Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1156 (OG) |
151076-Construction of Nehag Dara Road (Phase-II) District Dir Upper. |
Dir Upper |
01-08-16 | - | - | 09-02-16 | - | 200 | 9.5 | 10 | 48.544 | 46.05 | 46 | 55.5 | 180.5 | 10% |
28% December - 2017 |
Length 13 Km - earth work 80% completed. |
No Image |
PK-93 | |||||||||||||||||||
1156 (OG) |
151076-Construction of Nehag Dara Road (Phase-II) District Dir Upper. |
Dir Upper |
01-08-16 | - | - | 09-02-16 | - | 200 | 9.5 | 10 | 10 | 3.55 | 3.5 | 13 | 180.5 | 10% |
7% September - 2017 |
Length 13 Km - earth work 80% completed. |
No Image |
PK-93 | |||||||||||||||||||
1156 (OG) |
151076-Construction of Nehag Dara Road (Phase-II) District Dir Upper. |
Dir Upper |
01-08-16 | - | - | 09-02-16 | - | 200 | 9.5 | 10 | 10 | 3.55 | 3.5 | 13 | 180.5 | 10% |
7% August - 2017 |
Length 13 Km - earth work 80% completed. |
No Image |
PK-93 | |||||||||||||||||||
1156 (OG) |
151076-Construction of Nehag Dara Road (Phase-II) District Dir Upper. |
Dir Upper |
01-08-16 | - | - | 09-02-16 | - | 200 | 9.5 | 10 | 10 | 3.55 | 0 | 9.5 | 180.5 | 10% |
5% July - 2017 |
Length 13 Km - earth work 80% completed. |
No Image |
PK-93 | |||||||||||||||||||
1156 (OG) |
151076-Construction of Nehag Dara Road (Phase-II) District Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 9.5 | 10 | 50 | 46.05 | 6 | 15.5 | 180.5 | 10% |
8% November - 2017 |
Length 13 Km - earth work 80% completed. |
No Image |
PK-93 | |||||||||||||||||||
1156 (OG) |
151076-Construction of Nehag Dara Road (Phase-II) District Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 9.5 | 10 | 10 | 6 | 6 | 15.5 | 180.5 | 10% |
8% October - 2017 |
Length 13 Km - earth work 80% completed. |
No Image |
PK-93 | |||||||||||||||||||
1156 (OG) |
151076-Construction of Nehag Dara Road (Phase-II) District Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 9.5 | 10 | 48.55 | 48.55 | 48.55 | 58.05 | 180.5 | 10% |
29% June - 2018 |
Length 13 Km - earth work completed. |
No Image |
PK-93, Dir Upper (13 Km) | |||||||||||||||||||
1156 (OG) |
151076-Construction of Nehag Dara Road (Phase-II) District Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 9.5 | 10 | 48.55 | 48.55 | 48.55 | 58.05 | 180.5 | 10% |
29% May - 2018 |
Length 13 Km - earth work completed. |
No Image |
PK-93, Dir Upper (13 Km) | |||||||||||||||||||
1156 (OG) |
151076-Construction of Nehag Dara Road (Phase-II) District Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 9.5 | 10 | 48.55 | 48.55 | 48.55 | 58.05 | 180.5 | 10% |
29% April - 2018 |
Length 13 Km - earth work completed. |
No Image |
PK-93, Dir Upper (13 Km) | |||||||||||||||||||
1156 (OG) |
151076-Construction of Nehag Dara Road (Phase-II) District Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 9.5 | 10 | 48.55 | 48.55 | 48.55 | 58.05 | 180.5 | 10% |
29% March - 2018 |
Length 13 Km - earth work completed. Work stopped due to extreme cold weather/snow fall. |
No Image |
PK-93, Dir Upper (13 Km) | |||||||||||||||||||
1156 (OG) |
151076-Construction of Nehag Dara Road (Phase-II) District Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 9.5 | 10 | 48.544 | 46.05 | 46 | 55.5 | 180.5 | 10% |
28% February - 2018 |
Length 13 Km - earth work completed. |
No Image |
PK-93 | |||||||||||||||||||
1156 (OG) |
151076-Construction of Nehag Dara Road (Phase-II) District Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 9.5 | 10 | 48.544 | 46.05 | 46 | 55.5 | 180.5 | 10% |
28% January - 2018 |
Length 13 Km - earth work completed. |
No Image |
PK-93 | |||||||||||||||||||
1156 (OG) |
100425-Construction of Judicial Complex, Mansehra. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 972.98 | 465.001 | 5 | 5 | 1.25 | 0 | 465.001 | 502.979 | 48% |
48% December - 2020 |
Presentation for conceptual design was presented. |
No Image |
Judicial Complex, Mansehra PK-31 (boundary wall/civil work/developmental work OHT/trial drilling/coversion into tube well) | |||||||||||||||||||
1156 (OG) |
100425-Construction of Judicial Complex, Mansehra. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 972.98 | 465.001 | 5 | 5 | 1.25 | 0 | 465.001 | 502.979 | 48% |
48% December - 2020 |
Presentation for conceptual design was presented. |
No Image |
Judicial Complex, Mansehra PK-31 (boundary wall/civil work/developmental work OHT/trial drilling/coversion into tube well) | |||||||||||||||||||
1156 (OG) |
100425-Construction of Judicial Complex, Mansehra. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 972.98 | 465.001 | 5 | 5 | 1.25 | 0 | 465.001 | 502.979 | 48% |
48% October - 2020 |
Presentation for conceptual design was presented. |
No Image |
Judicial Complex, Mansehra PK-31 (boundary wall/civil work/developmental work OHT/trial drilling/coversion into tube well) | |||||||||||||||||||
1156 (OG) |
100425-Construction of Judicial Complex, Mansehra. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 972.98 | 465.001 | 5 | 5 | 1.25 | 0 | 465.001 | 502.979 | 48% |
48% September - 2020 |
Presentation for conceptual design was presented. |
No Image |
Judicial Complex, Mansehra PK-31 (boundary wall/civil work/developmental work OHT/trial drilling/coversion into tube well) | |||||||||||||||||||
1156 (OG) |
100425-Construction of Judicial Complex, Mansehra. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 972.98 | 465.001 | 5 | 5 | 0 | 0 | 465.001 | 502.979 | 48% |
48% August - 2020 |
Presentation for conceptual design was presented. |
No Image |
Judicial Complex, Mansehra PK-31 (boundary wall/civil work/developmental work OHT/trial drilling/coversion into tube well) | |||||||||||||||||||
1156 (OG) |
100425-Construction of Judicial Complex, Mansehra. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 972.98 | 465.001 | 5 | 0 | 0 | 0 | 465.001 | 502.979 | 48% |
48% July - 2020 |
Presentation for conceptual design was presented b |
No Image |
Judicial Complex, Mansehra PK-31 (boundary wa | |||||||||||||||||||
1156 (OG) |
100425-Construction of Judicial Complex, Mansehra. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 972.98 | 434.001 | 5 | 0 | 0 | 0 | 434.001 | 533.979 | 45% |
45% May - 2021 |
Drawing / Desing prepared by Mindheart Consultant and District & Session Judge Mansehra asked for fixed the date for presentation by Mindheard Consultant. Land Payment made to DC / Land Acquisition Collector Mansehra.
Revised DCE submitted to P&D. |
No Image |
Judicial Complex, Mansehra PK-31 (boundary wall/civil work/developmental work OHT/trial drilling/coversion into tube well) | |||||||||||||||||||
1156 (OG) |
100425-Construction of Judicial Complex, Mansehra. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 972.98 | 434.001 | 5 | 0 | 0 | 0 | 434.001 | 533.979 | 45% |
45% April - 2021 |
Drawing / Desing prepared by Mindheart Consultant and District & Session Judge Mansehra asked for fixed the date for presentation by Mindheard Consultant. Land Payment made to DC / Land Acquisition Collector Mansehra.
Revised DCE submitted to P&D. |
No Image |
Judicial Complex, Mansehra PK-31 (boundary wall/civil work/developmental work OHT/trial drilling/coversion into tube well) | |||||||||||||||||||
1156 (OG) |
100425-Construction of Judicial Complex, Mansehra. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 972.98 | 434.001 | 5 | 3.25 | 3.25 | 0 | 434.001 | 533.979 | 45% |
45% March - 2021 |
Drawing / Desing prepared by Mindheart Consultant and District & Session Judge Mansehra asked for fixed the date for presentation by Mindheard Consultant. Land Payment made to DC / Land Acquisition Collector Mansehra. |
No Image |
Judicial Complex, Mansehra PK-31 (boundary wall/civil work/developmental work OHT/trial drilling/coversion into tube well) | |||||||||||||||||||
1156 (OG) |
100425-Construction of Judicial Complex, Mansehra. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 972.98 | 434.001 | 5 | 3.25 | 3.25 | 0 | 434.001 | 533.979 | 45% |
45% February - 2021 |
Drawing / Desing prepared by Mindheart Consultant and District & Session Judge Mansehra asked for fixed the date for presentation by Mindheard Consultant. Land Payment made to DC / Land Acquisition Collector Mansehra. |
No Image |
Judicial Complex, Mansehra PK-31 (boundary wall/civil work/developmental work OHT/trial drilling/coversion into tube well) | |||||||||||||||||||
1156 (OG) |
100425-Construction of Judicial Complex, Mansehra. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 972.98 | 434.001 | 5 | 1.25 | 1.25 | 0 | 434.001 | 533.979 | 45% |
45% January - 2021 |
Presentation for conceptual design was presented. |
No Image |
Judicial Complex, Mansehra PK-31 (boundary wall/civil work/developmental work OHT/trial drilling/coversion into tube well) | |||||||||||||||||||
Pages : 1 |