Progressive Review for the month(s) of : January - 2018, January - 2021, February - 2018, February - 2021, March - 2018, March - 2021, April - 2018, April - 2021, May - 2018, May - 2021, June - 2018, July - 2020, July - 2017, August - 2020, August - 2017, September - 2017, September - 2020, October - 2017, October - 2020, November - 2017, December - 2017, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1148
(OG)
140903-Construction of PCC Road Samang Gulwadai Dara - 10 Km, District Dir Upper.
Dir Upper
01-07-15 - - 15-09-17 - 300 26.75 20 17.1 12.1 12.1 38.85 253.25 16% 13%
December - 2017
Length 10 Km - earth, structure work in progress.
No Image
1148
(OG)
140903-Construction of PCC Road Samang Gulwadai Dara - 10 Km, District Dir Upper.
Dir Upper
01-07-15 - - - - 300 26.75 20 20 7.1 7.1 33.85 253.25 16% 11%
September - 2017
Length 10 Km - earth, structure work in progress.
No Image
1148
(OG)
140903-Construction of PCC Road Samang Gulwadai Dara - 10 Km, District Dir Upper.
Dir Upper
01-07-15 - - - - 166.565 26.75 20 20 7.1 7.1 33.85 119.815 28% 20%
August - 2017
Length 10 Km - earth, structure work in progress. Revised PC-I submitted to Chief Infra.
No Image
1148
(OG)
140903-Construction of PCC Road Samang Gulwadai Dara - 10 Km, District Dir Upper.
Dir Upper
01-07-15 - - - - 166.565 26.75 20 20 7.1 0 26.75 119.815 28% 16%
July - 2017
Length 10 Km - earth, structure work in progress .Revised PC-I submitted to Chief Infra.
No Image
1148
(OG)
140903-Construction of PCC Road Samang Gulwadai Dara - 10 Km, District Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 300 26.75 20 17.1 12.1 12.1 38.85 253.25 16% 13%
November - 2017
Length 10 Km - earth, structure work in progress.
No Image
1148
(OG)
140903-Construction of PCC Road Samang Gulwadai Dara - 10 Km, District Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 300 26.75 20 20 12.1 7.1 33.85 253.25 16% 11%
October - 2017
Length 10 Km - earth, structure work in progress.
No Image
1148
(OG)
140903-Construction of PCC Road Samang Gulwadai Dara - 10 Km, District Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 300 26.75 20 24.058 24.058 24.058 50.808 253.25 16% 17%
June - 2018
Length 10 Km - cutting of 10 Km completed.
No Image
Dir Upper (Km-1 to 10)
1148
(OG)
140903-Construction of PCC Road Samang Gulwadai Dara - 10 Km, District Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 300 26.75 20 24.058 24.058 24.058 50.808 253.25 16% 17%
May - 2018
Length 10 Km - cutting of 10 Km completed.
No Image
Dir Upper (Km-1 to 10)
1148
(OG)
140903-Construction of PCC Road Samang Gulwadai Dara - 10 Km, District Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 300 26.75 20 24.058 24.058 24.053 50.803 253.25 16% 17%
April - 2018
Length 10 Km - cutting of 10 Km completed.
No Image
Dir Upper (Km-1 to 10)
1148
(OG)
140903-Construction of PCC Road Samang Gulwadai Dara - 10 Km, District Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 300 26.75 20 24.058 24.058 21.368 48.118 253.25 16% 16%
March - 2018
Length 10 Km - cutting of 10 Km completed.
No Image
Dir Upper (Km-1 to 10)
1148
(OG)
140903-Construction of PCC Road Samang Gulwadai Dara - 10 Km, District Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 300 26.75 20 21.368 21.368 12.1 38.85 253.25 16% 13%
February - 2018
Length 10 Km - cutting of 10 Km completed.
No Image
1148
(OG)
140903-Construction of PCC Road Samang Gulwadai Dara - 10 Km, District Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 300 26.75 20 21.368 21.368 12.1 38.85 253.25 16% 13%
January - 2018
Length 10 Km - cutting of 10 Km completed.
No Image
1148
(OG)
130445-Construction of Joint Judicial Complex at Karak and Takhte- Nasrati.
Karak
30-11--1 30-11--1 - 30-11--1 - 583.853 272.368 40 40 16 15.945 288.313 271.485 54% 49%
December - 2020
Main building - finishing in progress. B/Wall 80% complted. Liability : 15 M
No Image
Karak
1148
(OG)
130445-Construction of Joint Judicial Complex at Karak and Takhte- Nasrati.
Karak
30-11--1 30-11--1 - 30-11--1 - 583.853 272.368 40 40 16 15.945 288.313 271.485 54% 49%
December - 2020
Main building - finishing in progress. B/Wall 80% complted. Liability : 15 M
No Image
Karak
1148
(OG)
130445-Construction of Joint Judicial Complex at Karak and Takhte- Nasrati.
Karak
30-11--1 30-11--1 - 30-11--1 - 583.853 272.368 40 40 16 6.303 278.671 271.485 54% 48%
October - 2020
Main building - finishing in progress. B/Wall 80% complted. Liability : 15 M
No Image
Karak
1148
(OG)
130445-Construction of Joint Judicial Complex at Karak and Takhte- Nasrati.
Karak
30-11--1 30-11--1 - 30-11--1 - 583.853 272.368 40 40 16 6.3 278.668 271.485 54% 48%
September - 2020
Main building - finishing in progress. B/Wall 80% complted. Liability : 15 M
No Image
Karak
1148
(OG)
130445-Construction of Joint Judicial Complex at Karak and Takhte- Nasrati.
Karak
30-11--1 30-11--1 - 30-11--1 - 583.853 272.368 40 40 0 0 272.368 271.485 54% 47%
August - 2020
Main building - finishing in progress. B/Wall 80% complted.
No Image
Karak
1148
(OG)
130445-Construction of Joint Judicial Complex at Karak and Takhte- Nasrati.
Karak
30-11--1 30-11--1 - 30-11--1 - 583.853 272.368 40 0 0 0 272.368 271.485 54% 47%
July - 2020
Main building - Plastering in progress.
No Image
Karak
1148
(OG)
130445-Construction of Joint Judicial Complex at Karak and Takhte- Nasrati.
Karak
30-11--1 30-11--1 - 30-11--1 - 583.853 272.368 40 40 40 39.999 312.367 271.485 54% 54%
April - 2021
Main building - finishing in progress. B/Wall 80% complted. Liability : 15 M
No Image
Karak
1148
(OG)
130445-Construction of Joint Judicial Complex at Karak and Takhte- Nasrati.
Karak
30-11--1 30-11--1 - 30-11--1 - 583.853 272.368 40 40 40 28.365 300.733 271.485 54% 52%
March - 2021
Main building - finishing in progress. B/Wall 80% complted. Liability : 15 M
No Image
Karak
1148
(OG)
130445-Construction of Joint Judicial Complex at Karak and Takhte- Nasrati.
Karak
30-11--1 30-11--1 - 30-11--1 - 583.853 272.368 40 40 40 28.365 300.733 271.485 54% 52%
February - 2021
Main building - finishing in progress. B/Wall 80% complted. Liability : 15 M
No Image
Karak
1148
(OG)
130445-Construction of Joint Judicial Complex at Karak and Takhte- Nasrati.
Karak
30-11--1 30-11--1 - 30-11--1 - 583.853 272.368 40 40 16 15.945 288.313 271.485 54% 49%
January - 2021
Main building - finishing in progress. B/Wall 80% complted. Liability : 15 M
No Image
Karak
1148
(OG)
130445-Construction of Joint Judicial Complex at Karak and Takhte- Nasrati.
Kohat
30-11--1 30-11--1 - 30-11--1 - 583.853 272.368 40 40 40 39.999 312.367 271.485 54% 54%
May - 2021
B/Wall 40% Completed, M/Blud: Jionery in progress, Judicial Lockup Finihsing, R/Wall 80%, Public Facilitation building in progress
No Image
Karak