Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1159 (OG) |
90417-Widening & Carpeting of Booni Buzand Torkhow road (28 Km) District Chitral (PSDP Funded). |
Chitral |
01-06-10 | - | - | 09-03-15 | - | 1108.42 | 301.11 | 10 | 3 | 0.5 | 0 | 301.11 | 797.31 | 28% |
27% December - 2017 |
Original approval for Rs.279.922 m. PSDP share - 100%, GoKP share - 0%. The work started in 2010-11. Length 28 Km - earth work 17 Km completed, structure work 60% in progress. Land clearnce 6 km not yet cleared by DC office. Work on 2/4 No. RCC bridge in progress. Work on 5 km cutting in progress. Time extension submitted to CDWP. Releases will be made after approval of time extension. |
No Image |
1159 (OG) |
90417-Widening & Carpeting of Booni Buzand Torkhow road (28 Km) District Chitral (PSDP Funded). |
Chitral |
01-06-10 | - | - | 09-03-15 | - | 1108.42 | 0 | 0 | 0 | 0 | 0 | 0 | 1108.42 | - |
- December - 2017 |
Original approval for Rs.279.922 m. PSDP sha.re - 100%, GoKP share - 0%. The work started in 2010-11. Length 28 Km - earth work 17 km completed, structure work 60% in progress. Land clearnce 6 km not yet cleared by DC office. Work on 2/4 No. RCC bridge in progress. Work on 5 km cutting in progress. Time extension submitted to CDWP. Releases will be made after approval of time extension. |
No Image |
1159 (OG) |
90417-Widening & Carpeting of Booni Buzand Torkhow road (28 Km) District Chitral (PSDP Funded). |
Chitral |
01-06-10 | - | - | 09-03-15 | - | 1108.42 | 301.11 | 10 | 10 | 3.55 | 0 | 301.11 | 797.31 | 28% |
27% September - 2017 |
Original approval for Rs.279.922 m. PSDP share - 100%, GoKP share - 0%. The work started in 2010-11. Length 28 Km - earth work 17 km complted , structure work 60% in progress. Land clearnce 6 km not yet cleared by DC office . Work on 2/4 No. RCC bridge in progress. Work on 5 km cutting in progress. |
No Image |
1159 (OG) |
90417-Widening & Carpeting of Booni Buzand Torkhow road (28 Km) District Chitral (PSDP Funded). |
Chitral |
01-06-10 | - | - | 09-03-15 | - | 1108.42 | 0 | 0 | 0 | 0 | 0 | 0 | 1108.42 | - |
- September - 2017 |
Original approval for Rs.279.922 m. PSDP share - 100%, GoKP share - 0%. The work started in 2010-11. Length 28 Km - earth work 65%, structure work 60% in progress. Rs.100 m demanded from Federal Govt. |
No Image |
1159 (OG) |
90417-Widening & Carpeting of Booni Buzand Torkhow road (28 Km) District Chitral (PSDP Funded). |
Chitral |
01-06-10 | - | - | 09-03-15 | - | 1108.42 | 301.11 | 10 | 10 | 3.55 | 0 | 301.11 | 797.31 | 28% |
27% August - 2017 |
Original approval for Rs.279.922 m. PSDP share - 100%, GoKP share - 0%. The work started in 2010-11. Length 28 Km - earth work 65%, structure work 60% in progress. |
No Image |
1159 (OG) |
90417-Widening & Carpeting of Booni Buzand Torkhow road (28 Km) District Chitral (PSDP Funded). |
Chitral |
01-06-10 | - | - | 09-03-15 | - | 1108.42 | 0 | 0 | 0 | 0 | 0 | 0 | 1108.42 | - |
- August - 2017 |
Original approval for Rs.279.922 m. PSDP share - 100%, GoKP share - 0%. The work started in 2010-11. Length 28 Km - earth work 65%, structure work 60% in progress. Rs.100 m demanded from Federal Govt. |
No Image |
1159 (OG) |
90417-Widening & Carpeting of Booni Buzand Torkhow road (28 Km) District Chitral (PSDP Funded). |
Chitral |
01-06-10 | - | - | 09-03-15 | - | 1108.42 | 301.11 | 10 | 10 | 3.55 | 0 | 301.11 | 797.31 | 28% |
27% July - 2017 |
Original approval for Rs.279.922 m. PSDP share - 100%, GoKP share - 0%. The work started in 2010-11. Length 28 Km - earth work 65%, structure work 60% in progress. |
No Image |
1159 (OG) |
90417-Widening & Carpeting of Booni Buzand Torkhow road (28 Km) District Chitral (PSDP Funded). |
Chitral |
01-06-10 | - | - | 09-03-15 | - | 1108.42 | 0 | 0 | 0 | 0 | 0 | 0 | 1108.42 | - |
- July - 2017 |
Original approval for Rs.279.922 m. PSDP share - 100%, GoKP share - 0%. The work started in 2010-11. Length 28 Km - earth work 65%, structure work 60% in progress. Rs.100 m demanded from Federal Govt. |
No Image |
1159 (OG) |
90417-Widening & Carpeting of Booni Buzand Torkhow road (28 Km) District Chitral (PSDP Funded). |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1108.42 | 301.11 | 10 | 0 | 0 | 0 | 301.11 | 797.31 | 28% |
27% November - 2017 |
Original approval for Rs.279.922 m. PSDP share - 100%, GoKP share - 0%. The work started in 2010-11. Length 28 Km - earth work 17 Km completed, structure work 60% in progress. Land clearnce 6 km not yet cleared by DC office . Work on 2/4 No. RCC bridge in progress. Work on 5 km cutting in progress. Time extension submitted to CDWP. Releases will be made after approval of time extension. |
No Image |
1159 (OG) |
90417-Widening & Carpeting of Booni Buzand Torkhow road (28 Km) District Chitral (PSDP Funded). |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1108.42 | 0 | 0 | 0 | 0 | 0 | 0 | 1108.42 | - |
- November - 2017 |
Original approval for Rs.279.922 m. PSDP share - 100%, GoKP share - 0%. The work started in 2010-11. Length 28 Km - earth work 17 km complted, structure work 60% in progress. Land clearnce 6 km not yet cleared by DC office. Work on 2/4 No. RCC bridge in progress. Work on 5 km cutting in progress. Time extension submitted to CDWP. Releases will be made after approval of time extension |
No Image |
1159 (OG) |
90417-Widening & Carpeting of Booni Buzand Torkhow road (28 Km) District Chitral (PSDP Funded). |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1108.42 | 301.11 | 10 | 10 | 3.55 | 0 | 301.11 | 797.31 | 28% |
27% October - 2017 |
Original approval for Rs.279.922 m. PSDP share - 100%, GoKP share - 0%. The work started in 2010-11. Length 28 Km - earth work 17 Km completed, structure work 60% in progress. Land clearnce 6 km not yet cleared by DC office . Work on 2/4 No. RCC bridge in progress. Work on 5 km cutting in progress. Time extension submitted to CDWP. Releases will be made after approval of time extension. |
No Image |
1159 (OG) |
90417-Widening & Carpeting of Booni Buzand Torkhow road (28 Km) District Chitral (PSDP Funded). |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1108.42 | 0 | 0 | 0 | 0 | 0 | 0 | 1108.42 | - |
- October - 2017 |
Original approval for Rs.279.922 m. PSDP share - 100%, GoKP share - 0%. The work started in 2010-11. Length 28 Km - earth work 17 km complted, structure work 60% in progress. Land clearnce 6 km not yet cleared by DC office. Work on 2/4 No. RCC bridge in progress. Work on 5 km cutting in progress. Time extension submitted to CDWP. Releases will be made after approval of time extension |
No Image |
1159 (OG) |
90417-Widening & Carpeting of Booni Buzand Torkhow road (28 Km) District Chitral (PSDP Funded). |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1108.42 | 312.274 | 10 | 0 | 0 | 0 | 312.274 | 786.146 | 29% |
28% June - 2018 |
Original approval for Rs.279.922 m. PSDP share - 100%, GoKP share - 0%. The work started in 2010-11. Length 28 Km - earth work 17 Km completed, structure work 60% in progress. Land clearnce 6 km not yet cleared by DC office. Work on 2/3 No. RCC bridge in progress. Work on 5 km cutting in progress. Time extension submitted to CDWP. Releases will be made after approval of time extension. |
No Image |
Booni Buzand Torkhow road (28 Km), Chitral
(Roads+
RCC Bridge Stan Gole
RCC Bridge WerkupGole
RCC Bridge Rayeen) | |||||||||||||||||||
1159 (OG) |
90417-Widening & Carpeting of Booni Buzand Torkhow road (28 Km) District Chitral (PSDP Funded). |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1108.42 | 0 | 100 | 81.712 | 81.712 | 81.712 | 81.712 | 1008.42 | 9% |
7% June - 2018 |
Original approval for Rs.279.922 m. PSDP share - 100%, GoKP share - 0%. The work started in 2010-11. Length 28 Km - earth work 17 Km completed, structure work 60% in progress. Land clearnce 6 km not yet cleared by DC office. Work on 2/3 No. RCC bridge in progress. Work on 5 km cutting in progress. Time extension submitted to CDWP. Releases will be made after approval of time extension. |
No Image |
Booni Buzand Torkhow road (28 Km), Chitral
(Roads +
RCC Bridge Stan Gole
RCC Bridge WerkupGole
RCC Bridge Rayeen) | |||||||||||||||||||
1159 (OG) |
90417-Widening & Carpeting of Booni Buzand Torkhow road (28 Km) District Chitral (PSDP Funded). |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1108.42 | 312.274 | 10 | 3 | 3 | 0 | 312.274 | 786.146 | 29% |
28% May - 2018 |
Original approval for Rs.279.922 m. PSDP share - 100%, GoKP share - 0%. The work started in 2010-11. Length 28 Km - earth work 17 Km completed, structure work 60% in progress. Land clearnce 6 km not yet cleared by DC office. Work on 2/3 No. RCC bridge in progress. Work on 5 km cutting in progress. Time extension submitted to CDWP. Releases will be made after approval of time extension.
Rs. 3 M offerd for surrender. |
No Image |
Booni Buzand Torkhow road (28 Km), Chitral
(Roads+
RCC Bridge Stan Gole
RCC Bridge WerkupGole
RCC Bridge Rayeen) | |||||||||||||||||||
1159 (OG) |
90417-Widening & Carpeting of Booni Buzand Torkhow road (28 Km) District Chitral (PSDP Funded). |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1108.42 | 0 | 100 | 100 | 100 | 80.627 | 80.627 | 1008.42 | 9% |
7% May - 2018 |
Original approval for Rs.279.922 m. PSDP sha.re - 100%, GoKP share - 0%. The work started in 2010-11. Length 28 Km - earth work 17 km completed, structure work 60% in progress. Land clearnce 6 km not yet cleared by DC office. Work on 2/3 No. RCC bridge in progress. Work on 5 km cutting in progress. Time extension submitted to CDWP. Releases will be made after approval of time extension. |
No Image |
Booni Buzand Torkhow road (28 Km), Chitral
(Roads +
RCC Bridge Stan Gole
RCC Bridge WerkupGole
RCC Bridge Rayeen) | |||||||||||||||||||
1159 (OG) |
90417-Widening & Carpeting of Booni Buzand Torkhow road (28 Km) District Chitral (PSDP Funded). |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1108.42 | 312.274 | 10 | 3 | 0.5 | 0 | 312.274 | 786.146 | 29% |
28% April - 2018 |
Original approval for Rs.279.922 m. PSDP share - 100%, GoKP share - 0%. The work started in 2010-11. Length 28 Km - earth work 17 Km completed, structure work 60% in progress. Land clearnce 6 km not yet cleared by DC office. Work on 2/3 No. RCC bridge in progress. Work on 5 km cutting in progress. Time extension submitted to CDWP. Releases will be made after approval of time extension. |
No Image |
Booni Buzand Torkhow road (28 Km), Chitral
(Roads+
RCC Bridge Stan Gole
RCC Bridge WerkupGole
RCC Bridge Rayeen) | |||||||||||||||||||
1159 (OG) |
90417-Widening & Carpeting of Booni Buzand Torkhow road (28 Km) District Chitral (PSDP Funded). |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1108.42 | 0 | 100 | 100 | 65 | 48.804 | 48.804 | 1008.42 | 9% |
4% April - 2018 |
Original approval for Rs.279.922 m. PSDP sha.re - 100%, GoKP share - 0%. The work started in 2010-11. Length 28 Km - earth work 17 km completed, structure work 60% in progress. Land clearnce 6 km not yet cleared by DC office. Work on 2/3 No. RCC bridge in progress. Work on 5 km cutting in progress. Time extension submitted to CDWP. Releases will be made after approval of time extension. |
No Image |
Booni Buzand Torkhow road (28 Km), Chitral
(Roads +
RCC Bridge Stan Gole
RCC Bridge WerkupGole
RCC Bridge Rayeen) | |||||||||||||||||||
1159 (OG) |
90417-Widening & Carpeting of Booni Buzand Torkhow road (28 Km) District Chitral (PSDP Funded). |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1108.42 | 312.274 | 10 | 3 | 0.5 | 0 | 312.274 | 786.146 | 29% |
28% March - 2018 |
Original approval for Rs.279.922 m. PSDP share - 100%, GoKP share - 0%. The work started in 2010-11. Length 28 Km - earth work 17 Km completed, structure work 60% in progress. Land clearnce 6 km not yet cleared by DC office. Work on 2/3 No. RCC bridge in progress. Work on 5 km cutting in progress. Time extension submitted to CDWP. Releases will be made after approval of time extension. |
No Image |
Booni Buzand Torkhow road (28 Km), Chitral
(Roads+
RCC Bridge Stan Gole
RCC Bridge WerkupGole
RCC Bridge Rayeen) | |||||||||||||||||||
1159 (OG) |
90417-Widening & Carpeting of Booni Buzand Torkhow road (28 Km) District Chitral (PSDP Funded). |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1108.42 | 0 | 100 | 100 | 0 | 0 | 0 | 1008.42 | 9% |
- March - 2018 |
Original approval for Rs.279.922 m. PSDP sha.re - 100%, GoKP share - 0%. The work started in 2010-11. Length 28 Km - earth work 17 km completed, structure work 60% in progress. Land clearnce 6 km not yet cleared by DC office. Work on 2/3 No. RCC bridge in progress. Work on 5 km cutting in progress. Time extension submitted to CDWP. Releases will be made after approval of time extension. |
No Image |
Booni Buzand Torkhow road (28 Km), Chitral
(Roads +
RCC Bridge Stan Gole
RCC Bridge WerkupGole
RCC Bridge Rayeen) | |||||||||||||||||||
1159 (OG) |
90417-Widening & Carpeting of Booni Buzand Torkhow road (28 Km) District Chitral (PSDP Funded). |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1108.42 | 312.274 | 10 | 3 | 0.5 | 0 | 312.274 | 786.146 | 29% |
28% February - 2018 |
Original approval for Rs.279.922 m. PSDP share - 100%, GoKP share - 0%. The work started in 2010-11. Length 28 Km - earth work 17 Km completed, structure work 60% in progress. Land clearnce 6 km not yet cleared by DC office. Work on 2/4 No. RCC bridge in progress. Work on 5 km cutting in progress. Time extension submitted to CDWP. Releases will be made after approval of time extension. |
ADP's Images |
Chitral | |||||||||||||||||||
1159 (OG) |
90417-Widening & Carpeting of Booni Buzand Torkhow road (28 Km) District Chitral (PSDP Funded). |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1108.42 | 0 | 0 | 0 | 0 | 0 | 0 | 1108.42 | - |
- February - 2018 |
Original approval for Rs.279.922 m. PSDP sha.re - 100%, GoKP share - 0%. The work started in 2010-11. Length 28 Km - earth work 17 km completed, structure work 60% in progress. Land clearnce 6 km not yet cleared by DC office. Work on 2/4 No. RCC bridge in progress. Work on 5 km cutting in progress. Time extension submitted to CDWP. Releases will be made after approval of time extension. |
ADP's Images |
Chitral | |||||||||||||||||||
1159 (OG) |
90417-Widening & Carpeting of Booni Buzand Torkhow road (28 Km) District Chitral (PSDP Funded). |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1108.42 | 301.11 | 10 | 3 | 0.5 | 0 | 301.11 | 797.31 | 28% |
27% January - 2018 |
Original approval for Rs.279.922 m. PSDP share - 100%, GoKP share - 0%. The work started in 2010-11. Length 28 Km - earth work 17 Km completed, structure work 60% in progress. Land clearnce 6 km not yet cleared by DC office. Work on 2/4 No. RCC bridge in progress. Work on 5 km cutting in progress. Time extension submitted to CDWP. Releases will be made after approval of time extension. |
No Image |
Chitral | |||||||||||||||||||
1159 (OG) |
90417-Widening & Carpeting of Booni Buzand Torkhow road (28 Km) District Chitral (PSDP Funded). |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1108.42 | 0 | 0 | 0 | 0 | 0 | 0 | 1108.42 | - |
- January - 2018 |
Original approval for Rs.279.922 m. PSDP sha.re - 100%, GoKP share - 0%. The work started in 2010-11. Length 28 Km - earth work 17 km completed, structure work 60% in progress. Land clearnce 6 km not yet cleared by DC office. Work on 2/4 No. RCC bridge in progress. Work on 5 km cutting in progress. Time extension submitted to CDWP. Releases will be made after approval of time extension. |
No Image |
Chitral | |||||||||||||||||||
1159 (OG) |
110457-Construction of Judicial Complex and Construction of Lawyers shed in Judicial Complex, Haripur |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 859 | 747.788 | 40 | 40 | 35 | 28.75 | 776.538 | 71.212 | 92% |
90% December - 2020 |
Main building, bar room, 90% completed. Balance work in progress |
No Image |
Judicial Complex Haripur | |||||||||||||||||||
1159 (OG) |
110457-Construction of Judicial Complex and Construction of Lawyers shed in Judicial Complex, Haripur |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 859 | 747.788 | 40 | 40 | 35 | 28.75 | 776.538 | 71.212 | 92% |
90% December - 2020 |
Main building, bar room, 90% completed. Balance work in progress |
No Image |
Judicial Complex Haripur | |||||||||||||||||||
1159 (OG) |
110457-Construction of Judicial Complex and Construction of Lawyers shed in Judicial Complex, Haripur |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 859 | 747.788 | 40 | 40 | 30.5 | 10 | 757.788 | 71.212 | 92% |
88% October - 2020 |
Main building, bar room, 90% completed. Balance work in progress |
No Image |
Judicial Complex Haripur | |||||||||||||||||||
1159 (OG) |
110457-Construction of Judicial Complex and Construction of Lawyers shed in Judicial Complex, Haripur |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 859 | 747.788 | 40 | 40 | 30.5 | 10 | 757.788 | 71.212 | 92% |
88% September - 2020 |
Main building, bar room, 90% completed. Balance work in progress |
No Image |
Judicial Complex Haripur | |||||||||||||||||||
1159 (OG) |
110457-Construction of Judicial Complex and Construction of Lawyers shed in Judicial Complex, Haripur |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 859 | 747.788 | 40 | 40 | 0 | 0 | 747.788 | 71.212 | 92% |
87% August - 2020 |
Main building, bar room, 90% completed. Balance wo |
No Image |
Judicial Complex Haripur | |||||||||||||||||||
1159 (OG) |
110457-Construction of Judicial Complex and Construction of Lawyers shed in Judicial Complex, Haripur |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 859 | 747.788 | 40 | 0 | 0 | 0 | 747.788 | 71.212 | 92% |
87% July - 2020 |
Main building, bar room, 90% completed. Balance wo |
No Image |
Judicial Complex Haripur | |||||||||||||||||||
1159 (OG) |
110457-Construction of Judicial Complex and Construction of Lawyers shed in Judicial Complex, Haripur |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 859 | 747.788 | 40 | 59.276 | 59.276 | 45.05 | 792.838 | 71.212 | 92% |
92% May - 2021 |
Main building, bar room, 90% completed. Balance work in progress. |
No Image |
Judicial Complex Haripur | |||||||||||||||||||
1159 (OG) |
110457-Construction of Judicial Complex and Construction of Lawyers shed in Judicial Complex, Haripur |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 859 | 747.788 | 40 | 59.276 | 59.276 | 45.05 | 792.838 | 71.212 | 92% |
92% April - 2021 |
Main building, bar room, 90% completed. Balance work in progress. |
No Image |
Judicial Complex Haripur | |||||||||||||||||||
1159 (OG) |
110457-Construction of Judicial Complex and Construction of Lawyers shed in Judicial Complex, Haripur |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 859 | 747.788 | 40 | 40 | 35 | 28.75 | 776.538 | 71.212 | 92% |
90% March - 2021 |
Main building, bar room, 90% completed. Balance work in progress |
No Image |
Judicial Complex Haripur | |||||||||||||||||||
1159 (OG) |
110457-Construction of Judicial Complex and Construction of Lawyers shed in Judicial Complex, Haripur |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 859 | 747.788 | 40 | 40 | 35 | 28.75 | 776.538 | 71.212 | 92% |
90% February - 2021 |
Main building, bar room, 90% completed. Balance work in progress |
No Image |
Judicial Complex Haripur | |||||||||||||||||||
1159 (OG) |
110457-Construction of Judicial Complex and Construction of Lawyers shed in Judicial Complex, Haripur |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 859 | 747.788 | 40 | 40 | 35 | 28.75 | 776.538 | 71.212 | 92% |
90% January - 2021 |
Main building, bar room, 90% completed. Balance work in progress |
No Image |
Judicial Complex Haripur | |||||||||||||||||||
Pages : 1 |