |
No Image | |
1189 (New) |
190397-Improvement of Ring Road Sourthern Section. |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 1000 | 0 | 64 | 64 | 0 | 0 | 0 | 0 | - |
- October - 2019 |
No Image | |
1189 (New) |
190397-Improvement of Ring Road Sourthern Section. |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 1000 | 0 | 64 | 64 | 0 | 0 | 0 | 0 | - |
- September - 2019 |
No Image | |
1189 (New) |
190397-Improvement of Ring Road Sourthern Section. |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 1000 | 0 | 64 | 64 | 0 | 0 | 0 | 0 | - |
- August - 2019 |
No Image | |
1189 (New) |
190397-Improvement of Ring Road Sourthern Section. |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 1000 | 0 | 64 | 64 | 0 | 0 | 0 | 0 | - |
- May - 2020 |
No Image | |
1189 (New) |
190397-Improvement of Ring Road Sourthern Section. |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 1000 | 0 | 64 | 64 | 0 | 0 | 0 | 0 | - |
- April - 2020 |
No Image | |
1189 (New) |
190397-Improvement of Ring Road Sourthern Section. |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 1000 | 0 | 64 | 64 | 0 | 0 | 0 | 0 | - |
- March - 2020 |
No Image | |
1189 (New) |
190397-Improvement of Ring Road Sourthern Section. |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 1000 | 0 | 64 | 64 | 0 | 0 | 0 | 0 | - |
- February - 2020 |
No Image | |
1189 (New) |
190397-Improvement of Ring Road Sourthern Section. |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 1000 | 0 | 64 | 64 | 0 | 0 | 0 | 0 | - |
- January - 2020 |
No Image | |
1189 (OG) |
130382-Improvment of Water Supply, Sewerage/ Drainage System in Selected Districts of KP |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 750 | 680 | 10 | 10 | 0 | 0 | 680 | 0 | - |
- December - 2020 |
No Image | |
1189 (OG) |
130382-Improvment of Water Supply, Sewerage/ Drainage System in Selected Districts of KP |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 750 | 680 | 10 | 10 | 0 | 0 | 680 | 0 | - |
- December - 2020 |
No Image | |
1189 (OG) |
130382-Improvment of Water Supply, Sewerage/ Drainage System in Selected Districts of KP |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 750 | 680 | 10 | 10 | 0 | 0 | 680 | 0 | - |
- October - 2020 |
No Image | |
1189 (OG) |
130382-Improvment of Water Supply, Sewerage/ Drainage System in Selected Districts of KP |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 750 | 680 | 10 | 10 | 0 | 0 | 680 | 0 | - |
- September - 2020 |
No Image | |
1189 (OG) |
130382-Improvment of Water Supply, Sewerage/ Drainage System in Selected Districts of KP |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 750 | 680 | 10 | 10 | 0 | 0 | 680 | 0 | - |
- August - 2020 |
No Image | |
1189 (OG) |
130382-Improvment of Water Supply, Sewerage/ Drainage System in Selected Districts of KP |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 750 | 680 | 10 | 0 | 0 | 0 | 680 | 0 | - |
- July - 2020 |
No Image | |
1189 (OG) |
130382-Improvment of Water Supply, Sewerage/ Drainage System in Selected Districts of KP |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 750 | 680 | 10 | 10 | 0 | 0 | 680 | 0 | - |
- May - 2021 |
No Image | |
1189 (OG) |
130382-Improvment of Water Supply, Sewerage/ Drainage System in Selected Districts of KP |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 750 | 680 | 10 | 10 | 0 | 0 | 680 | 0 | - |
- April - 2021 |
No Image | |
1189 (OG) |
130382-Improvment of Water Supply, Sewerage/ Drainage System in Selected Districts of KP |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 750 | 680 | 10 | 10 | 0 | 0 | 680 | 0 | - |
- March - 2021 |
No Image | |
1189 (OG) |
130382-Improvment of Water Supply, Sewerage/ Drainage System in Selected Districts of KP |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 750 | 680 | 10 | 10 | 0 | 0 | 680 | 0 | - |
- February - 2021 |
No Image | |
1189 (OG) |
130382-Improvment of Water Supply, Sewerage/ Drainage System in Selected Districts of KP |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 750 | 680 | 10 | 10 | 0 | 0 | 680 | 0 | - |
- January - 2021 |
No Image | |