Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1130 (OG) |
140830-F/S, Design & Construction of BT roads (a) Mian Kalay to Kambat (b) Link road to Ghwara Banda, Gawardesh, Janpassa, Parata, Nawkoto and Hisarak District Dir Lower. |
Dir Lower |
15-08-15 | - | - | 14-04-15 | - | 1210.57 | 194.928 | 30 | 38.65 | 31.15 | 24.15 | 219.078 | 985.642 | 19% |
18% December - 2017 |
Length 43 Km - (a) Land acquisition under process in 22 Km. (b) Work in progress in 21 Km. BT 4 Km completed. |
No Image |
1130 (OG) |
140830-F/S, Design & Construction of BT roads (a) Mian Kalay to Kambat (b) Link road to Ghwara Banda, Gawardesh, Janpassa, Parata, Nawkoto and Hisarak District Dir Lower. |
Dir Lower |
15-08-15 | - | - | 14-04-15 | - | 1210.57 | 194.928 | 30 | 30 | 10.65 | 10.65 | 205.578 | 985.642 | 19% |
17% September - 2017 |
Length 43 Km - (a) Land acquisition under process in 22 Km. (b) Work in progress in 21 Km. BT 4 Km completed. |
No Image |
1130 (OG) |
140830-F/S, Design & Construction of BT roads (a) Mian Kalay to Kambat (b) Link road to Ghwara Banda, Gawardesh, Janpassa, Parata, Nawkoto and Hisarak District Dir Lower. |
Dir Lower |
15-08-15 | - | - | 14-04-15 | - | 1210.57 | 194.928 | 30 | 30 | 10.65 | 10.65 | 205.578 | 985.642 | 19% |
17% August - 2017 |
Length 43 Km - (a) Land acquisition under process in 22 Km. (b) Work in progress in 21 Km. BT 4 Km completed. |
No Image |
1130 (OG) |
140830-F/S, Design & Construction of BT roads (a) Mian Kalay to Kambat (b) Link road to Ghwara Banda, Gawardesh, Janpassa, Parata, Nawkoto and Hisarak District Dir Lower. |
Dir Lower |
15-08-15 | - | - | 14-04-15 | - | 1210.57 | 194.928 | 30 | 30 | 10.65 | 0 | 194.928 | 985.642 | 19% |
16% July - 2017 |
Length 43 Km - (a) Land acquisition under process in 22 Km. (b) Work in progress in 21 Km. BT 4 Km completed. |
No Image |
1130 (OG) |
140830-F/S, Design & Construction of BT roads (a) Mian Kalay to Kambat (b) Link road to Ghwara Banda, Gawardesh, Janpassa, Parata, Nawkoto and Hisarak District Dir Lower. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1210.57 | 194.928 | 30 | 31.65 | 24.15 | 24.15 | 219.078 | 985.642 | 19% |
18% November - 2017 |
Length 43 Km - (a) Land acquisition under process in 22 Km. (b) Work in progress in 21 Km. BT 4 Km completed. |
No Image |
1130 (OG) |
140830-F/S, Design & Construction of BT roads (a) Mian Kalay to Kambat (b) Link road to Ghwara Banda, Gawardesh, Janpassa, Parata, Nawkoto and Hisarak District Dir Lower. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1210.57 | 194.928 | 30 | 30 | 18.15 | 18.15 | 213.078 | 985.642 | 19% |
18% October - 2017 |
Length 43 Km - (a) Land acquisition under process in 22 Km. (b) Work in progress in 21 Km. BT 4 Km completed. |
No Image |
1130 (OG) |
140830-F/S, Design & Construction of BT roads (a) Mian Kalay to Kambat (b) Link road to Ghwara Banda, Gawardesh, Janpassa, Parata, Nawkoto and Hisarak District Dir Lower. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1210.57 | 194.61 | 30 | 47.742 | 47.742 | 47.742 | 242.352 | 985.96 | 19% |
20% June - 2018 |
Length 43 Km ) (7 units) - (a) Land acquisition under process in 22 Km. (b) Work in progress in 21 Km. BT 4 Km completed. |
No Image |
1) Mian Kalay to Kambat
2) Link road Ghwara Banda
3) Link road Gawardesh
4) Link road Janpassa
5) Link road Pratta
6) Link road Nawo Koto
7) Link road Hisarak | |||||||||||||||||||
1130 (OG) |
140830-F/S, Design & Construction of BT roads (a) Mian Kalay to Kambat (b) Link road to Ghwara Banda, Gawardesh, Janpassa, Parata, Nawkoto and Hisarak District Dir Lower. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1210.57 | 194.61 | 30 | 47.742 | 47.742 | 47.742 | 242.352 | 985.96 | 19% |
20% May - 2018 |
Length 43 Km ) (7 units) - (a) Land acquisition under process in 22 Km. (b) Work in progress in 21 Km. BT 4 Km completed. |
No Image |
1) Mian Kalay to Kambat
2) Link road Ghwara Banda
3) Link road Gawardesh
4) Link road Janpassa
5) Link road Pratta
6) Link road Nawo Koto
7) Link road Hisarak | |||||||||||||||||||
1130 (OG) |
140830-F/S, Design & Construction of BT roads (a) Mian Kalay to Kambat (b) Link road to Ghwara Banda, Gawardesh, Janpassa, Parata, Nawkoto and Hisarak District Dir Lower. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1210.57 | 194.61 | 30 | 47.742 | 47.742 | 47.742 | 242.352 | 985.96 | 19% |
20% April - 2018 |
Length 43 Km ) (7 units) - (a) Land acquisition under process in 22 Km. (b) Work in progress in 21 Km. BT 4 Km completed. |
No Image |
1) Mian Kalay to Kambat
2) Link road Ghwara Banda
3) Link road Gawardesh
4) Link road Janpassa
5) Link road Pratta
6) Link road Nawo Koto
7) Link road Hisarak | |||||||||||||||||||
1130 (OG) |
140830-F/S, Design & Construction of BT roads (a) Mian Kalay to Kambat (b) Link road to Ghwara Banda, Gawardesh, Janpassa, Parata, Nawkoto and Hisarak District Dir Lower. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1210.57 | 194.61 | 30 | 45.052 | 45.052 | 45.052 | 239.662 | 985.96 | 19% |
20% March - 2018 |
Length 43 Km ) (7 units) - (a) Land acquisition under process in 22 Km. (b) Work in progress in 21 Km. BT 4 Km completed. |
No Image |
1) Mian Kalay to Kambat
2) Link road Ghwara Banda
3) Link road Gawardesh
4) Link road Janpassa
5) Link road Pratta
6) Link road Nawo Koto
7) Link road Hisarak | |||||||||||||||||||
1130 (OG) |
140830-F/S, Design & Construction of BT roads (a) Mian Kalay to Kambat (b) Link road to Ghwara Banda, Gawardesh, Janpassa, Parata, Nawkoto and Hisarak District Dir Lower. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1210.57 | 194.61 | 30 | 45.052 | 45.052 | 45.052 | 239.662 | 985.96 | 19% |
20% February - 2018 |
Length 43 Km ) (7 units ) - (a) Land acquisition under process in 22 Km. (b) Work in progress in 21 Km. BT 4 Km completed. |
No Image |
1130 (OG) |
140830-F/S, Design & Construction of BT roads (a) Mian Kalay to Kambat (b) Link road to Ghwara Banda, Gawardesh, Janpassa, Parata, Nawkoto and Hisarak District Dir Lower. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1210.57 | 194.928 | 30 | 45.052 | 45.052 | 45.052 | 239.98 | 985.642 | 19% |
20% January - 2018 |
Length 43 Km - (a) Land acquisition under process in 22 Km. (b) Work in progress in 21 Km. BT 4 Km completed. |
No Image |
1130 (New) |
200063-F/S & Establishment of Industrial Estates in Merged Districts (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 50 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
No Image | |
1130 (New) |
200063-F/S & Establishment of Industrial Estates in Merged Districts (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 50 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
No Image | |
1130 (New) |
200063-F/S & Establishment of Industrial Estates in Merged Districts (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 50 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- October - 2020 |
No Image | |
1130 (New) |
200063-F/S & Establishment of Industrial Estates in Merged Districts (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 50 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- September - 2020 |
No Image | |
1130 (New) |
200063-F/S & Establishment of Industrial Estates in Merged Districts (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 50 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- August - 2020 |
No Image | |
1130 (New) |
200063-F/S & Establishment of Industrial Estates in Merged Districts (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 50 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- July - 2020 |
No Image | |
1130 (New) |
200063-F/S & Establishment of Industrial Estates in Merged Districts (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 50 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- May - 2021 |
No Image | |
1130 (New) |
200063-F/S & Establishment of Industrial Estates in Merged Districts (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 50 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- April - 2021 |
No Image | |
1130 (New) |
200063-F/S & Establishment of Industrial Estates in Merged Districts (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 50 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- March - 2021 |
No Image | |
1130 (New) |
200063-F/S & Establishment of Industrial Estates in Merged Districts (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 50 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- February - 2021 |
No Image | |
1130 (New) |
200063-F/S & Establishment of Industrial Estates in Merged Districts (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 50 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- January - 2021 |
No Image | |
Pages : 1 |