Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2018, February - 2018, March - 2018, April - 2018, May - 2018, June - 2018, July - 2017, August - 2017, September - 2017, October - 2017, November - 2017, December - 2017,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1167
(OG)
130420-Construction of Pre Stressed RCC Bridge over Indus River from KKH to Seo village at Dassu Kohistan.
Kohistan
15-05-10 30-06-18 - 29-05-14 - 322.534 153.755 112.653 112.653 56.327 6.859 160.614 56.126 83% 50%
December - 2017
35/48 piles, 6/9 girder, left abutment completed. Piling on right side in progress. Right approach road earth work completed. 1/2 pier in progress.
No Image
1167
(OG)
130420-Construction of Pre Stressed RCC Bridge over Indus River from KKH to Seo village at Dassu Kohistan.
Kohistan
15-05-10 30-06-18 - 29-05-14 - 322.534 153.755 112.653 112.653 56.327 3.69 157.445 56.126 83% 49%
September - 2017
35/48 piles, 6/9 girder, left abutment completed. Piling on right side in progress. Right approach road earth work completed. 1/2 pier in progress.
No Image
1167
(OG)
130420-Construction of Pre Stressed RCC Bridge over Indus River from KKH to Seo village at Dassu Kohistan.
Kohistan
15-05-10 30-06-18 - 29-05-14 - 322.534 153.755 112.653 112.653 39.992 3.69 157.445 56.126 83% 49%
August - 2017
35/48 piles, 6/9 girder, left abutment completed. Piling on right side in progress. Right approach road earth work completed. 1/2 pier in progress.
No Image
1167
(OG)
130420-Construction of Pre Stressed RCC Bridge over Indus River from KKH to Seo village at Dassu Kohistan.
Kohistan
15-05-10 30-06-18 - 29-05-14 - 322.534 153.755 112.653 112.653 39.992 0 153.755 56.126 83% 48%
July - 2017
35/48 piles, 6/9 girder, left abutment completed. Piling on right side in progress. Right approach road earth work completed. 1/2 pier in progress.
No Image
1167
(OG)
130420-Construction of Pre Stressed RCC Bridge over Indus River from KKH to Seo village at Dassu Kohistan.
Kohistan
30-11--1 30-11--1 - 30-11--1 - 322.534 153.755 112.653 112.653 56.327 6.5 160.255 56.126 83% 50%
November - 2017
35/48 piles, 6/9 girder, left abutment completed. Piling on right side in progress. Right approach road earth work completed. 1/2 pier in progress.
No Image
1167
(OG)
130420-Construction of Pre Stressed RCC Bridge over Indus River from KKH to Seo village at Dassu Kohistan.
Kohistan
30-11--1 30-11--1 - 30-11--1 - 322.534 153.755 112.653 112.653 56.327 3.69 157.445 56.126 83% 49%
October - 2017
35/48 piles, 6/9 girder, left abutment completed. Piling on right side in progress. Right approach road earth work completed. 1/2 pier in progress.
No Image
1167
(OG)
130420-Construction of Pre Stressed RCC Bridge over Indus River from KKH to Seo village at Dassu Kohistan.
Kohistan
30-11--1 30-11--1 - 30-11--1 - 322.534 153.755 112.653 43.955 43.955 43.955 197.71 56.126 83% 61%
June - 2018
Length 210 m tr - 35/48 piles, 6/9 girder, left and right abutment completed. Right approach road earth work completed. 1/2 pier in progress.
No Image
Dassu Kohistan
1167
(OG)
130420-Construction of Pre Stressed RCC Bridge over Indus River from KKH to Seo village at Dassu Kohistan.
Kohistan
30-11--1 30-11--1 - 30-11--1 - 322.534 153.755 112.653 112.653 112.653 44.653 198.408 56.126 83% 62%
May - 2018
Length 210 m tr - 35/48 piles, 6/9 girder, left and right abutment completed. Right approach road earth work completed. 1/2 pier in progress.
No Image
Dassu Kohistan
1167
(OG)
130420-Construction of Pre Stressed RCC Bridge over Indus River from KKH to Seo village at Dassu Kohistan.
Kohistan
30-11--1 30-11--1 - 30-11--1 - 322.534 153.755 112.653 112.653 56.327 6.859 160.614 56.126 83% 50%
April - 2018
Length 210 m tr - 35/48 piles, 6/9 girder, left and right abutment completed. Right approach road earth work completed. 1/2 pier in progress.
No Image
Dassu Kohistan
1167
(OG)
130420-Construction of Pre Stressed RCC Bridge over Indus River from KKH to Seo village at Dassu Kohistan.
Kohistan
30-11--1 30-11--1 - 30-11--1 - 322.534 153.755 112.653 112.653 56.327 6.859 160.614 56.126 83% 50%
March - 2018
Length 210 m tr - 35/48 piles, 6/9 girder, left and right abutment completed. Right approach road earth work completed. 1/2 pier in progress.
No Image
Dassu Kohistan
1167
(OG)
130420-Construction of Pre Stressed RCC Bridge over Indus River from KKH to Seo village at Dassu Kohistan.
Kohistan
30-11--1 30-11--1 - 30-11--1 - 322.534 153.755 112.653 112.653 56.327 6.859 160.614 56.126 83% 50%
February - 2018
length 210 m - 35/48 piles, 6/9 girder, left and Right abutment completed. Right approach road earth work completed. 1/2 pier in progress.
ADP's Images
1167
(OG)
130420-Construction of Pre Stressed RCC Bridge over Indus River from KKH to Seo village at Dassu Kohistan.
Kohistan
30-11--1 30-11--1 - 30-11--1 - 322.534 153.755 112.653 112.653 56.327 6.859 160.614 56.126 83% 50%
January - 2018
35/48 piles, 6/9 girder, left abutment completed. Piling on right side in progress. Right approach road earth work completed. 1/2 pier in progress.