Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2018, February - 2018, March - 2018, April - 2018, May - 2018, June - 2018, July - 2017, August - 2017, September - 2017, October - 2017, November - 2017, December - 2017,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1156
(OG)
151076-Construction of Nehag Dara Road (Phase-II) District Dir Upper.
Dir Upper
01-08-16 - - 09-02-16 - 200 9.5 10 48.544 46.05 46 55.5 180.5 10% 28%
December - 2017
Length 13 Km - earth work 80% completed.
No Image
PK-93
1156
(OG)
151076-Construction of Nehag Dara Road (Phase-II) District Dir Upper.
Dir Upper
01-08-16 - - 09-02-16 - 200 9.5 10 10 3.55 3.5 13 180.5 10% 7%
September - 2017
Length 13 Km - earth work 80% completed.
No Image
PK-93
1156
(OG)
151076-Construction of Nehag Dara Road (Phase-II) District Dir Upper.
Dir Upper
01-08-16 - - 09-02-16 - 200 9.5 10 10 3.55 3.5 13 180.5 10% 7%
August - 2017
Length 13 Km - earth work 80% completed.
No Image
PK-93
1156
(OG)
151076-Construction of Nehag Dara Road (Phase-II) District Dir Upper.
Dir Upper
01-08-16 - - 09-02-16 - 200 9.5 10 10 3.55 0 9.5 180.5 10% 5%
July - 2017
Length 13 Km - earth work 80% completed.
No Image
PK-93
1156
(OG)
151076-Construction of Nehag Dara Road (Phase-II) District Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 200 9.5 10 50 46.05 6 15.5 180.5 10% 8%
November - 2017
Length 13 Km - earth work 80% completed.
No Image
PK-93
1156
(OG)
151076-Construction of Nehag Dara Road (Phase-II) District Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 200 9.5 10 10 6 6 15.5 180.5 10% 8%
October - 2017
Length 13 Km - earth work 80% completed.
No Image
PK-93
1156
(OG)
151076-Construction of Nehag Dara Road (Phase-II) District Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 200 9.5 10 48.55 48.55 48.55 58.05 180.5 10% 29%
June - 2018
Length 13 Km - earth work completed.
No Image
PK-93, Dir Upper (13 Km)
1156
(OG)
151076-Construction of Nehag Dara Road (Phase-II) District Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 200 9.5 10 48.55 48.55 48.55 58.05 180.5 10% 29%
May - 2018
Length 13 Km - earth work completed.
No Image
PK-93, Dir Upper (13 Km)
1156
(OG)
151076-Construction of Nehag Dara Road (Phase-II) District Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 200 9.5 10 48.55 48.55 48.55 58.05 180.5 10% 29%
April - 2018
Length 13 Km - earth work completed.
No Image
PK-93, Dir Upper (13 Km)
1156
(OG)
151076-Construction of Nehag Dara Road (Phase-II) District Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 200 9.5 10 48.55 48.55 48.55 58.05 180.5 10% 29%
March - 2018
Length 13 Km - earth work completed. Work stopped due to extreme cold weather/snow fall.
No Image
PK-93, Dir Upper (13 Km)
1156
(OG)
151076-Construction of Nehag Dara Road (Phase-II) District Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 200 9.5 10 48.544 46.05 46 55.5 180.5 10% 28%
February - 2018
Length 13 Km - earth work completed.
No Image
PK-93
1156
(OG)
151076-Construction of Nehag Dara Road (Phase-II) District Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 200 9.5 10 48.544 46.05 46 55.5 180.5 10% 28%
January - 2018
Length 13 Km - earth work completed.
No Image
PK-93
Pages : 1