Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1182 (OG) |
160601-Development Package for District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 69.507 | 0 | 40 | 40 | 3 | 3 | 0 | 0 |
December - 2020 |
Executing agency of the scheme is AD LG&RD Deptt B |
No Image | |
1182 (OG) |
160601-Development Package for District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 69.507 | 0 | 40 | 40 | 3 | 3 | 0 | 0 |
December - 2020 |
Executing agency of the scheme is AD LG&RD Deptt B |
No Image | |
1182 (OG) |
160601-Development Package for District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 69.507 | 123.853 | 40 | 40 | 0 | 0 | 123.853 | 0 | 100% |
100% October - 2020 |
Executing agency of the scheme is AD LG&RD Deptt B |
No Image |
1182 (OG) |
160601-Development Package for District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 69.507 | 123.853 | 40 | 40 | 0 | 0 | 123.853 | 0 | 100% |
100% September - 2020 |
Executing agency of the scheme is AD LG&RD Deptt B |
No Image |
1182 (OG) |
160601-Development Package for District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 69.507 | 123.853 | 40 | 40 | 0 | 0 | 123.853 | 0 | 100% |
100% August - 2020 |
Executing agency of the scheme is AD LG&RD Deptt B |
No Image |
1182 (OG) |
160601-Development Package for District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 69.507 | 123.853 | 40 | 0 | 0 | 0 | 123.853 | 0 | 100% |
100% July - 2020 |
Executing agency of the scheme is AD LG&RD Deptt B |
No Image |
1182 (OG) |
160601-Development Package for District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 69.507 | 45.624 | 40 | 3 | 3 | 3 | 48.624 | 0 | 100% |
70% May - 2021 |
07 Units
05 Completed
02 Non availibility of funds work stopped
Demand Rs: 7.5 M |
No Image |
| |||||||||||||||||||
1182 (OG) |
160601-Development Package for District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 69.507 | 45.624 | 40 | 3 | 3 | 3 | 48.624 | 0 | 100% |
70% April - 2021 |
07 Units
05 Completed
02 Non availibility of funds work stopped
Demand Rs: 7.5 M |
No Image |
| |||||||||||||||||||
1182 (OG) |
160601-Development Package for District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 69.507 | 45.624 | 40 | 3 | 3 | 3 | 48.624 | 0 | 100% |
70% March - 2021 |
07 Units
05 Completed
02 Non availibility of funds work stopped
Demand Rs: 7.5 M |
No Image |
| |||||||||||||||||||
1182 (OG) |
160601-Development Package for District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 69.507 | 45.624 | 40 | 3 | 3 | 3 | 48.624 | 0 | 100% |
70% February - 2021 |
07 Units
05 Completed
02 Non availibility of funds work stopped
Demand Rs: 7.5 M |
No Image |
| |||||||||||||||||||
1182 (OG) |
160601-Development Package for District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 69.507 | 0 | 40 | 3 | 3 | 3 | 0 | 0 |
January - 2021 |
07 Units
05 Completed
02 Non availibility of funds work stopped |
No Image | |
1182 (OG) |
150869-Improvement / widening & Rehabilitation of Chakia Junglan Sundar Kalarian road and Shahkail Garhi Pairan road District Manshera. |
Mansehra |
- | - | - | 10-09-15 | - | 100 | 12.25 | 10 | 8.55 | 6.05 | 6.05 | 18.3 | 77.75 | 22% |
18% December - 2017 |
Length 7 Km - earth work 60%, WBM 40%, structure work 55% completed. |
No Image |
1182 (OG) |
150869-Improvement / widening & Rehabilitation of Chakia Junglan Sundar Kalarian road and Shahkail Garhi Pairan road District Manshera. |
Mansehra |
- | - | - | 10-09-15 | - | 100 | 12.25 | 10 | 10 | 3.55 | 3.55 | 15.8 | 77.75 | 22% |
16% September - 2017 |
Length 7 Km - earth work 60%, WBM 40%, structure work 55% completed. |
No Image |
1182 (OG) |
150869-Improvement / widening & Rehabilitation of Chakia Junglan Sundar Kalarian road and Shahkail Garhi Pairan road District Manshera. |
Mansehra |
- | - | - | 10-09-15 | - | 100 | 12.25 | 10 | 10 | 3.55 | 3.55 | 15.8 | 77.75 | 22% |
16% August - 2017 |
Length 7 Km - earth work 60%, WBM 40%, structure work 55% completed. |
No Image |
1182 (OG) |
150869-Improvement / widening & Rehabilitation of Chakia Junglan Sundar Kalarian road and Shahkail Garhi Pairan road District Manshera. |
Mansehra |
- | - | - | 10-09-15 | - | 100 | 12.25 | 10 | 10 | 3.55 | 0 | 12.25 | 77.75 | 22% |
12% July - 2017 |
Length 7 Km - earth work 60%, WBM 40%, structure work 55% completed. |
No Image |
1182 (OG) |
150869-Improvement / widening & Rehabilitation of Chakia Junglan Sundar Kalarian road and Shahkail Garhi Pairan road District Manshera. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 12.25 | 10 | 8.55 | 6.05 | 6.05 | 18.3 | 77.75 | 22% |
18% November - 2017 |
Length 7 Km - earth work 60%, WBM 40%, structure work 55% completed. |
No Image |
1182 (OG) |
150869-Improvement / widening & Rehabilitation of Chakia Junglan Sundar Kalarian road and Shahkail Garhi Pairan road District Manshera. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 12.25 | 10 | 10 | 3.55 | 3.55 | 15.8 | 77.75 | 22% |
16% October - 2017 |
Length 7 Km - earth work 60%, WBM 40%, structure work 55% completed. |
No Image |
1182 (OG) |
150869-Improvement / widening & Rehabilitation of Chakia Junglan Sundar Kalarian road and Shahkail Garhi Pairan road District Manshera. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 12.25 | 10 | 8.55 | 8.55 | 8.55 | 20.8 | 77.75 | 22% |
21% June - 2018 |
Length 7 Km (2 units ) - 3 Km BT completed. |
No Image |
PK-53, Mansehra | |||||||||||||||||||
1182 (OG) |
150869-Improvement / widening & Rehabilitation of Chakia Junglan Sundar Kalarian road and Shahkail Garhi Pairan road District Manshera. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 12.25 | 10 | 8.55 | 8.55 | 8.55 | 20.8 | 77.75 | 22% |
21% May - 2018 |
Length 7 Km (2 units ) - 3 Km BT completed. |
No Image |
PK-53, Mansehra | |||||||||||||||||||
1182 (OG) |
150869-Improvement / widening & Rehabilitation of Chakia Junglan Sundar Kalarian road and Shahkail Garhi Pairan road District Manshera. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 12.25 | 10 | 8.55 | 8.55 | 8.55 | 20.8 | 77.75 | 22% |
21% April - 2018 |
Length 7 Km (2 units ) - 3 Km BT completed. |
No Image |
PK-53, Mansehra | |||||||||||||||||||
1182 (OG) |
150869-Improvement / widening & Rehabilitation of Chakia Junglan Sundar Kalarian road and Shahkail Garhi Pairan road District Manshera. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 12.25 | 10 | 8.55 | 8.55 | 6.05 | 18.3 | 77.75 | 22% |
18% March - 2018 |
Length 7 Km (2 units ) - 3 Km BT completed. |
No Image |
PK-53, Mansehra | |||||||||||||||||||
1182 (OG) |
150869-Improvement / widening & Rehabilitation of Chakia Junglan Sundar Kalarian road and Shahkail Garhi Pairan road District Manshera. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 12.25 | 10 | 8.55 | 6.05 | 6.05 | 18.3 | 77.75 | 22% |
18% February - 2018 |
Length 7 Km (2 units ) - 3 km BT complted. |
No Image |
PK-53, Mansehra | |||||||||||||||||||
1182 (OG) |
150869-Improvement / widening & Rehabilitation of Chakia Junglan Sundar Kalarian road and Shahkail Garhi Pairan road District Manshera. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 12.25 | 10 | 8.55 | 6.05 | 6.05 | 18.3 | 77.75 | 22% |
18% January - 2018 |
Length 7 Km - earth work 60%, WBM 40%, structure work 55% completed. |
No Image |
1182 (OG) |
180536-F/S & Rehabilitation of Sewerage / Solid Waste Treatment Plants in Peshawar & Divisional Headquarters. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 21.58 | 0 | 21.58 | 21.58 | 0 | 0 | 0 | 0 | - |
- December - 2019 |
No Image | |
1182 (OG) |
180536-F/S & Rehabilitation of Sewerage / Solid Waste Treatment Plants in Peshawar & Divisional Headquarters. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 21.58 | 0 | 21.58 | 21.58 | 0 | 0 | 0 | 0 | - |
- November - 2019 |
No Image | |
1182 (OG) |
180536-F/S & Rehabilitation of Sewerage / Solid Waste Treatment Plants in Peshawar & Divisional Headquarters. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 21.58 | 0 | 21.58 | 21.58 | 0 | 0 | 0 | 0 | - |
- October - 2019 |
No Image | |
1182 (OG) |
180536-F/S & Rehabilitation of Sewerage / Solid Waste Treatment Plants in Peshawar & Divisional Headquarters. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 21.58 | 0 | 21.58 | 21.58 | 0 | 0 | 0 | 0 | - |
- September - 2019 |
No Image | |
1182 (OG) |
180536-F/S & Rehabilitation of Sewerage / Solid Waste Treatment Plants in Peshawar & Divisional Headquarters. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 21.58 | 0 | 21.58 | 21.58 | 0 | 0 | 0 | 0 | - |
- August - 2019 |
No Image | |
1182 (OG) |
180536-F/S & Rehabilitation of Sewerage / Solid Waste Treatment Plants in Peshawar & Divisional Headquarters. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 21.58 | 0 | 21.58 | 21.58 | 0 | 0 | 0 | 0 | - |
- May - 2020 |
No Image | |
1182 (OG) |
180536-F/S & Rehabilitation of Sewerage / Solid Waste Treatment Plants in Peshawar & Divisional Headquarters. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 21.58 | 0 | 21.58 | 21.58 | 0 | 0 | 0 | 0 | - |
- April - 2020 |
No Image | |
1182 (OG) |
180536-F/S & Rehabilitation of Sewerage / Solid Waste Treatment Plants in Peshawar & Divisional Headquarters. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 21.58 | 0 | 21.58 | 21.58 | 0 | 0 | 0 | 0 | - |
- March - 2020 |
No Image | |
1182 (OG) |
180536-F/S & Rehabilitation of Sewerage / Solid Waste Treatment Plants in Peshawar & Divisional Headquarters. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 21.58 | 0 | 21.58 | 21.58 | 0 | 0 | 0 | 0 | - |
- February - 2020 |
No Image | |
1182 (OG) |
180536-F/S & Rehabilitation of Sewerage / Solid Waste Treatment Plants in Peshawar & Divisional Headquarters. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 21.58 | 0 | 21.58 | 21.58 | 0 | 0 | 0 | 0 | - |
- January - 2020 |
No Image | |