Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1136 (OG) |
150837-Construction & Black Topping of Gudhar Takurro road UC Munda and Danjarri to Ijjara, Nawey Kallay, Bota & Qaziabad Tatar road Dir Lower. |
Dir Lower |
- | - | - | 02-11-15 | - | 199.796 | 51.41 | 20 | 19.1 | 14.1 | 14.1 | 65.51 | 128.386 | 36% |
33% December - 2017 |
Length 12 Km - work in progress on all 6 units. |
No Image |
1136 (OG) |
150837-Construction & Black Topping of Gudhar Takurro road UC Munda and Danjarri to Ijjara, Nawey Kallay, Bota & Qaziabad Tatar road Dir Lower. |
Dir Lower |
- | - | - | 02-11-15 | - | 199.796 | 51.41 | 20 | 20 | 7.1 | 7.1 | 58.51 | 128.386 | 36% |
29% September - 2017 |
Length 12 Km - work in progress on all 6 units. |
No Image |
1136 (OG) |
150837-Construction & Black Topping of Gudhar Takurro road UC Munda and Danjarri to Ijjara, Nawey Kallay, Bota & Qaziabad Tatar road Dir Lower. |
Dir Lower |
- | - | - | 02-11-15 | - | 199.796 | 51.41 | 20 | 20 | 7.1 | 7.1 | 58.51 | 128.386 | 36% |
29% August - 2017 |
Length 12 Km - work in progress on all 6 units. |
No Image |
1136 (OG) |
150837-Construction & Black Topping of Gudhar Takurro road UC Munda and Danjarri to Ijjara, Nawey Kallay, Bota & Qaziabad Tatar road Dir Lower. |
Dir Lower |
- | - | - | 02-11-15 | - | 199.796 | 51.41 | 20 | 20 | 7.1 | 0 | 51.41 | 128.386 | 36% |
26% July - 2017 |
Length 12 Km - work in progress on all 6 units. |
No Image |
1136 (OG) |
150837-Construction & Black Topping of Gudhar Takurro road UC Munda and Danjarri to Ijjara, Nawey Kallay, Bota & Qaziabad Tatar road Dir Lower. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 199.796 | 51.41 | 20 | 17.1 | 12.1 | 12.1 | 63.51 | 128.386 | 36% |
32% November - 2017 |
Length 12 Km - work in progress on all 6 units. |
No Image |
1136 (OG) |
150837-Construction & Black Topping of Gudhar Takurro road UC Munda and Danjarri to Ijjara, Nawey Kallay, Bota & Qaziabad Tatar road Dir Lower. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 199.796 | 51.41 | 20 | 20 | 12.1 | 12.1 | 63.51 | 128.386 | 36% |
32% October - 2017 |
Length 12 Km - work in progress on all 6 units. |
No Image |
1136 (OG) |
150837-Construction & Black Topping of Gudhar Takurro road UC Munda and Danjarri to Ijjara, Nawey Kallay, Bota & Qaziabad Tatar road Dir Lower. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 199.796 | 51.41 | 20 | 26.058 | 26.058 | 26.058 | 77.468 | 128.386 | 36% |
39% June - 2018 |
Length 12 Km - work in progress on all 6 units. |
No Image |
1) Gudar road
2) Takurro road
3) Denjarai to Ijara road
4) Naway Kalay road
5) Bota road
6) Qazi Abad Tatar road | |||||||||||||||||||
1136 (OG) |
150837-Construction & Black Topping of Gudhar Takurro road UC Munda and Danjarri to Ijjara, Nawey Kallay, Bota & Qaziabad Tatar road Dir Lower. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 199.796 | 51.41 | 20 | 26.058 | 26.058 | 26.058 | 77.468 | 128.386 | 36% |
39% May - 2018 |
Length 12 Km - work in progress on all 6 units. |
No Image |
1) Gudar road
2) Takurro road
3) Denjarai to Ijara road
4) Naway Kalay road
5) Bota road
6) Qazi Abad Tatar road | |||||||||||||||||||
1136 (OG) |
150837-Construction & Black Topping of Gudhar Takurro road UC Munda and Danjarri to Ijjara, Nawey Kallay, Bota & Qaziabad Tatar road Dir Lower. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 199.796 | 51.41 | 20 | 26.058 | 26.058 | 26.058 | 77.468 | 128.386 | 36% |
39% April - 2018 |
Length 12 Km - work in progress on all 6 units. |
No Image |
1) Gudar road
2) Takurro road
3) Denjarai to Ijara road
4) Naway Kalay road
5) Bota road
6) Qazi Abad Tatar road | |||||||||||||||||||
1136 (OG) |
150837-Construction & Black Topping of Gudhar Takurro road UC Munda and Danjarri to Ijjara, Nawey Kallay, Bota & Qaziabad Tatar road Dir Lower. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 199.796 | 51.41 | 20 | 26.052 | 26.052 | 23.368 | 74.778 | 128.386 | 36% |
37% March - 2018 |
Length 12 Km - work in progress on all 6 units. |
No Image |
1) Gudar road
2) Takurro road
3) Denjarai to Ijara road
4) Naway Kalay road
5) Bota road
6) Qazi Abad Tatar road | |||||||||||||||||||
1136 (OG) |
150837-Construction & Black Topping of Gudhar Takurro road UC Munda and Danjarri to Ijjara, Nawey Kallay, Bota & Qaziabad Tatar road Dir Lower. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 199.796 | 51.41 | 20 | 23.368 | 23.368 | 23.368 | 74.778 | 128.386 | 36% |
37% February - 2018 |
Length 12 Km - work in progress on all 6 units. |
No Image |
1136 (OG) |
150837-Construction & Black Topping of Gudhar Takurro road UC Munda and Danjarri to Ijjara, Nawey Kallay, Bota & Qaziabad Tatar road Dir Lower. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 199.796 | 51.41 | 20 | 23.368 | 23.368 | 23.368 | 74.778 | 128.386 | 36% |
37% January - 2018 |
Length 12 Km - work in progress on all 6 units. |
No Image |
1136 (New) |
200043-Establishment of Communication and Social Media Cell For Publicity of AIP Projects & Launching of Mass Awareness Campaigns in Newly Merged Areas (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 950 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
No Image | |
1136 (New) |
200043-Establishment of Communication and Social Media Cell For Publicity of AIP Projects & Launching of Mass Awareness Campaigns in Newly Merged Areas (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 950 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
No Image | |
1136 (New) |
200043-Establishment of Communication and Social Media Cell For Publicity of AIP Projects & Launching of Mass Awareness Campaigns in Newly Merged Areas (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 950 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- October - 2020 |
No Image | |
1136 (New) |
200043-Establishment of Communication and Social Media Cell For Publicity of AIP Projects & Launching of Mass Awareness Campaigns in Newly Merged Areas (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 950 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- September - 2020 |
No Image | |
1136 (New) |
200043-Establishment of Communication and Social Media Cell For Publicity of AIP Projects & Launching of Mass Awareness Campaigns in Newly Merged Areas (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 950 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- August - 2020 |
No Image | |
1136 (New) |
200043-Establishment of Communication and Social Media Cell For Publicity of AIP Projects & Launching of Mass Awareness Campaigns in Newly Merged Areas (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 950 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- July - 2020 |
No Image | |
1136 (New) |
200043-Establishment of Communication and Social Media Cell For Publicity of AIP Projects & Launching of Mass Awareness Campaigns in Newly Merged Areas (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 950 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- May - 2021 |
No Image | |
1136 (New) |
200043-Establishment of Communication and Social Media Cell For Publicity of AIP Projects & Launching of Mass Awareness Campaigns in Newly Merged Areas (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 950 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- April - 2021 |
No Image | |
1136 (New) |
200043-Establishment of Communication and Social Media Cell For Publicity of AIP Projects & Launching of Mass Awareness Campaigns in Newly Merged Areas (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 950 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- March - 2021 |
No Image | |
1136 (New) |
200043-Establishment of Communication and Social Media Cell For Publicity of AIP Projects & Launching of Mass Awareness Campaigns in Newly Merged Areas (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 950 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- February - 2021 |
No Image | |
1136 (New) |
200043-Establishment of Communication and Social Media Cell For Publicity of AIP Projects & Launching of Mass Awareness Campaigns in Newly Merged Areas (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 950 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- January - 2021 |
No Image | |
Pages : 1 |