Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2021, January - 2018, February - 2021, February - 2018, March - 2021, March - 2018, April - 2021, April - 2018, May - 2021, May - 2018, June - 2018, July - 2017, July - 2020, August - 2017, August - 2020, September - 2017, September - 2020, October - 2017, October - 2020, November - 2017, December - 2020, December - 2017,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1146
(OG)
120003-Construction of Peshawar High Court, Bannu Bench.
Bannu
30-11--1 30-11--1 - 30-11--1 - 950 828.799 5 5 2.5 2.5 831.299 116.201 88% 88%
December - 2020
Main building, residences - finishing in progress.
No Image
1) Additional works
2) VRF (Variable Regregitor Flow)
1146
(OG)
120003-Construction of Peshawar High Court, Bannu Bench.
Bannu
30-11--1 30-11--1 - 30-11--1 - 950 828.799 5 5 2.5 2.5 831.299 116.201 88% 88%
December - 2020
Main building, residences - finishing in progress.
No Image
1) Additional works
2) VRF (Variable Regregitor Flow)
1146
(OG)
120003-Construction of Peshawar High Court, Bannu Bench.
Bannu
30-11--1 30-11--1 - 30-11--1 - 950 828.799 5 5 7.45 1.25 830.049 116.201 88% 87%
October - 2020
Main building, residences - finishing in progress.
No Image
1) Additional works
2) VRF (Variable Regregitor Flow)
1146
(OG)
120003-Construction of Peshawar High Court, Bannu Bench.
Bannu
30-11--1 30-11--1 - 30-11--1 - 950 828.799 5 5 7.45 1.25 830.049 116.201 88% 87%
September - 2020
Main building, residences - finishing in progress.
No Image
1) Additional works
2) VRF (Variable Regregitor Flow)
1146
(OG)
120003-Construction of Peshawar High Court, Bannu Bench.
Bannu
30-11--1 30-11--1 - 30-11--1 - 950 828.799 5 5 1.25 1.25 830.049 116.201 88% 87%
August - 2020
Main building, residences - finishing in progress.
No Image
1) Additional works
2) VRF (Variable Regregitor Flow)
1146
(OG)
120003-Construction of Peshawar High Court, Bannu Bench.
Bannu
30-11--1 30-11--1 - 30-11--1 - 950 828.799 5 0 0 0 828.799 116.201 88% 87%
July - 2020
Main building, residences - finishing in progress.
No Image
1) Additional works
2) VRF (Var
1146
(OG)
120003-Construction of Peshawar High Court, Bannu Bench.
Bannu
30-11--1 30-11--1 - 30-11--1 - 950 792.594 5 113.701 113.701 57.491 850.085 152.406 84% 89%
May - 2021
01- Unit Phase-I Main Buld:, G/F, 1st Floor, 2nd, Floor Momty & Electric lift 02 Nos completed Phase-II Residences 03 Nos, Judges Lodges, B/Wall, Foot Path, Int: roads, Tube well, O.H.W Tank & Dev: work completed, Ext: Sui Gas work in progrss
No Image
1 Main Court
2 Residental Buliding
3 100 KW Grid Tried Solar PV System
4 Installation of Spilt AC Units
1146
(OG)
120003-Construction of Peshawar High Court, Bannu Bench.
Bannu
30-11--1 30-11--1 - 30-11--1 - 950 828.799 5 113.701 113.701 47.6 876.399 116.201 88% 92%
April - 2021
Main building, residences - finishing in progress.
No Image
1 Main Court
2 Residental Buliding
3 100 KW Grid Tried Solar PV System
4 Installation of Spilt AC Units
1146
(OG)
120003-Construction of Peshawar High Court, Bannu Bench.
Bannu
30-11--1 30-11--1 - 30-11--1 - 950 828.799 5 113.701 113.701 46.547 875.346 116.201 88% 92%
March - 2021
Main building, residences - finishing in progress.
No Image
1 Main Court
2 Residental Buliding
3 100 KW Grid Tried Solar PV System
4 Installation of Spilt AC Units
1146
(OG)
120003-Construction of Peshawar High Court, Bannu Bench.
Bannu
30-11--1 30-11--1 - 30-11--1 - 950 828.799 5 113.701 113.701 39.358 868.157 116.201 88% 91%
February - 2021
Main building, residences - finishing in progress.
No Image
1 Main Court
2 Residental Buliding
3 100 KW Grid Tried Solar PV System
4 Installation of Spilt AC Units
1146
(OG)
120003-Construction of Peshawar High Court, Bannu Bench.
Bannu
30-11--1 30-11--1 - 30-11--1 - 950 828.799 5 5 2.5 2.5 831.299 116.201 88% 88%
January - 2021
Main building, residences - finishing in progress.
No Image
1) Additional works
2) VRF (Variable Regregitor Flow)
1146
(OG)
140650-F/S, Design, Improvement & BT of Shingara Darra Road (8 Km) Dir Upper.
Dir Upper
01-07-15 30-06-18 - 22-01-15 - 120 51.348 68.152 68.152 53.114 43.206 94.554 0.5 100% 79%
December - 2017
Length 8 Km - 6 Km BT completed.
No Image
1146
(OG)
140650-F/S, Design, Improvement & BT of Shingara Darra Road (8 Km) Dir Upper.
Dir Upper
01-07-15 30-06-18 - 22-01-15 - 120 51.348 68.152 68.152 34.076 34.076 85.424 0.5 100% 71%
September - 2017
Length 8 Km - earth work, structure work in progress.
No Image
1146
(OG)
140650-F/S, Design, Improvement & BT of Shingara Darra Road (8 Km) Dir Upper.
Dir Upper
01-07-15 30-06-18 - 22-01-15 - 120 51.348 68.152 68.152 34.076 34.076 85.424 0.5 100% 71%
August - 2017
Length 8 Km - earth work, structure work in progress.
No Image
1146
(OG)
140650-F/S, Design, Improvement & BT of Shingara Darra Road (8 Km) Dir Upper.
Dir Upper
01-07-15 30-06-18 - 22-01-15 - 120 51.348 68.152 68.152 24.194 0 51.348 0.5 100% 43%
July - 2017
Length 8 Km - earth work, structure work in progress.
No Image
1146
(OG)
140650-F/S, Design, Improvement & BT of Shingara Darra Road (8 Km) Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 120 51.348 68.152 68.152 53.114 43.206 94.554 0.5 100% 79%
November - 2017
Length 8 Km - 6 Km BT completed.
No Image
1146
(OG)
140650-F/S, Design, Improvement & BT of Shingara Darra Road (8 Km) Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 120 51.348 68.152 68.152 51.114 34.076 85.424 0.5 100% 71%
October - 2017
Length 8 Km - 6 Km BT completed.
No Image
1146
(OG)
140650-F/S, Design, Improvement & BT of Shingara Darra Road (8 Km) Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 120 51.348 68.152 43.206 43.206 43.206 94.554 0.5 100% 79%
June - 2018
Length 8 Km - 6 Km BT completed.
No Image
 Dir Upper (Km-1 to 8)
1146
(OG)
140650-F/S, Design, Improvement & BT of Shingara Darra Road (8 Km) Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 120 51.348 68.152 68.152 68.152 43.206 94.554 0.5 100% 79%
May - 2018
Length 8 Km - 6 Km BT completed.
No Image
 Dir Upper (Km-1 to 8)
1146
(OG)
140650-F/S, Design, Improvement & BT of Shingara Darra Road (8 Km) Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 120 51.348 68.152 68.152 68.144 43.206 94.554 0.5 100% 79%
April - 2018
Length 8 Km - 6 Km BT completed.
No Image
 Dir Upper (Km-1 to 8)
1146
(OG)
140650-F/S, Design, Improvement & BT of Shingara Darra Road (8 Km) Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 120 51.348 68.152 68.152 68.144 43.206 94.554 0.5 100% 79%
March - 2018
Length 8 Km - 6 Km BT completed.
No Image
 Dir Upper (Km-1 to 8)
1146
(OG)
140650-F/S, Design, Improvement & BT of Shingara Darra Road (8 Km) Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 120 51.348 68.152 68.152 53.114 43.206 94.554 0.5 100% 79%
February - 2018
Length 8 Km - 6 Km BT completed.
ADP's Images
1146
(OG)
140650-F/S, Design, Improvement & BT of Shingara Darra Road (8 Km) Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 120 51.348 68.152 68.152 53.114 43.206 94.554 0.5 100% 79%
January - 2018
Length 8 Km - 6 Km BT completed.
No Image
Pages : 1