Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2021, January - 2018, February - 2021, February - 2018, March - 2018, March - 2021, April - 2018, April - 2021, May - 2018, May - 2021, June - 2018, July - 2020, July - 2017, August - 2020, August - 2017, September - 2020, September - 2017, October - 2020, October - 2017, November - 2017, December - 2020, December - 2017,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1126
(OG)
195215-Interest free microfinance schemes (IFMS) for entrepreneurship development in MAs (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 - 1105 150 0 0 0 0 150 0 - -
December - 2020
No Image
1126
(OG)
195215-Interest free microfinance schemes (IFMS) for entrepreneurship development in MAs (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 - 1105 150 0 0 0 0 150 0 - -
December - 2020
No Image
1126
(OG)
195215-Interest free microfinance schemes (IFMS) for entrepreneurship development in MAs (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 - 1105 150 0 0 0 0 150 0 - -
October - 2020
No Image
1126
(OG)
195215-Interest free microfinance schemes (IFMS) for entrepreneurship development in MAs (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 - 1105 150 0 0 0 0 150 0 - -
September - 2020
No Image
1126
(OG)
195215-Interest free microfinance schemes (IFMS) for entrepreneurship development in MAs (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 - 1105 150 0 0 0 0 150 0 - -
August - 2020
No Image
1126
(OG)
195215-Interest free microfinance schemes (IFMS) for entrepreneurship development in MAs (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 - 1105 150 0 0 0 0 150 0 -
July - 2020
No Image
1126
(OG)
195215-Interest free microfinance schemes (IFMS) for entrepreneurship development in MAs (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 - 1105 150 0 0 0 0 150 0 - -
May - 2021
No Image
1126
(OG)
195215-Interest free microfinance schemes (IFMS) for entrepreneurship development in MAs (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 - 1105 150 0 0 0 0 150 0 - -
April - 2021
No Image
1126
(OG)
195215-Interest free microfinance schemes (IFMS) for entrepreneurship development in MAs (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 - 1105 150 0 0 0 0 150 0 - -
March - 2021
No Image
1126
(OG)
195215-Interest free microfinance schemes (IFMS) for entrepreneurship development in MAs (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 - 1105 150 0 0 0 0 150 0 - -
February - 2021
No Image
1126
(OG)
195215-Interest free microfinance schemes (IFMS) for entrepreneurship development in MAs (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 - 1105 150 0 0 0 0 150 0 - -
January - 2021
No Image
1126
(OG)
150819-F/S, Design, Construction and Widening of Shalpin to Jishar Road, Babu to Mashkomai Maira road,Topsin to Ganajir Top road, Chinkolai to Faqira road, Khwazakhela to Dumbara road, Swat.
Swat
HW
05-04-17 - - 03-11-16 - 231.52 56.924 60 51.3 36.3 36.3 93.224 114.596 51% 40%
December - 2017
Shalpin Jishar road - 40% completed. Topsin to Ganajir road - 40% completed. Khawza Khela to Dambara - 30% completed.
No Image
PK 86
1126
(OG)
150819-F/S, Design, Construction and Widening of Shalpin to Jishar Road, Babu to Mashkomai Maira road,Topsin to Ganajir Top road, Chinkolai to Faqira road, Khwazakhela to Dumbara road, Swat.
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 231.52 56.924 60 51.3 36.3 29.453 86.377 114.596 51% 37%
November - 2017
Shalpin Jishar road - 40% completed. Topsin to Ganajir road - 40% completed. Khawza Khela to Dambara - 30% completed.
No Image
PK 86
1126
(OG)
150819-F/S, Design, Construction and Widening of Shalpin to Jishar Road, Babu to Mashkomai Maira road,Topsin to Ganajir Top road, Chinkolai to Faqira road, Khwazakhela to Dumbara road, Swat.
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 231.52 56.924 60 60 21.3 21.3 78.224 114.596 51% 34%
October - 2017
Shalpin Jishar road - 40% completed. Topsin to Ganajir road - 40% completed. Khawza Khela to Dambara - 30% completed.
No Image
PK 86
1126
(OG)
150819-F/S, Design, Construction and Widening of Shalpin to Jishar Road, Babu to Mashkomai Maira road,Topsin to Ganajir Top road, Chinkolai to Faqira road, Khwazakhela to Dumbara road, Swat.
Swat
HW
- - - 03-11-16 - 231.52 56.924 60 60 21.3 21.3 78.224 114.596 51% 34%
September - 2017
Shalpin Jishar road - 40% completed. Topsin to Ganajir road - 40% completed. Khawza Khela to Dambara - 30% completed.
No Image
PK 86
1126
(OG)
150819-F/S, Design, Construction and Widening of Shalpin to Jishar Road, Babu to Mashkomai Maira road,Topsin to Ganajir Top road, Chinkolai to Faqira road, Khwazakhela to Dumbara road, Swat.
Swat
HW
- - - 03-11-16 - 231.52 56.924 60 60 21.3 10 66.924 114.596 51% 29%
August - 2017
Shalpin Jishar road - 40% completed. Topsin to Ganajir road - 40% completed. Khawza Khela to Dambara - 30% completed.
No Image
PK 86
1126
(OG)
150819-F/S, Design, Construction and Widening of Shalpin to Jishar Road, Babu to Mashkomai Maira road,Topsin to Ganajir Top road, Chinkolai to Faqira road, Khwazakhela to Dumbara road, Swat.
Swat
HW
- - - 03-11-16 - 231.52 56.924 60 60 21.3 0 56.924 114.596 51% 25%
July - 2017
Shalpin Jishar road - 40% completed. Topsin to Ganajir road - 40% completed. Khawza Khela to Dambara - 30% completed.
No Image
PK 86
1126
(OG)
150819-F/S, Design, Construction and Widening of Shalpin to Jishar Road, Babu to Mashkomai Maira road,Topsin to Ganajir Top road, Chinkolai to Faqira road, Khwazakhela to Dumbara road, Swat.
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 231.52 56.924 60 60.753 61.673 60.753 117.677 114.596 51% 51%
June - 2018
Length 16.2 Km (5 units) - Shalpin Jishar road - 40% completed. Topsin to Ganajir road - 40% completed. Khawza Khela to Dambara - 30% completed.
No Image
PK 86, Swat
1126
(OG)
150819-F/S, Design, Construction and Widening of Shalpin to Jishar Road, Babu to Mashkomai Maira road,Topsin to Ganajir Top road, Chinkolai to Faqira road, Khwazakhela to Dumbara road, Swat.
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 231.52 56.924 60 61.673 61.673 59.277 116.201 114.596 51% 50%
May - 2018
Length 16.2 Km (5 units) - Shalpin Jishar road - 40% completed. Topsin to Ganajir road - 40% completed. Khawza Khela to Dambara - 30% completed. Rs.71 m demanded.
No Image
PK 86, Swat
1126
(OG)
150819-F/S, Design, Construction and Widening of Shalpin to Jishar Road, Babu to Mashkomai Maira road,Topsin to Ganajir Top road, Chinkolai to Faqira road, Khwazakhela to Dumbara road, Swat.
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 231.52 56.924 60 61.673 61.673 51.5 108.424 114.596 51% 47%
April - 2018
Length 16.2 Km (5 units) - Shalpin Jishar road - 40% completed. Topsin to Ganajir road - 40% completed. Khawza Khela to Dambara - 30% completed. Rs.71 m demanded.
No Image
PK 86, Swat
1126
(OG)
150819-F/S, Design, Construction and Widening of Shalpin to Jishar Road, Babu to Mashkomai Maira road,Topsin to Ganajir Top road, Chinkolai to Faqira road, Khwazakhela to Dumbara road, Swat.
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 231.52 56.924 60 61.673 61.673 51.5 108.424 114.596 51% 47%
March - 2018
Length 16.2 Km (5 units) - Shalpin Jishar road - 40% completed. Topsin to Ganajir road - 40% completed. Khawza Khela to Dambara - 30% completed.
No Image
PK 86, Swat
1126
(OG)
150819-F/S, Design, Construction and Widening of Shalpin to Jishar Road, Babu to Mashkomai Maira road,Topsin to Ganajir Top road, Chinkolai to Faqira road, Khwazakhela to Dumbara road, Swat.
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 231.52 56.924 60 58.983 58.983 36.3 93.224 114.596 51% 40%
February - 2018
length 16.2 km (units 5 ) Shalpin Jishar road - 40% completed. Topsin to Ganajir road - 40% completed. Khawza Khela to Dambara - 30% completed.
ADP's Images
PK 86, Swat
1126
(OG)
150819-F/S, Design, Construction and Widening of Shalpin to Jishar Road, Babu to Mashkomai Maira road,Topsin to Ganajir Top road, Chinkolai to Faqira road, Khwazakhela to Dumbara road, Swat.
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 231.52 56.924 60 58.983 58.983 36.3 93.224 114.596 51% 40%
January - 2018
Shalpin Jishar road - 40% completed. Topsin to Ganajir road - 40% completed. Khawza Khela to Dambara - 30% completed.