Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1148 (OG) |
140903-Construction of PCC Road Samang Gulwadai Dara - 10 Km, District Dir Upper. |
Dir Upper |
01-07-15 | - | - | 15-09-17 | - | 300 | 26.75 | 20 | 17.1 | 12.1 | 12.1 | 38.85 | 253.25 | 16% |
13% December - 2017 |
Length 10 Km - earth, structure work in progress. |
No Image |
1148 (OG) |
140903-Construction of PCC Road Samang Gulwadai Dara - 10 Km, District Dir Upper. |
Dir Upper |
01-07-15 | - | - | - | - | 300 | 26.75 | 20 | 20 | 7.1 | 7.1 | 33.85 | 253.25 | 16% |
11% September - 2017 |
Length 10 Km - earth, structure work in progress. |
No Image |
1148 (OG) |
140903-Construction of PCC Road Samang Gulwadai Dara - 10 Km, District Dir Upper. |
Dir Upper |
01-07-15 | - | - | - | - | 166.565 | 26.75 | 20 | 20 | 7.1 | 7.1 | 33.85 | 119.815 | 28% |
20% August - 2017 |
Length 10 Km - earth, structure work in progress. Revised PC-I submitted to Chief Infra. |
No Image |
1148 (OG) |
140903-Construction of PCC Road Samang Gulwadai Dara - 10 Km, District Dir Upper. |
Dir Upper |
01-07-15 | - | - | - | - | 166.565 | 26.75 | 20 | 20 | 7.1 | 0 | 26.75 | 119.815 | 28% |
16% July - 2017 |
Length 10 Km - earth, structure work in progress .Revised PC-I submitted to Chief Infra. |
No Image |
1148 (OG) |
140903-Construction of PCC Road Samang Gulwadai Dara - 10 Km, District Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 300 | 26.75 | 20 | 17.1 | 12.1 | 12.1 | 38.85 | 253.25 | 16% |
13% November - 2017 |
Length 10 Km - earth, structure work in progress. |
No Image |
1148 (OG) |
140903-Construction of PCC Road Samang Gulwadai Dara - 10 Km, District Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 300 | 26.75 | 20 | 20 | 12.1 | 7.1 | 33.85 | 253.25 | 16% |
11% October - 2017 |
Length 10 Km - earth, structure work in progress. |
No Image |
1148 (OG) |
140903-Construction of PCC Road Samang Gulwadai Dara - 10 Km, District Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 300 | 26.75 | 20 | 24.058 | 24.058 | 24.058 | 50.808 | 253.25 | 16% |
17% June - 2018 |
Length 10 Km - cutting of 10 Km completed. |
No Image |
Dir Upper (Km-1 to 10) | |||||||||||||||||||
1148 (OG) |
140903-Construction of PCC Road Samang Gulwadai Dara - 10 Km, District Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 300 | 26.75 | 20 | 24.058 | 24.058 | 24.058 | 50.808 | 253.25 | 16% |
17% May - 2018 |
Length 10 Km - cutting of 10 Km completed. |
No Image |
Dir Upper (Km-1 to 10) | |||||||||||||||||||
1148 (OG) |
140903-Construction of PCC Road Samang Gulwadai Dara - 10 Km, District Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 300 | 26.75 | 20 | 24.058 | 24.058 | 24.053 | 50.803 | 253.25 | 16% |
17% April - 2018 |
Length 10 Km - cutting of 10 Km completed. |
No Image |
Dir Upper (Km-1 to 10) | |||||||||||||||||||
1148 (OG) |
140903-Construction of PCC Road Samang Gulwadai Dara - 10 Km, District Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 300 | 26.75 | 20 | 24.058 | 24.058 | 21.368 | 48.118 | 253.25 | 16% |
16% March - 2018 |
Length 10 Km - cutting of 10 Km completed. |
No Image |
Dir Upper (Km-1 to 10) | |||||||||||||||||||
1148 (OG) |
140903-Construction of PCC Road Samang Gulwadai Dara - 10 Km, District Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 300 | 26.75 | 20 | 21.368 | 21.368 | 12.1 | 38.85 | 253.25 | 16% |
13% February - 2018 |
Length 10 Km - cutting of 10 Km completed. |
No Image |
1148 (OG) |
140903-Construction of PCC Road Samang Gulwadai Dara - 10 Km, District Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 300 | 26.75 | 20 | 21.368 | 21.368 | 12.1 | 38.85 | 253.25 | 16% |
13% January - 2018 |
Length 10 Km - cutting of 10 Km completed. |
No Image |
1148 (OG) |
130445-Construction of Joint Judicial Complex at Karak and Takhte- Nasrati. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 583.853 | 272.368 | 40 | 40 | 16 | 15.945 | 288.313 | 271.485 | 54% |
49% December - 2020 |
Main building - finishing in progress. B/Wall 80% complted.
Liability : 15 M |
No Image |
Karak | |||||||||||||||||||
1148 (OG) |
130445-Construction of Joint Judicial Complex at Karak and Takhte- Nasrati. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 583.853 | 272.368 | 40 | 40 | 16 | 15.945 | 288.313 | 271.485 | 54% |
49% December - 2020 |
Main building - finishing in progress. B/Wall 80% complted.
Liability : 15 M |
No Image |
Karak | |||||||||||||||||||
1148 (OG) |
130445-Construction of Joint Judicial Complex at Karak and Takhte- Nasrati. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 583.853 | 272.368 | 40 | 40 | 16 | 6.303 | 278.671 | 271.485 | 54% |
48% October - 2020 |
Main building - finishing in progress. B/Wall 80% complted.
Liability : 15 M |
No Image |
Karak | |||||||||||||||||||
1148 (OG) |
130445-Construction of Joint Judicial Complex at Karak and Takhte- Nasrati. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 583.853 | 272.368 | 40 | 40 | 16 | 6.3 | 278.668 | 271.485 | 54% |
48% September - 2020 |
Main building - finishing in progress. B/Wall 80% complted.
Liability : 15 M |
No Image |
Karak | |||||||||||||||||||
1148 (OG) |
130445-Construction of Joint Judicial Complex at Karak and Takhte- Nasrati. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 583.853 | 272.368 | 40 | 40 | 0 | 0 | 272.368 | 271.485 | 54% |
47% August - 2020 |
Main building - finishing in progress. B/Wall 80% complted. |
No Image |
Karak | |||||||||||||||||||
1148 (OG) |
130445-Construction of Joint Judicial Complex at Karak and Takhte- Nasrati. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 583.853 | 272.368 | 40 | 0 | 0 | 0 | 272.368 | 271.485 | 54% |
47% July - 2020 |
Main building - Plastering in progress. |
No Image |
Karak | |||||||||||||||||||
1148 (OG) |
130445-Construction of Joint Judicial Complex at Karak and Takhte- Nasrati. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 583.853 | 272.368 | 40 | 40 | 40 | 39.999 | 312.367 | 271.485 | 54% |
54% April - 2021 |
Main building - finishing in progress. B/Wall 80% complted.
Liability : 15 M |
No Image |
Karak | |||||||||||||||||||
1148 (OG) |
130445-Construction of Joint Judicial Complex at Karak and Takhte- Nasrati. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 583.853 | 272.368 | 40 | 40 | 40 | 28.365 | 300.733 | 271.485 | 54% |
52% March - 2021 |
Main building - finishing in progress. B/Wall 80% complted.
Liability : 15 M |
No Image |
Karak | |||||||||||||||||||
1148 (OG) |
130445-Construction of Joint Judicial Complex at Karak and Takhte- Nasrati. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 583.853 | 272.368 | 40 | 40 | 40 | 28.365 | 300.733 | 271.485 | 54% |
52% February - 2021 |
Main building - finishing in progress. B/Wall 80% complted.
Liability : 15 M |
No Image |
Karak | |||||||||||||||||||
1148 (OG) |
130445-Construction of Joint Judicial Complex at Karak and Takhte- Nasrati. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 583.853 | 272.368 | 40 | 40 | 16 | 15.945 | 288.313 | 271.485 | 54% |
49% January - 2021 |
Main building - finishing in progress. B/Wall 80% complted.
Liability : 15 M |
No Image |
Karak | |||||||||||||||||||
1148 (OG) |
130445-Construction of Joint Judicial Complex at Karak and Takhte- Nasrati. |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 583.853 | 272.368 | 40 | 40 | 40 | 39.999 | 312.367 | 271.485 | 54% |
54% May - 2021 |
B/Wall 40% Completed, M/Blud: Jionery in progress, Judicial Lockup Finihsing, R/Wall 80%, Public Facilitation building in progress |
No Image |
Karak | |||||||||||||||||||
Pages : 1 |