Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1187 (OG) |
140630-F/S, Design and Construction of Barthan to Kasala Bara Road, District Abbottabad (8 Kms). |
Abbottabad |
06-06-15 | - | - | 27-03-15 | - | 80 | 56.95 | 30 | 25.65 | 10.65 | 10.65 | 67.6 | 0 | 100% |
85% December - 2017 |
Length 8 Km - earth work 100%, structure work 80%, road work 20%, WBM completed. |
No Image |
PK-47 | |||||||||||||||||||
1187 (OG) |
140630-F/S, Design and Construction of Barthan to Kasala Bara Road, District Abbottabad (8 Kms). |
Abbottabad |
06-06-15 | - | - | 27-03-15 | - | 80 | 56.95 | 30 | 30 | 10.65 | 10.65 | 67.6 | 0 | 100% |
85% September - 2017 |
Length 8 Km - earth work 100%, structure work 80%, road work 20%, WBM completed. |
No Image |
PK-47 | |||||||||||||||||||
1187 (OG) |
140630-F/S, Design and Construction of Barthan to Kasala Bara Road, District Abbottabad (8 Kms). |
Abbottabad |
06-06-15 | - | - | 27-03-15 | - | 80 | 56.95 | 30 | 30 | 10.65 | 8 | 64.95 | 0 | 100% |
81% August - 2017 |
Length 8 Km - earth work 100%, structure work 80%, road work 20%, WBM completed. |
No Image |
PK-47 | |||||||||||||||||||
1187 (OG) |
140630-F/S, Design and Construction of Barthan to Kasala Bara Road, District Abbottabad (8 Kms). |
Abbottabad |
06-06-15 | - | - | 27-03-15 | - | 80 | 56.95 | 30 | 30 | 10.65 | 0 | 56.95 | 0 | 100% |
71% July - 2017 |
Length 8 Km - earth work 100%, structure work 80%, road work 20%, WBM completed. |
No Image |
PK-47 | |||||||||||||||||||
1187 (OG) |
140630-F/S, Design and Construction of Barthan to Kasala Bara Road, District Abbottabad (8 Kms). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 80 | 56.95 | 30 | 25.65 | 10.65 | 10.65 | 67.6 | 0 | 100% |
85% November - 2017 |
Length 8 Km - earth work 100%, structure work 80%, road work 20%, WBM completed. |
No Image |
PK-47 | |||||||||||||||||||
1187 (OG) |
140630-F/S, Design and Construction of Barthan to Kasala Bara Road, District Abbottabad (8 Kms). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 80 | 56.95 | 30 | 30 | 10.65 | 10.65 | 67.6 | 0 | 100% |
85% October - 2017 |
Length 8 Km - earth work 100%, structure work 80%, road work 20%, WBM completed. |
No Image |
PK-47 | |||||||||||||||||||
1187 (OG) |
140630-F/S, Design and Construction of Barthan to Kasala Bara Road, District Abbottabad (8 Kms). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 126.5 | 56.95 | 30 | 30 | 30 | 24.17 | 81.12 | 39.55 | 69% |
64% June - 2018 |
Length 5 Km - earth work 100%, structure work 100%, road work 100% completed. |
No Image |
PK-47, Abbottabad | |||||||||||||||||||
1187 (OG) |
140630-F/S, Design and Construction of Barthan to Kasala Bara Road, District Abbottabad (8 Kms). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 126.5 | 56.95 | 30 | 30.047 | 30.047 | 24.17 | 81.12 | 39.55 | 69% |
64% May - 2018 |
Length 5 Km - earth work 100%, structure work 100%, road work 100% completed. |
No Image |
PK-47, Abbottabad | |||||||||||||||||||
1187 (OG) |
140630-F/S, Design and Construction of Barthan to Kasala Bara Road, District Abbottabad (8 Kms). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 126.5 | 56.95 | 30 | 30.047 | 30.047 | 24.17 | 81.12 | 39.55 | 69% |
64% April - 2018 |
Length 5 Km - earth work 100%, structure work 100%, road work 100% completed. |
No Image |
PK-47, Abbottabad | |||||||||||||||||||
1187 (OG) |
140630-F/S, Design and Construction of Barthan to Kasala Bara Road, District Abbottabad (8 Kms). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 80 | 56.95 | 30 | 30.047 | 30.047 | 24.17 | 81.12 | 0 | 100% |
100% March - 2018 |
Length 5 Km - earth work 100%, structure work 100%, road work 100% completed. |
No Image |
PK-47, Abbottabad | |||||||||||||||||||
1187 (OG) |
140630-F/S, Design and Construction of Barthan to Kasala Bara Road, District Abbottabad (8 Kms). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 80 | 56.95 | 30 | 27.357 | 27.357 | 24.17 | 81.12 | 0 | 100% |
100% February - 2018 |
Length 5 Km - earth work 100%, structure work 80%, road work 20%, WBM completed. |
No Image |
PK-47, Abbottabad | |||||||||||||||||||
1187 (OG) |
140630-F/S, Design and Construction of Barthan to Kasala Bara Road, District Abbottabad (8 Kms). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 80 | 56.95 | 30 | 27.357 | 27.357 | 10.65 | 67.6 | 0 | 100% |
85% January - 2018 |
Length 8 Km - earth work 100%, structure work 80%, road work 20%, WBM completed. |
No Image |
PK-47 | |||||||||||||||||||
1187 (New) |
190323-Construction of Detour Road Hayatabad remaining portion( Land and Construction Cost). |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 2000 | 0 | 100 | 100 | 0 | 0 | 0 | 0 | - |
- December - 2019 |
No Image | |
1187 (New) |
190323-Construction of Detour Road Hayatabad remaining portion( Land and Construction Cost). |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 2000 | 0 | 100 | 100 | 0 | 0 | 0 | 0 | - |
- November - 2019 |
No Image | |
1187 (New) |
190323-Construction of Detour Road Hayatabad remaining portion( Land and Construction Cost). |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 2000 | 0 | 100 | 100 | 0 | 0 | 0 | 0 | - |
- October - 2019 |
No Image | |
1187 (New) |
190323-Construction of Detour Road Hayatabad remaining portion( Land and Construction Cost). |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 2000 | 0 | 100 | 100 | 0 | 0 | 0 | 0 | - |
- September - 2019 |
No Image | |
1187 (New) |
190323-Construction of Detour Road Hayatabad remaining portion( Land and Construction Cost). |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 2000 | 0 | 100 | 100 | 0 | 0 | 0 | 0 | - |
- August - 2019 |
No Image | |
1187 (New) |
190323-Construction of Detour Road Hayatabad remaining portion( Land and Construction Cost). |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 2000 | 0 | 100 | 100 | 0 | 0 | 0 | 0 | - |
- May - 2020 |
No Image | |
1187 (New) |
190323-Construction of Detour Road Hayatabad remaining portion( Land and Construction Cost). |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 2000 | 0 | 100 | 100 | 0 | 0 | 0 | 0 | - |
- April - 2020 |
No Image | |
1187 (New) |
190323-Construction of Detour Road Hayatabad remaining portion( Land and Construction Cost). |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 2000 | 0 | 100 | 100 | 0 | 0 | 0 | 0 | - |
- March - 2020 |
No Image | |
1187 (New) |
190323-Construction of Detour Road Hayatabad remaining portion( Land and Construction Cost). |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 2000 | 0 | 100 | 100 | 0 | 0 | 0 | 0 | - |
- February - 2020 |
No Image | |
1187 (New) |
190323-Construction of Detour Road Hayatabad remaining portion( Land and Construction Cost). |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 2000 | 0 | 100 | 100 | 0 | 0 | 0 | 0 | - |
- January - 2020 |
No Image | |
1187 (OG) |
110326-Municipal Services Delivery Project. (USAID Assisted) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1105 | 833.327 | 0 | 0 | 0 | 0 | 833.327 | 0 | - |
- December - 2020 |
No Image | |
1187 (OG) |
110326-Municipal Services Delivery Project. (USAID Assisted) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1105 | 833.327 | 0 | 0 | 0 | 0 | 833.327 | 0 | - |
- December - 2020 |
No Image | |
1187 (OG) |
110326-Municipal Services Delivery Project. (USAID Assisted) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1105 | 833.327 | 0 | 0 | 0 | 0 | 833.327 | 0 | - |
- October - 2020 |
No Image | |
1187 (OG) |
110326-Municipal Services Delivery Project. (USAID Assisted) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1105 | 833.327 | 0 | 0 | 0 | 0 | 833.327 | 0 | - |
- September - 2020 |
No Image | |
1187 (OG) |
110326-Municipal Services Delivery Project. (USAID Assisted) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1105 | 833.327 | 0 | 0 | 0 | 0 | 833.327 | 0 | - |
- August - 2020 |
No Image | |
1187 (OG) |
110326-Municipal Services Delivery Project. (USAID Assisted) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1105 | 833.327 | 0 | 0 | 0 | 0 | 833.327 | 0 | - |
July - 2020 |
No Image | |
1187 (OG) |
110326-Municipal Services Delivery Project. (USAID Assisted) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1105 | 833.327 | 0 | 0 | 0 | 0 | 833.327 | 0 | - |
- May - 2021 |
No Image | |
1187 (OG) |
110326-Municipal Services Delivery Project. (USAID Assisted) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1105 | 833.327 | 0 | 0 | 0 | 0 | 833.327 | 0 | - |
- April - 2021 |
No Image | |
1187 (OG) |
110326-Municipal Services Delivery Project. (USAID Assisted) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1105 | 833.327 | 0 | 0 | 0 | 0 | 833.327 | 0 | - |
- March - 2021 |
No Image | |
1187 (OG) |
110326-Municipal Services Delivery Project. (USAID Assisted) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1105 | 833.327 | 0 | 0 | 0 | 0 | 833.327 | 0 | - |
- February - 2021 |
No Image | |
1187 (OG) |
110326-Municipal Services Delivery Project. (USAID Assisted) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1105 | 833.327 | 0 | 0 | 0 | 0 | 833.327 | 0 | - |
- January - 2021 |
No Image | |
Pages : 1 |