Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2020, January - 2021, January - 2018, February - 2020, February - 2021, February - 2018, March - 2018, March - 2020, March - 2021, April - 2018, April - 2020, April - 2021, May - 2018, May - 2020, May - 2021, June - 2018, July - 2020, July - 2017, August - 2019, August - 2020, August - 2017, September - 2019, September - 2020, September - 2017, October - 2019, October - 2020, October - 2017, November - 2019, November - 2017, December - 2019, December - 2020, December - 2017,

Showing Page Number : 1 of 3

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1177
(OG)
140711-Improvement of Municipal Roads in Urban Areas of Khyber Pakhtunkhwa.
Bannu
30-11--1 30-11--1 - 30-11--1 - 49.997 16 10 10 10 3 19 23.997 52% 38%
December - 2019
Work order issued. Work not started due to local dispute.
No Image
1) Construction/rehabilitation of BTR of Tablighi Markaz Bannu Airport 2) Construction/rehabilitation of BTR Landy Killa Narmi Khel 3) Construction/rehabilitation of BTR from Marwat Canal to Ghora road Narmi Khel 4) Construction/rehabilitation of BTR of Main Jani Khel road 5) Construction/rehabilitation of BTR of Ghora Bakka Khel road from Mani Koroona to Bazid Koroona
1177
(OG)
140711-Improvement of Municipal Roads in Urban Areas of Khyber Pakhtunkhwa.
Bannu
30-11--1 30-11--1 - 30-11--1 - 49.997 16 10 10 10 3 19 23.997 52% 38%
November - 2019
Work order issued. Work not started due to local dispute.
No Image
1) Construction/rehabilitation of BTR of Tablighi Markaz Bannu Airport 2) Construction/rehabilitation of BTR Landy Killa Narmi Khel 3) Construction/rehabilitation of BTR from Marwat Canal to Ghora road Narmi Khel 4) Construction/rehabilitation of BTR of Main Jani Khel road 5) Construction/rehabilitation of BTR of Ghora Bakka Khel road from Mani Koroona to Bazid Koroona
1177
(OG)
140711-Improvement of Municipal Roads in Urban Areas of Khyber Pakhtunkhwa.
Bannu
30-11--1 30-11--1 - 30-11--1 - 49.997 16 0 0 0 0 16 33.997 - 32%
October - 2019
Work order issued.
No Image
1) Construction/rehabilitation of BTR of Tablighi Markaz Bannu Airport 2) Construction/rehabilitation of BTR Landy Killa Narmi Khel 3) Construction/rehabilitation of BTR from Marwat Canal to Ghora road Narmi Khel 4) Construction/rehabilitation of BTR of Main Jani Khel road 5) Construction/rehabilitation of BTR of Ghora Bakka Khel road from Mani Koroona to Bazid Koroona
1177
(OG)
140711-Improvement of Municipal Roads in Urban Areas of Khyber Pakhtunkhwa.
Bannu
30-11--1 30-11--1 - 30-11--1 - 49.997 16 0 0 0 0 16 33.997 - 32%
September - 2019
Work order issued.
No Image
1) Construction/rehabilitation of BTR of Tablighi Markaz Bannu Airport 2) Construction/rehabilitation of BTR Landy Killa Narmi Khel 3) Construction/rehabilitation of BTR from Marwat Canal to Ghora road Narmi Khel 4) Construction/rehabilitation of BTR of Main Jani Khel road 5) Construction/rehabilitation of BTR of Ghora Bakka Khel road from Mani Koroona to Bazid Koroona
1177
(OG)
140711-Improvement of Municipal Roads in Urban Areas of Khyber Pakhtunkhwa.
Bannu
30-11--1 30-11--1 - 30-11--1 - 49.997 16 0 0 0 0 16 33.997 - 32%
August - 2019
Work order issued.
No Image
1) Construction/rehabilitation of BTR of Tablighi Markaz Bannu Airport 2) Construction/rehabilitation of BTR Landy Killa Narmi Khel 3) Construction/rehabilitation of BTR from Marwat Canal to Ghora road Narmi Khel 4) Construction/rehabilitation of BTR of Main Jani Khel road 5) Construction/rehabilitation of BTR of Ghora Bakka Khel road from Mani Koroona to Bazid Koroona
1177
(OG)
140711-Improvement of Municipal Roads in Urban Areas of Khyber Pakhtunkhwa.
Bannu
30-11--1 30-11--1 - 30-11--1 - 49.997 16 23 23 23 5.869 21.869 10.997 78% 44%
May - 2020
Work order issued. Work not started due to local dispute.
No Image
1) Construction/rehabilitation of BTR of Tablighi Markaz Bannu Airport 2) Construction/rehabilitation of BTR Landy Killa Narmi Khel 3) Construction/rehabilitation of BTR from Marwat Canal to Ghora road Narmi Khel 4) Construction/rehabilitation of BTR of Main Jani Khel road 5) Construction/rehabilitation of BTR of Ghora Bakka Khel road from Mani Koroona to Bazid Koroona
1177
(OG)
140711-Improvement of Municipal Roads in Urban Areas of Khyber Pakhtunkhwa.
Bannu
30-11--1 30-11--1 - 30-11--1 - 49.997 16 23 23 23 5.869 21.869 10.997 78% 44%
April - 2020
Work order issued. Work not started due to local dispute.
No Image
1) Construction/rehabilitation of BTR of Tablighi Markaz Bannu Airport 2) Construction/rehabilitation of BTR Landy Killa Narmi Khel 3) Construction/rehabilitation of BTR from Marwat Canal to Ghora road Narmi Khel 4) Construction/rehabilitation of BTR of Main Jani Khel road 5) Construction/rehabilitation of BTR of Ghora Bakka Khel road from Mani Koroona to Bazid Koroona
1177
(OG)
140711-Improvement of Municipal Roads in Urban Areas of Khyber Pakhtunkhwa.
Bannu
30-11--1 30-11--1 - 30-11--1 - 49.997 16 23 23 23 5.869 21.869 10.997 78% 44%
March - 2020
Work order issued. Work not started due to local dispute.
No Image
1) Construction/rehabilitation of BTR of Tablighi Markaz Bannu Airport 2) Construction/rehabilitation of BTR Landy Killa Narmi Khel 3) Construction/rehabilitation of BTR from Marwat Canal to Ghora road Narmi Khel 4) Construction/rehabilitation of BTR of Main Jani Khel road 5) Construction/rehabilitation of BTR of Ghora Bakka Khel road from Mani Koroona to Bazid Koroona
1177
(OG)
140711-Improvement of Municipal Roads in Urban Areas of Khyber Pakhtunkhwa.
Bannu
30-11--1 30-11--1 - 30-11--1 - 49.997 16 23 23 23 5.869 21.869 10.997 78% 44%
February - 2020
Work order issued. Work not started due to local dispute.
No Image
1) Construction/rehabilitation of BTR of Tablighi Markaz Bannu Airport 2) Construction/rehabilitation of BTR Landy Killa Narmi Khel 3) Construction/rehabilitation of BTR from Marwat Canal to Ghora road Narmi Khel 4) Construction/rehabilitation of BTR of Main Jani Khel road 5) Construction/rehabilitation of BTR of Ghora Bakka Khel road from Mani Koroona to Bazid Koroona
1177
(OG)
140711-Improvement of Municipal Roads in Urban Areas of Khyber Pakhtunkhwa.
Bannu
30-11--1 30-11--1 - 30-11--1 - 49.997 16 10 10 10 3 19 23.997 52% 38%
January - 2020
Work order issued. Work not started due to local dispute.
No Image
1) Construction/rehabilitation of BTR of Tablighi Markaz Bannu Airport 2) Construction/rehabilitation of BTR Landy Killa Narmi Khel 3) Construction/rehabilitation of BTR from Marwat Canal to Ghora road Narmi Khel 4) Construction/rehabilitation of BTR of Main Jani Khel road 5) Construction/rehabilitation of BTR of Ghora Bakka Khel road from Mani Koroona to Bazid Koroona
1177
(OG)
160604-Special Initiative Programm for District Charsada
Charsadda
30-11--1 30-11--1 - 30-11--1 - 250 124.352 60 60 0 0 124.352 65.648 74% 50%
December - 2020
Roads, Janazagah, Streets in progress. School completed.
No Image
1) PK-17
2) PK-18
3) PK-19
4) PK-20
5) PK-21
6) PK-22
1177
(OG)
160604-Special Initiative Programm for District Charsada
Charsadda
30-11--1 30-11--1 - 30-11--1 - 250 124.352 60 60 0 0 124.352 65.648 74% 50%
December - 2020
Roads, Janazagah, Streets in progress. School completed.
No Image
1) PK-17
2) PK-18
3) PK-19
4) PK-20
5) PK-21
6) PK-22
1177
(OG)
160604-Special Initiative Programm for District Charsada
Charsadda
30-11--1 30-11--1 - 30-11--1 - 250 124.352 60 60 0 0 124.352 65.648 74% 50%
October - 2020
Roads, Janazagah, Streets in progress. School completed.
No Image
1) PK-17
2) PK-18
3) PK-19
4) PK-20
5) PK-21
6) PK-22
1177
(OG)
160604-Special Initiative Programm for District Charsada
Charsadda
30-11--1 30-11--1 - 30-11--1 - 250 124.352 60 60 0 0 124.352 65.648 74% 50%
September - 2020
Roads, Janazagah, Streets in progress. School completed.
No Image
1) PK-17
2) PK-18
3) PK-19
4) PK-20
5) PK-21
6) PK-22
1177
(OG)
160604-Special Initiative Programm for District Charsada
Charsadda
30-11--1 30-11--1 - 30-11--1 - 250 124.352 60 60 0 0 124.352 65.648 74% 50%
August - 2020
Roads, Janazagah, Streets in progress. School completed.
No Image
1) PK-17
2) PK-18
3) PK-19
4) PK-20
5) PK-21
6) PK-22
1177
(OG)
160604-Special Initiative Programm for District Charsada
Charsadda
30-11--1 30-11--1 - 30-11--1 - 250 124.352 60 0 0 0 124.352 65.648 74% 50%
July - 2020
Roads, Janazagah, Streets in progress. School completed.
No Image
1) PK-17
2) PK-18
1177
(OG)
160604-Special Initiative Programm for District Charsada
Charsadda
30-11--1 30-11--1 - 30-11--1 - 250 124.352 60 0 0 0 124.352 65.648 74% 50%
May - 2021
Revised PC-I Submitted to Local Govt: Deptt: Roads, Janazagah, Streets in progress. School completed.
No Image
1) PK-17
2) PK-18
3) PK-19
4) PK-20
5) PK-21
6) PK-22
1177
(OG)
160604-Special Initiative Programm for District Charsada
Charsadda
30-11--1 30-11--1 - 30-11--1 - 250 124.352 60 0 0 0 124.352 65.648 74% 50%
April - 2021
Revised PC-I Submitted to Local Govt: Deptt: Roads, Janazagah, Streets in progress. School completed.
No Image
1) PK-17
2) PK-18
3) PK-19
4) PK-20
5) PK-21
6) PK-22
1177
(OG)
160604-Special Initiative Programm for District Charsada
Charsadda
30-11--1 30-11--1 - 30-11--1 - 250 124.352 60 0 0 0 124.352 65.648 74% 50%
March - 2021
Revised PC-I Submitted to Local Govt: Deptt: Roads, Janazagah, Streets in progress. School completed.
No Image
1) PK-17
2) PK-18
3) PK-19
4) PK-20
5) PK-21
6) PK-22
1177
(OG)
160604-Special Initiative Programm for District Charsada
Charsadda
30-11--1 30-11--1 - 30-11--1 - 250 124.352 60 0 0 0 124.352 65.648 74% 50%
February - 2021
Revised PC-I Submitted to Local Govt: Deptt: Roads, Janazagah, Streets in progress. School completed.
No Image
1) PK-17
2) PK-18
3) PK-19
4) PK-20
5) PK-21
6) PK-22
1177
(OG)
160604-Special Initiative Programm for District Charsada
Charsadda
30-11--1 30-11--1 - 30-11--1 - 250 124.352 60 60 0 0 124.352 65.648 74% 50%
January - 2021
Roads, Janazagah, Streets in progress. School completed.
No Image
1) PK-17
2) PK-18
3) PK-19
4) PK-20
5) PK-21
6) PK-22
1177
(OG)
140711-Improvement of Municipal Roads in Urban Areas of Khyber Pakhtunkhwa.
D.I.Khan
HW
30-11--1 30-11--1 - 30-11--1 - 49.787 0 3 3 3 3 3 46.787 6% 6%
December - 2019
Work in progress.
No Image
1) Construction of BT road of Kuhawar Village (balance portion)
2) Construction of BT road from Gandi Ashiq Gandi Umer Khanroad to Mochiwal Village (balance portion)
3) Rehabilitation of Kulachi City roads/street
1177
(OG)
140711-Improvement of Municipal Roads in Urban Areas of Khyber Pakhtunkhwa.
D.I.Khan
HW
30-11--1 30-11--1 - 30-11--1 - 49.787 0 3 3 3 3 3 46.787 6% 6%
November - 2019
Work in progress.
No Image
1) Construction of BT road of Kuhawar Village (balance portion)
2) Construction of BT road from Gandi Ashiq Gandi Umer Khanroad to Mochiwal Village (balance portion)
3) Rehabilitation of Kulachi City roads/street
1177
(OG)
140711-Improvement of Municipal Roads in Urban Areas of Khyber Pakhtunkhwa.
D.I.Khan
HW
30-11--1 30-11--1 - 30-11--1 - 49.787 0 3 3 3 3 3 46.787 6% 6%
October - 2019
Work in progress.
No Image
1) Construction of BT road of Kuhawar Village (balance portion)
2) Construction of BT road from Gandi Ashiq Gandi Umer Khanroad to Mochiwal Village (balance portion)
3) Rehabilitation of Kulachi City roads/street
1177
(OG)
140711-Improvement of Municipal Roads in Urban Areas of Khyber Pakhtunkhwa.
D.I.Khan
HW
30-11--1 30-11--1 - 30-11--1 - 49.787 0 0 0 0 0 0 49.787 - -
September - 2019
Work order issued to contractor.
No Image
1) Construction of BT road of Kuhawar Village (balance portion)
2) Construction of BT road from Gandi Ashiq Gandi Umer Khanroad to Mochiwal Village (balance portion)
3) Rehabilitation of Kulachi City roads/street
1177
(OG)
140711-Improvement of Municipal Roads in Urban Areas of Khyber Pakhtunkhwa.
D.I.Khan
HW
30-11--1 30-11--1 - 30-11--1 - 49.787 0 0 0 0 0 0 49.787 - -
August - 2019
Work order issued to contractor.
No Image
1) Construction of BT road of Kuhawar Village (balance portion)
2) Construction of BT road from Gandi Ashiq Gandi Umer Khanroad to Mochiwal Village (balance portion)
3) Rehabilitation of Kulachi City roads/street
1177
(OG)
140711-Improvement of Municipal Roads in Urban Areas of Khyber Pakhtunkhwa.
D.I.Khan
HW
30-11--1 30-11--1 - 30-11--1 - 49.787 0 3 3 3 3 3 46.787 6% 6%
May - 2020
Work in progress.
No Image
1) Construction of BT road of Kuhawar Village (balance portion)
2) Construction of BT road from Gandi Ashiq Gandi Umer Khanroad to Mochiwal Village (balance portion)
3) Rehabilitation of Kulachi City roads/street
1177
(OG)
140711-Improvement of Municipal Roads in Urban Areas of Khyber Pakhtunkhwa.
D.I.Khan
HW
30-11--1 30-11--1 - 30-11--1 - 49.787 0 3 3 3 3 3 46.787 6% 6%
April - 2020
Work in progress.
No Image
1) Construction of BT road of Kuhawar Village (balance portion)
2) Construction of BT road from Gandi Ashiq Gandi Umer Khanroad to Mochiwal Village (balance portion)
3) Rehabilitation of Kulachi City roads/street
1177
(OG)
140711-Improvement of Municipal Roads in Urban Areas of Khyber Pakhtunkhwa.
D.I.Khan
HW
30-11--1 30-11--1 - 30-11--1 - 49.787 0 3 3 3 3 3 46.787 6% 6%
March - 2020
Work in progress.
No Image
1) Construction of BT road of Kuhawar Village (balance portion)
2) Construction of BT road from Gandi Ashiq Gandi Umer Khanroad to Mochiwal Village (balance portion)
3) Rehabilitation of Kulachi City roads/street
1177
(OG)
140711-Improvement of Municipal Roads in Urban Areas of Khyber Pakhtunkhwa.
D.I.Khan
HW
30-11--1 30-11--1 - 30-11--1 - 49.787 0 3 3 3 3 3 46.787 6% 6%
February - 2020
Work in progress.
No Image
1) Construction of BT road of Kuhawar Village (balance portion)
2) Construction of BT road from Gandi Ashiq Gandi Umer Khanroad to Mochiwal Village (balance portion)
3) Rehabilitation of Kulachi City roads/street
1177
(OG)
140711-Improvement of Municipal Roads in Urban Areas of Khyber Pakhtunkhwa.
D.I.Khan
HW
30-11--1 30-11--1 - 30-11--1 - 49.787 0 3 3 3 3 3 46.787 6% 6%
January - 2020
Work in progress.
No Image
1) Construction of BT road of Kuhawar Village (balance portion)
2) Construction of BT road from Gandi Ashiq Gandi Umer Khanroad to Mochiwal Village (balance portion)
3) Rehabilitation of Kulachi City roads/street
1177
(OG)
140711-Improvement of Municipal Roads in Urban Areas of Khyber Pakhtunkhwa.
Karak
30-11--1 30-11--1 - 30-11--1 - 10 8.778 0 0 0 0 8.778 1.222 - 88%
December - 2019
BTR Wanki Siraj Khel - earth work 90%, sub base 100%, WBM 90%, structure work 90% completed. BTR Mandawa - completed. Court Case (Wanki Siraj khel).
No Image
1) BTR from Wanki Siraj Khel to Zarki Nasratti via Mohallah Zargaran (0.579 Km)
2) BTR Mandawa (1.25 Km)
1177
(OG)
140711-Improvement of Municipal Roads in Urban Areas of Khyber Pakhtunkhwa.
Karak
30-11--1 30-11--1 - 30-11--1 - 10 8.778 0 0 0 0 8.778 1.222 - 88%
November - 2019
BTR Wanki Siraj Khel - earth work 90%, sub base 100%, WBM 90%, structure work 90% completed. BTR Mandawa - completed. Court Case (Wanki Siraj khel).
No Image
1) BTR from Wanki Siraj Khel to Zarki Nasratti via Mohallah Zargaran (0.579 Km)
2) BTR Mandawa (1.25 Km)
1177
(OG)
140711-Improvement of Municipal Roads in Urban Areas of Khyber Pakhtunkhwa.
Karak
30-11--1 30-11--1 - 30-11--1 - 10 8.778 0 0 0 0 8.778 1.222 - 88%
October - 2019
BTR Wanki Siraj Khel - earth work 90%, sub base 100%, WBM 90%, structure work 90% completed. BTR Mandawa - completed. Court Case (Wanki Siraj khel).
No Image
1) BTR from Wanki Siraj Khel to Zarki Nasratti via Mohallah Zargaran (0.579 Km)
2) BTR Mandawa (1.25 Km)
1177
(OG)
140711-Improvement of Municipal Roads in Urban Areas of Khyber Pakhtunkhwa.
Karak
30-11--1 30-11--1 - 30-11--1 - 10 8.778 0 0 0 0 8.778 1.222 - 88%
September - 2019
BTR Wanki Siraj Khel - earth work 90%, sub base 100%, WBM 90%, structure work 90% completed. BTR Mandawa - completed. Court Case (Wanki Siraj khel).
No Image
1) BTR from Wanki Siraj Khel to Zarki Nasratti via Mohallah Zargaran (0.579 Km)
2) BTR Mandawa (1.25 Km)
1177
(OG)
140711-Improvement of Municipal Roads in Urban Areas of Khyber Pakhtunkhwa.
Karak
30-11--1 30-11--1 - 30-11--1 - 10 8.778 0 0 0 0 8.778 1.222 - 88%
August - 2019
BTR Wanki Siraj Khel - earth work 90%, sub base 100%, WBM 90%, structure work 90% completed. BTR Mandawa - completed. Court Case.
No Image
1) BTR from Wanki Siraj Khel to Zarki Nasratti via Mohallah Zargaran (0.579 Km)
2) BTR Mandawa (1.25 Km)
1177
(OG)
140711-Improvement of Municipal Roads in Urban Areas of Khyber Pakhtunkhwa.
Karak
30-11--1 30-11--1 - 30-11--1 - 10 8.778 0 0 0 0 8.778 1.222 - 88%
May - 2020
BTR Wanki Siraj Khel - earth work 90%, sub base 100%, WBM 90%, structure work 90% completed. BTR Mandawa - completed. Court Case (Wanki Siraj khel).
No Image
1) BTR from Wanki Siraj Khel to Zarki Nasratti via Mohallah Zargaran (0.579 Km)
2) BTR Mandawa (1.25 Km)
1177
(OG)
140711-Improvement of Municipal Roads in Urban Areas of Khyber Pakhtunkhwa.
Karak
30-11--1 30-11--1 - 30-11--1 - 10 8.778 0 0 0 0 8.778 1.222 - 88%
April - 2020
BTR Wanki Siraj Khel - earth work 90%, sub base 100%, WBM 90%, structure work 90% completed. BTR Mandawa - completed. Court Case (Wanki Siraj khel).
No Image
1) BTR from Wanki Siraj Khel to Zarki Nasratti via Mohallah Zargaran (0.579 Km)
2) BTR Mandawa (1.25 Km)
1177
(OG)
140711-Improvement of Municipal Roads in Urban Areas of Khyber Pakhtunkhwa.
Karak
30-11--1 30-11--1 - 30-11--1 - 10 8.778 0 0 0 0 8.778 1.222 - 88%
March - 2020
BTR Wanki Siraj Khel - earth work 90%, sub base 100%, WBM 90%, structure work 90% completed. BTR Mandawa - completed. Court Case (Wanki Siraj khel).
No Image
1) BTR from Wanki Siraj Khel to Zarki Nasratti via Mohallah Zargaran (0.579 Km)
2) BTR Mandawa (1.25 Km)
1177
(OG)
140711-Improvement of Municipal Roads in Urban Areas of Khyber Pakhtunkhwa.
Karak
30-11--1 30-11--1 - 30-11--1 - 10 8.778 0 0 0 0 8.778 1.222 - 88%
February - 2020
BTR Wanki Siraj Khel - earth work 90%, sub base 100%, WBM 90%, structure work 90% completed. BTR Mandawa - completed. Court Case (Wanki Siraj khel).
No Image
1) BTR from Wanki Siraj Khel to Zarki Nasratti via Mohallah Zargaran (0.579 Km)
2) BTR Mandawa (1.25 Km)
1177
(OG)
140711-Improvement of Municipal Roads in Urban Areas of Khyber Pakhtunkhwa.
Karak
30-11--1 30-11--1 - 30-11--1 - 10 8.778 0 0 0 0 8.778 1.222 - 88%
January - 2020
BTR Wanki Siraj Khel - earth work 90%, sub base 100%, WBM 90%, structure work 90% completed. BTR Mandawa - completed. Court Case (Wanki Siraj khel).
No Image
1) BTR from Wanki Siraj Khel to Zarki Nasratti via Mohallah Zargaran (0.579 Km)
2) BTR Mandawa (1.25 Km)
1177
(OG)
140711-Improvement of Municipal Roads in Urban Areas of Khyber Pakhtunkhwa.
Kohat
30-11--1 30-11--1 - 30-11--1 - 50 0 0 0 0 0 0 50 - -
December - 2019
Approved.
No Image
1) Construction/rehabilitation of Pai Daraki road
2) Construction/rehabilitation of Muhammad Akbar Amakhel road
3) Construction of bridge for village Kotkat
4) Construction/rehabilitation of Marma Gul Nawaz
5) Construction of 1 Kmroad for Main City Bazar
1177
(OG)
140711-Improvement of Municipal Roads in Urban Areas of Khyber Pakhtunkhwa.
Kohat
30-11--1 30-11--1 - 30-11--1 - 50 0 0 0 0 0 0 50 - -
November - 2019
Approved.
No Image
1) Construction/rehabilitation of Pai Daraki road
2) Construction/rehabilitation of Muhammad Akbar Amakhel road
3) Construction of bridge for village Kotkat
4) Construction/rehabilitation of Marma Gul Nawaz
5) Construction of 1 Kmroad for Main City Bazar
1177
(OG)
140711-Improvement of Municipal Roads in Urban Areas of Khyber Pakhtunkhwa.
Kohat
30-11--1 30-11--1 - 30-11--1 - 50 0 0 0 0 0 0 50 - -
October - 2019
Approved.
No Image
1) Construction/rehabilitation of Pai Daraki road
2) Construction/rehabilitation of Muhammad Akbar Amakhel road
3) Construction of bridge for village Kotkat
4) Construction/rehabilitation of Marma Gul Nawaz
5) Construction of 1 Kmroad for Main City Bazar
1177
(OG)
140711-Improvement of Municipal Roads in Urban Areas of Khyber Pakhtunkhwa.
Kohat
30-11--1 30-11--1 - 30-11--1 - 50 0 0 0 0 0 0 50 - -
September - 2019
Approved.
No Image
1) Construction/rehabilitation of Pai Daraki road
2) Construction/rehabilitation of Muhammad Akbar Amakhel road
3) Construction of bridge for village Kotkat
4) Construction/rehabilitation of Marma Gul Nawaz
5) Construction of 1 Kmroad for Main City Bazar
1177
(OG)
140711-Improvement of Municipal Roads in Urban Areas of Khyber Pakhtunkhwa.
Kohat
30-11--1 30-11--1 - 30-11--1 - 50 0 0 0 0 0 0 50 - -
August - 2019
Approved.
No Image
1) Construction/rehabilitation of Pai Daraki road
2) Construction/rehabilitation of Muhammad Akbar Amakhel road
3) Construction of bridge for village Kotkat
4) Construction/rehabilitation of Marma Gul Nawaz
5) Construction of 1 Kmroad for Main City Bazar
1177
(OG)
140711-Improvement of Municipal Roads in Urban Areas of Khyber Pakhtunkhwa.
Kohat
30-11--1 30-11--1 - 30-11--1 - 50 0 0 0 0 0 0 50 - -
May - 2020
Approved.
No Image
1) Construction/rehabilitation of Pai Daraki road
2) Construction/rehabilitation of Muhammad Akbar Amakhel road
3) Construction of bridge for village Kotkat
4) Construction/rehabilitation of Marma Gul Nawaz
5) Construction of 1 Kmroad for Main City Bazar
1177
(OG)
140711-Improvement of Municipal Roads in Urban Areas of Khyber Pakhtunkhwa.
Kohat
30-11--1 30-11--1 - 30-11--1 - 50 0 0 0 0 0 0 50 - -
April - 2020
Approved.
No Image
1) Construction/rehabilitation of Pai Daraki road
2) Construction/rehabilitation of Muhammad Akbar Amakhel road
3) Construction of bridge for village Kotkat
4) Construction/rehabilitation of Marma Gul Nawaz
5) Construction of 1 Kmroad for Main City Bazar
1177
(OG)
140711-Improvement of Municipal Roads in Urban Areas of Khyber Pakhtunkhwa.
Kohat
30-11--1 30-11--1 - 30-11--1 - 50 0 0 0 0 0 0 50 - -
March - 2020
Approved.
No Image
1) Construction/rehabilitation of Pai Daraki road
2) Construction/rehabilitation of Muhammad Akbar Amakhel road
3) Construction of bridge for village Kotkat
4) Construction/rehabilitation of Marma Gul Nawaz
5) Construction of 1 Kmroad for Main City Bazar
1177
(OG)
140711-Improvement of Municipal Roads in Urban Areas of Khyber Pakhtunkhwa.
Kohat
30-11--1 30-11--1 - 30-11--1 - 50 0 0 0 0 0 0 50 - -
February - 2020
Approved.
No Image
1) Construction/rehabilitation of Pai Daraki road
2) Construction/rehabilitation of Muhammad Akbar Amakhel road
3) Construction of bridge for village Kotkat
4) Construction/rehabilitation of Marma Gul Nawaz
5) Construction of 1 Kmroad for Main City Bazar
Pages : 1 2 3