Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1129 (OG) |
130669-Improvement and blacktopping of Mayar-Asmar Road, Dir Lower (Phase-II). |
Dir Lower |
24-10-14 | 30-06-18 | - | 10-10-13 | - | 126.085 | 75.444 | 48.141 | 48.141 | 36.105 | 30.82 | 106.264 | 2.5 | 98% |
84% December - 2017 |
Length 7.8 Km - 7.8 BT Km completed. |
No Image |
1129 (OG) |
130669-Improvement and blacktopping of Mayar-Asmar Road, Dir Lower (Phase-II). |
Dir Lower |
24-10-14 | 30-06-18 | - | 10-10-13 | - | 126.085 | 75.444 | 48.141 | 48.141 | 24.07 | 24.07 | 99.514 | 2.5 | 98% |
79% September - 2017 |
Length 7.8 Km - 4 Km completed. 2 Km sub base, WBM completed. |
No Image |
1129 (OG) |
130669-Improvement and blacktopping of Mayar-Asmar Road, Dir Lower (Phase-II). |
Dir Lower |
24-10-14 | 30-06-18 | - | 10-10-13 | - | 126.085 | 75.444 | 48.141 | 48.141 | 17.09 | 9.873 | 85.317 | 2.5 | 98% |
68% August - 2017 |
Length 7.8 Km - 4 Km completed. 2 Km sub base, WBM completed. |
No Image |
1129 (OG) |
130669-Improvement and blacktopping of Mayar-Asmar Road, Dir Lower (Phase-II). |
Dir Lower |
24-10-14 | 30-06-18 | - | 10-10-13 | - | 126.085 | 75.444 | 48.141 | 48.141 | 17.09 | 0 | 75.444 | 2.5 | 98% |
60% July - 2017 |
Length 7.8 Km - 4 Km completed. 2 Km sub base, WBM completed. |
No Image |
1129 (OG) |
130669-Improvement and blacktopping of Mayar-Asmar Road, Dir Lower (Phase-II). |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 126.085 | 75.444 | 48.141 | 48.141 | 36.105 | 30.77 | 106.214 | 2.5 | 98% |
84% November - 2017 |
Length 7.8 Km - 7.8 BT Km completed. |
No Image |
1129 (OG) |
130669-Improvement and blacktopping of Mayar-Asmar Road, Dir Lower (Phase-II). |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 126.085 | 75.444 | 48.141 | 48.141 | 36.015 | 24.07 | 99.514 | 2.5 | 98% |
79% October - 2017 |
Length 7.8 Km - 6.5 Km completed. |
No Image |
1129 (OG) |
130669-Improvement and blacktopping of Mayar-Asmar Road, Dir Lower (Phase-II). |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 126.085 | 75.445 | 48.141 | 32.721 | 34.72 | 32.721 | 108.166 | 2.499 | 98% |
86% June - 2018 |
Length 7.8 Km - 7.8 BT Km completed. |
No Image |
1) Package-1
2) Package-2 | |||||||||||||||||||
1129 (OG) |
130669-Improvement and blacktopping of Mayar-Asmar Road, Dir Lower (Phase-II). |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 126.085 | 75.445 | 48.141 | 48.141 | 48.141 | 32.109 | 107.554 | 2.499 | 98% |
85% May - 2018 |
Length 7.8 Km - 7.8 BT Km completed. |
No Image |
1) Package-1
2) Package-2 | |||||||||||||||||||
1129 (OG) |
130669-Improvement and blacktopping of Mayar-Asmar Road, Dir Lower (Phase-II). |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 126.085 | 75.445 | 48.141 | 48.141 | 48.14 | 32.109 | 107.554 | 2.499 | 98% |
85% April - 2018 |
Length 7.8 Km - 7.8 BT Km completed. |
No Image |
1) Package-1
2) Package-2 | |||||||||||||||||||
1129 (OG) |
130669-Improvement and blacktopping of Mayar-Asmar Road, Dir Lower (Phase-II). |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 126.085 | 75.445 | 48.141 | 48.141 | 48.14 | 30.82 | 106.265 | 2.499 | 98% |
84% March - 2018 |
Length 7.8 Km - 7.8 BT Km completed. |
No Image |
1) Package-1
2) Package-2 | |||||||||||||||||||
1129 (OG) |
130669-Improvement and blacktopping of Mayar-Asmar Road, Dir Lower (Phase-II). |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 126.085 | 75.445 | 48.141 | 48.141 | 36.105 | 30.82 | 106.265 | 2.499 | 98% |
84% February - 2018 |
Length 7.8 Km - 7.8 BT Km completed. |
No Image |
1129 (OG) |
130669-Improvement and blacktopping of Mayar-Asmar Road, Dir Lower (Phase-II). |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 126.085 | 75.444 | 48.141 | 48.141 | 36.105 | 30.82 | 106.264 | 2.5 | 98% |
84% January - 2018 |
Length 7.8 Km - 7.8 BT Km completed. |
No Image |
1129 (OG) |
190089 - Small Scale Tourism Promotional activities in Khyber Pakhtunkhwa |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.88 | 0 | 0 | 0 | 0 | 0 | 0 | 99.88 | - |
- May - 2020 |
Procurement under process. |
No Image |
1. | |||||||||||||||||||
1129 (OG) |
190089 - Small Scale Tourism Promotional activities in Khyber Pakhtunkhwa |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.88 | 0 | 0 | 0 | 0 | 0 | 0 | 99.88 | - |
- April - 2020 |
Procurement under process. |
No Image |
1. | |||||||||||||||||||
1129 (OG) |
190089 - Small Scale Tourism Promotional activities in Khyber Pakhtunkhwa |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.88 | 0 | 0 | 0 | 0 | 0 | 0 | 99.88 | - |
- March - 2020 |
Procurement under process. |
No Image |
1. | |||||||||||||||||||
1129 (OG) |
190089 - Small Scale Tourism Promotional activities in Khyber Pakhtunkhwa |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.88 | 0 | 0 | 0 | 0 | 0 | 0 | 99.88 | - |
- February - 2020 |
Procurement under process. |
No Image |
1. | |||||||||||||||||||
1129 (New) |
200062-Establishment of Small Industrial Estate at Bajaur (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 300 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
No Image | |
1129 (New) |
200062-Establishment of Small Industrial Estate at Bajaur (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 300 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
No Image | |
1129 (New) |
200062-Establishment of Small Industrial Estate at Bajaur (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 300 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- October - 2020 |
No Image | |
1129 (New) |
200062-Establishment of Small Industrial Estate at Bajaur (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 300 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- September - 2020 |
No Image | |
1129 (New) |
200062-Establishment of Small Industrial Estate at Bajaur (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 300 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- August - 2020 |
No Image | |
1129 (New) |
200062-Establishment of Small Industrial Estate at Bajaur (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 300 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- July - 2020 |
No Image | |
1129 (OG) |
190089 - Small Scale Tourism Promotional activities in Khyber Pakhtunkhwa |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- May - 2020 |
No Image | |
1129 (New) |
200062-Establishment of Small Industrial Estate at Bajaur (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 300 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- May - 2021 |
No Image | |
1129 (OG) |
190089 - Small Scale Tourism Promotional activities in Khyber Pakhtunkhwa |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- April - 2020 |
No Image | |
1129 (New) |
200062-Establishment of Small Industrial Estate at Bajaur (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 300 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- April - 2021 |
No Image | |
1129 (OG) |
190089 - Small Scale Tourism Promotional activities in Khyber Pakhtunkhwa |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- March - 2020 |
No Image | |
1129 (New) |
200062-Establishment of Small Industrial Estate at Bajaur (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 300 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- March - 2021 |
No Image | |
1129 (OG) |
190089 - Small Scale Tourism Promotional activities in Khyber Pakhtunkhwa |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- February - 2020 |
No Image | |
1129 (New) |
200062-Establishment of Small Industrial Estate at Bajaur (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 300 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- February - 2021 |
No Image | |
1129 (New) |
200062-Establishment of Small Industrial Estate at Bajaur (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 300 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- January - 2021 |
No Image | |