Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2018, January - 2021, February - 2018, February - 2021, March - 2018, March - 2021, April - 2018, April - 2021, May - 2018, May - 2021, June - 2018, July - 2020, July - 2017, August - 2020, August - 2017, September - 2020, September - 2017, October - 2017, October - 2020, November - 2017, December - 2020, December - 2017,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1130
(OG)
140830-F/S, Design & Construction of BT roads (a) Mian Kalay to Kambat (b) Link road to Ghwara Banda, Gawardesh, Janpassa, Parata, Nawkoto and Hisarak District Dir Lower.
Dir Lower
15-08-15 - - 14-04-15 - 1210.57 194.928 30 38.65 31.15 24.15 219.078 985.642 19% 18%
December - 2017
Length 43 Km - (a) Land acquisition under process in 22 Km. (b) Work in progress in 21 Km. BT 4 Km completed.
No Image
1130
(OG)
140830-F/S, Design & Construction of BT roads (a) Mian Kalay to Kambat (b) Link road to Ghwara Banda, Gawardesh, Janpassa, Parata, Nawkoto and Hisarak District Dir Lower.
Dir Lower
15-08-15 - - 14-04-15 - 1210.57 194.928 30 30 10.65 10.65 205.578 985.642 19% 17%
September - 2017
Length 43 Km - (a) Land acquisition under process in 22 Km. (b) Work in progress in 21 Km. BT 4 Km completed.
No Image
1130
(OG)
140830-F/S, Design & Construction of BT roads (a) Mian Kalay to Kambat (b) Link road to Ghwara Banda, Gawardesh, Janpassa, Parata, Nawkoto and Hisarak District Dir Lower.
Dir Lower
15-08-15 - - 14-04-15 - 1210.57 194.928 30 30 10.65 10.65 205.578 985.642 19% 17%
August - 2017
Length 43 Km - (a) Land acquisition under process in 22 Km. (b) Work in progress in 21 Km. BT 4 Km completed.
No Image
1130
(OG)
140830-F/S, Design & Construction of BT roads (a) Mian Kalay to Kambat (b) Link road to Ghwara Banda, Gawardesh, Janpassa, Parata, Nawkoto and Hisarak District Dir Lower.
Dir Lower
15-08-15 - - 14-04-15 - 1210.57 194.928 30 30 10.65 0 194.928 985.642 19% 16%
July - 2017
Length 43 Km - (a) Land acquisition under process in 22 Km. (b) Work in progress in 21 Km. BT 4 Km completed.
No Image
1130
(OG)
140830-F/S, Design & Construction of BT roads (a) Mian Kalay to Kambat (b) Link road to Ghwara Banda, Gawardesh, Janpassa, Parata, Nawkoto and Hisarak District Dir Lower.
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 1210.57 194.928 30 31.65 24.15 24.15 219.078 985.642 19% 18%
November - 2017
Length 43 Km - (a) Land acquisition under process in 22 Km. (b) Work in progress in 21 Km. BT 4 Km completed.
No Image
1130
(OG)
140830-F/S, Design & Construction of BT roads (a) Mian Kalay to Kambat (b) Link road to Ghwara Banda, Gawardesh, Janpassa, Parata, Nawkoto and Hisarak District Dir Lower.
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 1210.57 194.928 30 30 18.15 18.15 213.078 985.642 19% 18%
October - 2017
Length 43 Km - (a) Land acquisition under process in 22 Km. (b) Work in progress in 21 Km. BT 4 Km completed.
No Image
1130
(OG)
140830-F/S, Design & Construction of BT roads (a) Mian Kalay to Kambat (b) Link road to Ghwara Banda, Gawardesh, Janpassa, Parata, Nawkoto and Hisarak District Dir Lower.
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 1210.57 194.61 30 47.742 47.742 47.742 242.352 985.96 19% 20%
June - 2018
Length 43 Km ) (7 units) - (a) Land acquisition under process in 22 Km. (b) Work in progress in 21 Km. BT 4 Km completed.
No Image
1) Mian Kalay to Kambat
2) Link road Ghwara Banda
3) Link road Gawardesh
4) Link road Janpassa
5) Link road Pratta
6) Link road Nawo Koto
7) Link road Hisarak
1130
(OG)
140830-F/S, Design & Construction of BT roads (a) Mian Kalay to Kambat (b) Link road to Ghwara Banda, Gawardesh, Janpassa, Parata, Nawkoto and Hisarak District Dir Lower.
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 1210.57 194.61 30 47.742 47.742 47.742 242.352 985.96 19% 20%
May - 2018
Length 43 Km ) (7 units) - (a) Land acquisition under process in 22 Km. (b) Work in progress in 21 Km. BT 4 Km completed.
No Image
1) Mian Kalay to Kambat
2) Link road Ghwara Banda
3) Link road Gawardesh
4) Link road Janpassa
5) Link road Pratta
6) Link road Nawo Koto
7) Link road Hisarak
1130
(OG)
140830-F/S, Design & Construction of BT roads (a) Mian Kalay to Kambat (b) Link road to Ghwara Banda, Gawardesh, Janpassa, Parata, Nawkoto and Hisarak District Dir Lower.
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 1210.57 194.61 30 47.742 47.742 47.742 242.352 985.96 19% 20%
April - 2018
Length 43 Km ) (7 units) - (a) Land acquisition under process in 22 Km. (b) Work in progress in 21 Km. BT 4 Km completed.
No Image
1) Mian Kalay to Kambat
2) Link road Ghwara Banda
3) Link road Gawardesh
4) Link road Janpassa
5) Link road Pratta
6) Link road Nawo Koto
7) Link road Hisarak
1130
(OG)
140830-F/S, Design & Construction of BT roads (a) Mian Kalay to Kambat (b) Link road to Ghwara Banda, Gawardesh, Janpassa, Parata, Nawkoto and Hisarak District Dir Lower.
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 1210.57 194.61 30 45.052 45.052 45.052 239.662 985.96 19% 20%
March - 2018
Length 43 Km ) (7 units) - (a) Land acquisition under process in 22 Km. (b) Work in progress in 21 Km. BT 4 Km completed.
No Image
1) Mian Kalay to Kambat
2) Link road Ghwara Banda
3) Link road Gawardesh
4) Link road Janpassa
5) Link road Pratta
6) Link road Nawo Koto
7) Link road Hisarak
1130
(OG)
140830-F/S, Design & Construction of BT roads (a) Mian Kalay to Kambat (b) Link road to Ghwara Banda, Gawardesh, Janpassa, Parata, Nawkoto and Hisarak District Dir Lower.
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 1210.57 194.61 30 45.052 45.052 45.052 239.662 985.96 19% 20%
February - 2018
Length 43 Km ) (7 units ) - (a) Land acquisition under process in 22 Km. (b) Work in progress in 21 Km. BT 4 Km completed.
No Image
1130
(OG)
140830-F/S, Design & Construction of BT roads (a) Mian Kalay to Kambat (b) Link road to Ghwara Banda, Gawardesh, Janpassa, Parata, Nawkoto and Hisarak District Dir Lower.
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 1210.57 194.928 30 45.052 45.052 45.052 239.98 985.642 19% 20%
January - 2018
Length 43 Km - (a) Land acquisition under process in 22 Km. (b) Work in progress in 21 Km. BT 4 Km completed.
No Image
1130
(New)
200063-F/S & Establishment of Industrial Estates in Merged Districts (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 50 0 0 0 0 0 0 0 - -
December - 2020
No Image
1130
(New)
200063-F/S & Establishment of Industrial Estates in Merged Districts (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 50 0 0 0 0 0 0 0 - -
December - 2020
No Image
1130
(New)
200063-F/S & Establishment of Industrial Estates in Merged Districts (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 50 0 0 0 0 0 0 0 - -
October - 2020
No Image
1130
(New)
200063-F/S & Establishment of Industrial Estates in Merged Districts (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 50 0 0 0 0 0 0 0 - -
September - 2020
No Image
1130
(New)
200063-F/S & Establishment of Industrial Estates in Merged Districts (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 50 0 0 0 0 0 0 0 - -
August - 2020
No Image
1130
(New)
200063-F/S & Establishment of Industrial Estates in Merged Districts (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 50 0 0 0 0 0 0 0 - -
July - 2020
No Image
1130
(New)
200063-F/S & Establishment of Industrial Estates in Merged Districts (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 50 0 0 0 0 0 0 0 - -
May - 2021
No Image
1130
(New)
200063-F/S & Establishment of Industrial Estates in Merged Districts (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 50 0 0 0 0 0 0 0 - -
April - 2021
No Image
1130
(New)
200063-F/S & Establishment of Industrial Estates in Merged Districts (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 50 0 0 0 0 0 0 0 - -
March - 2021
No Image
1130
(New)
200063-F/S & Establishment of Industrial Estates in Merged Districts (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 50 0 0 0 0 0 0 0 - -
February - 2021
No Image
1130
(New)
200063-F/S & Establishment of Industrial Estates in Merged Districts (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 50 0 0 0 0 0 0 0 - -
January - 2021
No Image
Pages : 1