Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2018, January - 2021, February - 2018, February - 2021, March - 2018, March - 2021, April - 2018, April - 2021, May - 2018, May - 2021, June - 2018, July - 2020, July - 2017, August - 2020, August - 2017, September - 2017, September - 2020, October - 2017, October - 2020, November - 2017, December - 2017, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1155
(OG)
120004-Construction of Judicial Complex, Chitral.
Chitral
30-11--1 30-11--1 - 30-11--1 - 930.934 311.95 50 0 0 0 311.95 568.984 39% 34%
July - 2020
Consultant AA Associates. Main building, High cou
No Image
Judicial Complex, Chitral.
1155
(OG)
120004-Construction of Judicial Complex, Chitral.
Chitral Lower
30-11--1 30-11--1 - 30-11--1 - 930.934 311.95 50 50 37.5 36.93 348.88 568.984 39% 37%
December - 2020
Consultant AA Associates. Main building, High court
No Image
Judicial Complex, Chitral.
1155
(OG)
120004-Construction of Judicial Complex, Chitral.
Chitral Lower
30-11--1 30-11--1 - 30-11--1 - 930.934 311.95 50 50 37.5 36.93 348.88 568.984 39% 37%
December - 2020
Consultant AA Associates. Main building, High court
No Image
Judicial Complex, Chitral.
1155
(OG)
120004-Construction of Judicial Complex, Chitral.
Chitral Lower
30-11--1 30-11--1 - 30-11--1 - 930.934 311.95 50 50 37.5 12.5 324.45 568.984 39% 35%
October - 2020
Consultant AA Associates. Main building, High court
No Image
Judicial Complex, Chitral.
1155
(OG)
120004-Construction of Judicial Complex, Chitral.
Chitral Lower
30-11--1 30-11--1 - 30-11--1 - 930.934 311.95 50 50 37.5 12.5 324.45 568.984 39% 35%
September - 2020
Consultant AA Associates. Main building, High court
No Image
Judicial Complex, Chitral.
1155
(OG)
120004-Construction of Judicial Complex, Chitral.
Chitral Lower
30-11--1 30-11--1 - 30-11--1 - 930.934 311.95 50 50 0 0 311.95 568.984 39% 34%
August - 2020
Consultant AA Associates. Main building, High cou
No Image
Judicial Complex, Chitral.
1155
(OG)
120004-Construction of Judicial Complex, Chitral.
Chitral Lower
30-11--1 30-11--1 - 30-11--1 - 930.934 271.45 50 130 130 129.999 401.449 609.484 35% 43%
May - 2021
Package I 33 % Package II 40 % Package III 41 % Pacakge IV 08 %
No Image
Judicial Complex, Chitral.
 
Scope of work:
  • Main Building
  • High Court Block Building
  • Judicial Lodge (03 Nos)
  • Staff Accommodation
  • Judicial Lock up building
  • Parking Basement
  • Lav: Block
  • Watch Tower 06 Nos
  • Guard Room
1155
(OG)
120004-Construction of Judicial Complex, Chitral.
Chitral Lower
30-11--1 30-11--1 - 30-11--1 - 930.934 271.45 50 130 130 129.999 401.449 609.484 35% 43%
April - 2021
Package I 33 % Package II 40 % Package III 41 % Pacakge IV 08 %
No Image
Judicial Complex, Chitral.
1155
(OG)
120004-Construction of Judicial Complex, Chitral.
Chitral Lower
30-11--1 30-11--1 - 30-11--1 - 930.934 271.45 50 117.5 117.5 91.856 363.306 609.484 35% 39%
March - 2021
Package I 33 % Package II 40 % Package III 41 % Pacakge IV 08 %
No Image
Judicial Complex, Chitral.
1155
(OG)
120004-Construction of Judicial Complex, Chitral.
Chitral Lower
30-11--1 30-11--1 - 30-11--1 - 930.934 271.45 50 117.5 117.5 90 361.45 609.484 35% 39%
February - 2021
Package I 33 % Package II 40 % Package III 41 % Pacakge IV 08 %
No Image
Judicial Complex, Chitral.
1155
(OG)
120004-Construction of Judicial Complex, Chitral.
Chitral Lower
30-11--1 30-11--1 - 30-11--1 - 930.934 311.95 50 130 130 78.735 390.685 568.984 39% 42%
January - 2021
Consultant AA Associates. Main building, High court
No Image
Judicial Complex, Chitral.
1155
(OG)
151071-Construction / Rehabilitation of Dir Mattaka Road, Dir Upper.
Dir Upper
01-03-16 30-06-18 - 16-10-15 - 50 9.75 40 40 30 30 39.75 0.25 100% 80%
December - 2017
Length 2.5 Km - PCC 1 Km completed. 70% structure work completed.
No Image
PK-91
1155
(OG)
151071-Construction / Rehabilitation of Dir Mattaka Road, Dir Upper.
Dir Upper
01-03-16 30-06-18 - 16-10-15 - 50 9.75 40 40 20 20 29.75 0.25 100% 60%
September - 2017
Length 5 Km - PCC 1 Km completed. 70% structure work completed.
No Image
PK-91
1155
(OG)
151071-Construction / Rehabilitation of Dir Mattaka Road, Dir Upper.
Dir Upper
01-03-16 30-06-18 - 16-10-15 - 50 9.75 40 40 20 8.347 18.097 0.25 100% 36%
August - 2017
Length 25 Km - 70% structure work completed.
No Image
PK-91
1155
(OG)
151071-Construction / Rehabilitation of Dir Mattaka Road, Dir Upper.
Dir Upper
01-03-16 30-06-18 - 16-10-15 - 50 9.75 40 40 14.2 0 9.75 0.25 100% 20%
July - 2017
Length 25 Km - 70% structure work completed.
No Image
PK-91
1155
(OG)
151071-Construction / Rehabilitation of Dir Mattaka Road, Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 50 9.75 40 40 30 30 39.75 0.25 100% 80%
November - 2017
Length 2.5 Km - PCC 1 Km completed. 70% structure work completed.
No Image
PK-91
1155
(OG)
151071-Construction / Rehabilitation of Dir Mattaka Road, Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 50 9.75 40 40 30 20 29.75 0.25 100% 60%
October - 2017
Length 2.5 Km - PCC 1 Km completed. 70% structure work completed.
No Image
PK-91
1155
(OG)
151071-Construction / Rehabilitation of Dir Mattaka Road, Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 50 9.75 40 34.96 34.96 34.96 44.71 0.25 100% 89%
June - 2018
Length 2.5 Km - PCC 1 Km completed.
No Image
PK-91, Dir Upper (PCC road 25 Km)
1155
(OG)
151071-Construction / Rehabilitation of Dir Mattaka Road, Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 50 9.75 40 40 40 30 39.75 0.25 100% 80%
May - 2018
Length 2.5 Km - PCC 1 Km completed.
No Image
PK-91, Dir Upper (PCC road 25 Km)
1155
(OG)
151071-Construction / Rehabilitation of Dir Mattaka Road, Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 50 9.75 40 40 40 30 39.75 0.25 100% 80%
April - 2018
Length 2.5 Km - PCC 1 Km completed.
No Image
PK-91, Dir Upper (PCC road 25 Km)
1155
(OG)
151071-Construction / Rehabilitation of Dir Mattaka Road, Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 50 9.75 40 40 40 30 39.75 0.25 100% 80%
March - 2018
Length 2.5 Km - PCC 1 Km completed. Work stopped due to extreme cold weather/snow fall.
No Image
PK-91, Dir Upper (PCC road 25 Km)
1155
(OG)
151071-Construction / Rehabilitation of Dir Mattaka Road, Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 50 9.75 40 40 30 30 39.75 0.25 100% 80%
February - 2018
Length 2.5 Km - PCC 1 Km completed.
No Image
PK-91
1155
(OG)
151071-Construction / Rehabilitation of Dir Mattaka Road, Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 50 9.75 40 40 30 30 39.75 0.25 100% 80%
January - 2018
Length 2.5 Km - PCC 1 Km completed.
No Image
PK-91
Pages : 1