Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1132 (OG) |
140900-F/S, Design & Improvement & BT of Kumber to Gumbat Banda Road (15 Km) Dir Lower. |
Dir Lower |
19-08-15 | - | - | 28-01-15 | - | 162.54 | 34.5 | 30 | 23.25 | 15.75 | 15.726 | 50.226 | 98.04 | 40% |
31% December - 2017 |
Length 15 Km - out of 4 packages, all in progress. 2 Km BT. |
No Image |
1132 (OG) |
140900-F/S, Design & Improvement & BT of Kumber to Gumbat Banda Road (15 Km) Dir Lower. |
Dir Lower |
19-08-15 | - | - | 28-01-15 | - | 162.54 | 34.5 | 30 | 30 | 10.65 | 10.65 | 45.15 | 98.04 | 40% |
28% September - 2017 |
Length 15 Km - out of 4 packages, all in progress. 2 Km BT. |
No Image |
1132 (OG) |
140900-F/S, Design & Improvement & BT of Kumber to Gumbat Banda Road (15 Km) Dir Lower. |
Dir Lower |
19-08-15 | - | - | 28-01-15 | - | 162.54 | 34.5 | 30 | 30 | 10.65 | 10.65 | 45.15 | 98.04 | 40% |
28% August - 2017 |
Length 15 Km - out of 4 packages, all in progress. 2 Km BT. |
No Image |
1132 (OG) |
140900-F/S, Design & Improvement & BT of Kumber to Gumbat Banda Road (15 Km) Dir Lower. |
Dir Lower |
19-08-15 | - | - | 28-01-15 | - | 162.54 | 34.5 | 30 | 30 | 10.65 | 0 | 34.5 | 98.04 | 40% |
21% July - 2017 |
Length 15 Km - out of 4 packages, all in progress. 2 Km BT. |
No Image |
1132 (OG) |
140900-F/S, Design & Improvement & BT of Kumber to Gumbat Banda Road (15 Km) Dir Lower. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 162.54 | 34.5 | 30 | 23.226 | 15.726 | 15.726 | 50.226 | 98.04 | 40% |
31% November - 2017 |
Length 15 Km - out of 4 packages, all in progress. 2 Km BT. |
No Image |
1132 (OG) |
140900-F/S, Design & Improvement & BT of Kumber to Gumbat Banda Road (15 Km) Dir Lower. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 162.54 | 34.5 | 30 | 30 | 18.15 | 10.65 | 45.15 | 98.04 | 40% |
28% October - 2017 |
Length 15 Km - out of 4 packages, all in progress. 2 Km BT. |
No Image |
1132 (OG) |
140900-F/S, Design & Improvement & BT of Kumber to Gumbat Banda Road (15 Km) Dir Lower. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 162.54 | 34.5 | 30 | 23.25 | 23.25 | 23.25 | 57.75 | 98.04 | 40% |
36% June - 2018 |
Length 15 Km - out of 4 packages, all in progress. 2 Km BT. |
No Image |
1) Package-1
2) Package-2
3) Package-3
4) Package-4 | |||||||||||||||||||
1132 (OG) |
140900-F/S, Design & Improvement & BT of Kumber to Gumbat Banda Road (15 Km) Dir Lower. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 162.54 | 34.5 | 30 | 23.25 | 23.25 | 23.25 | 57.75 | 98.04 | 40% |
36% May - 2018 |
Length 15 Km - out of 4 packages, all in progress. 2 Km BT. |
No Image |
1) Package-1
2) Package-2
3) Package-3
4) Package-4 | |||||||||||||||||||
1132 (OG) |
140900-F/S, Design & Improvement & BT of Kumber to Gumbat Banda Road (15 Km) Dir Lower. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 162.54 | 34.5 | 30 | 23.25 | 23.25 | 23.25 | 57.75 | 98.04 | 40% |
36% April - 2018 |
Length 15 Km - out of 4 packages, all in progress. 2 Km BT. |
No Image |
1) Package-1
2) Package-2
3) Package-3
4) Package-4 | |||||||||||||||||||
1132 (OG) |
140900-F/S, Design & Improvement & BT of Kumber to Gumbat Banda Road (15 Km) Dir Lower. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 162.54 | 34.5 | 30 | 23.25 | 15.75 | 15.726 | 50.226 | 98.04 | 40% |
31% March - 2018 |
Length 15 Km - out of 4 packages, all in progress. 2 Km BT. |
No Image |
1) Package-1
2) Package-2
3) Package-3
4) Package-4 | |||||||||||||||||||
1132 (OG) |
140900-F/S, Design & Improvement & BT of Kumber to Gumbat Banda Road (15 Km) Dir Lower. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 162.54 | 34.5 | 30 | 23.25 | 15.75 | 15.726 | 50.226 | 98.04 | 40% |
31% February - 2018 |
Length 15 Km - out of 4 packages, all in progress. 2 Km BT. |
ADP's Images |
1132 (OG) |
140900-F/S, Design & Improvement & BT of Kumber to Gumbat Banda Road (15 Km) Dir Lower. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 162.54 | 34.5 | 30 | 23.25 | 15.75 | 15.726 | 50.226 | 98.04 | 40% |
31% January - 2018 |
Length 15 Km - out of 4 packages, all in progress. 2 Km BT. |
No Image |
1132 (New) |
180561-F/S and Establishment of Female indoor sports facilities at divisional headquarters in Khyber Pakhtunkhwa. |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- December - 2018 |
PC-I/DCE for Rs.83 m sumbitted to DSO Mardan on 17/12/2018. |
No Image |
Construction of Gymnasium for female at Mardan | |||||||||||||||||||
1132 (New) |
180561-F/S and Establishment of Female indoor sports facilities at divisional headquarters in Khyber Pakhtunkhwa. |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- April - 2019 |
PC-I/DCE for Rs.83.121 m sumbitted to DSO Mardan on 04/01/2019. |
No Image |
Construction of Gymnasium for female at Mardan | |||||||||||||||||||
1132 (New) |
180561-F/S and Establishment of Female indoor sports facilities at divisional headquarters in Khyber Pakhtunkhwa. |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- March - 2019 |
PC-I/DCE for Rs.83.121 m sumbitted to DSO Mardan on 04/01/2019. |
No Image |
Construction of Gymnasium for female at Mardan | |||||||||||||||||||
1132 (New) |
180561-F/S and Establishment of Female indoor sports facilities at divisional headquarters in Khyber Pakhtunkhwa. |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- March - 2019 |
PC-I/DCE for Rs.83.121 m sumbitted to DSO Mardan on 04/01/2019. |
No Image |
Construction of Gymnasium for female at Mardan | |||||||||||||||||||
1132 (New) |
180561-F/S and Establishment of Female indoor sports facilities at divisional headquarters in Khyber Pakhtunkhwa. |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- February - 2019 |
PC-I/DCE for Rs.83 m sumbitted to DSO Mardan on 17/12/2018. |
No Image |
Construction of Gymnasium for female at Mardan | |||||||||||||||||||
1132 (New) |
180561-F/S and Establishment of Female indoor sports facilities at divisional headquarters in Khyber Pakhtunkhwa. |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- January - 2019 |
PC-I/DCE for Rs.83 m sumbitted to DSO Mardan on 17/12/2018. |
No Image |
Construction of Gymnasium for female at Mardan | |||||||||||||||||||
1132 (New) |
180561-F/S and Establishment of Female indoor sports facilities at divisional headquarters in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 700 | 0 | 5 | 5 | 0 | 0 | 0 | 0 | - |
- December - 2018 |
No Image | |
1132 (New) |
200082-F/S for Establishment of Construction Machinery Training Institute in Merged Areas (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 20 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
No Image | |
1132 (New) |
200082-F/S for Establishment of Construction Machinery Training Institute in Merged Areas (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 20 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
No Image | |
1132 (New) |
200082-F/S for Establishment of Construction Machinery Training Institute in Merged Areas (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 20 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- October - 2020 |
No Image | |
1132 (New) |
200082-F/S for Establishment of Construction Machinery Training Institute in Merged Areas (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 20 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- September - 2020 |
No Image | |
1132 (New) |
200082-F/S for Establishment of Construction Machinery Training Institute in Merged Areas (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 20 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- August - 2020 |
No Image | |
1132 (New) |
200082-F/S for Establishment of Construction Machinery Training Institute in Merged Areas (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 20 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- July - 2020 |
No Image | |
1132 (New) |
200082-F/S for Establishment of Construction Machinery Training Institute in Merged Areas (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 20 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- May - 2021 |
No Image | |
1132 (New) |
180561-F/S and Establishment of Female indoor sports facilities at divisional headquarters in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 700 | 0 | 5 | 5 | 0 | 0 | 0 | 695 | 1% |
- April - 2019 |
Approved. |
No Image |
1132 (New) |
200082-F/S for Establishment of Construction Machinery Training Institute in Merged Areas (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 20 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- April - 2021 |
No Image | |
1132 (New) |
180561-F/S and Establishment of Female indoor sports facilities at divisional headquarters in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 700 | 0 | 5 | 5 | 0 | 0 | 0 | 695 | 1% |
- March - 2019 |
Approved. |
No Image |
1132 (New) |
180561-F/S and Establishment of Female indoor sports facilities at divisional headquarters in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 700 | 0 | 5 | 5 | 0 | 0 | 0 | 695 | 1% |
- March - 2019 |
Approved. |
No Image |
1132 (New) |
200082-F/S for Establishment of Construction Machinery Training Institute in Merged Areas (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 20 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- March - 2021 |
No Image | |
1132 (New) |
180561-F/S and Establishment of Female indoor sports facilities at divisional headquarters in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 700 | 0 | 5 | 5 | 0 | 0 | 0 | 0 | - |
- February - 2019 |
No Image | |
1132 (New) |
200082-F/S for Establishment of Construction Machinery Training Institute in Merged Areas (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 20 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- February - 2021 |
No Image | |
1132 (New) |
180561-F/S and Establishment of Female indoor sports facilities at divisional headquarters in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 700 | 0 | 5 | 5 | 0 | 0 | 0 | 0 | - |
- January - 2019 |
No Image | |
1132 (New) |
200082-F/S for Establishment of Construction Machinery Training Institute in Merged Areas (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 20 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- January - 2021 |
No Image | |
Pages : 1 |