Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2021, January - 2018, February - 2021, February - 2018, March - 2021, March - 2018, April - 2021, April - 2018, May - 2018, May - 2021, June - 2018, July - 2020, July - 2017, August - 2020, August - 2017, September - 2020, September - 2017, October - 2020, October - 2017, November - 2017, December - 2020, December - 2017,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1120
(OG)
193189-Establishment of Vocational Training Centers/Institutes in Bajaur Agency, NWA and FR Kohat. (A) BOD 15/09/2017 [FDA]
FR Kohat
30-11--1 30-11--1 - 30-11--1 - 80.802 3.968 15 15 3.032 1.66 5.628 61.834 23% 7%
December - 2020
B/Wall,Bore completed. Remaining work in progress.
No Image
1120
(OG)
193189-Establishment of Vocational Training Centers/Institutes in Bajaur Agency, NWA and FR Kohat. (A) BOD 15/09/2017 [FDA]
FR Kohat
30-11--1 30-11--1 - 30-11--1 - 80.802 3.968 15 15 3.032 1.66 5.628 61.834 23% 7%
December - 2020
B/Wall,Bore completed. Remaining work in progress.
No Image
1120
(OG)
193189-Establishment of Vocational Training Centers/Institutes in Bajaur Agency, NWA and FR Kohat. (A) BOD 15/09/2017 [FDA]
FR Kohat
30-11--1 30-11--1 - 30-11--1 - 80.802 3.968 15 15 3.032 0.736 4.704 61.834 23% 6%
October - 2020
B/Wall,Bore completed. Remaining work in progress.
No Image
1120
(OG)
193189-Establishment of Vocational Training Centers/Institutes in Bajaur Agency, NWA and FR Kohat. (A) BOD 15/09/2017 [FDA]
FR Kohat
30-11--1 30-11--1 - 30-11--1 - 80.802 3.968 15 15 3.032 1.728 5.696 61.834 23% 7%
September - 2020
B/Wall,Bore completed. Remaining work in progress.
No Image
1120
(OG)
193189-Establishment of Vocational Training Centers/Institutes in Bajaur Agency, NWA and FR Kohat. (A) BOD 15/09/2017 [FDA]
FR Kohat
30-11--1 30-11--1 - 30-11--1 - 80.802 3.968 15 15 0 0 3.968 61.834 23% 5%
August - 2020
B/Wall,Bore completed. Remaining work in progress.
No Image
1120
(OG)
193189-Establishment of Vocational Training Centers/Institutes in Bajaur Agency, NWA and FR Kohat. (A) BOD 15/09/2017 [FDA]
FR Kohat
30-11--1 30-11--1 - 30-11--1 - 80.802 3.968 15 0 0 0 3.968 61.834 23% 5%
July - 2020
B/Wall,Bore completed. Remaining work in progress.
No Image
1120
(OG)
193189-Establishment of Vocational Training Centers/Institutes in Bajaur Agency, NWA and FR Kohat. (A) BOD 15/09/2017 [FDA]
FR Kohat
30-11--1 30-11--1 - 30-11--1 - 80.802 3.968 15 3.032 3.032 1.66 5.628 61.834 23% 7%
May - 2021
B/Wall,Bore completed. Remaining work in progress.
No Image
Govt. Tehcnical Insitite (Boys) Darra Adam Khel FR Kohat
1120
(OG)
193189-Establishment of Vocational Training Centers/Institutes in Bajaur Agency, NWA and FR Kohat. (A) BOD 15/09/2017 [FDA]
FR Kohat
30-11--1 30-11--1 - 30-11--1 - 80.802 3.968 15 3.032 3.032 1.66 5.628 61.834 23% 7%
April - 2021
B/Wall,Bore completed. Remaining work in progress.
No Image
Govt. Tehcnical Insitite (Boys) Darra Adam Khel FR Kohat
1120
(OG)
193189-Establishment of Vocational Training Centers/Institutes in Bajaur Agency, NWA and FR Kohat. (A) BOD 15/09/2017 [FDA]
FR Kohat
30-11--1 30-11--1 - 30-11--1 - 80.802 3.968 15 3.032 3.032 1.66 5.628 61.834 23% 7%
March - 2021
B/Wall,Bore completed. Remaining work in progress.
No Image
Govt. Tehcnical Insitite (Boys) Darra Adam Khel FR Kohat
1120
(OG)
193189-Establishment of Vocational Training Centers/Institutes in Bajaur Agency, NWA and FR Kohat. (A) BOD 15/09/2017 [FDA]
FR Kohat
30-11--1 30-11--1 - 30-11--1 - 80.802 3.968 15 3.032 3.032 1.66 5.628 61.834 23% 7%
February - 2021
B/Wall,Bore completed. Remaining work in progress.
No Image
Govt. Tehcnical Insitite (Boys) Darra Adam Khel FR Kohat
1120
(OG)
193189-Establishment of Vocational Training Centers/Institutes in Bajaur Agency, NWA and FR Kohat. (A) BOD 15/09/2017 [FDA]
FR Kohat
30-11--1 30-11--1 - 30-11--1 - 80.802 3.968 15 3.032 3.032 1.66 5.628 61.834 23% 7%
January - 2021
B/Wall,Bore completed. Remaining work in progress.
No Image
Govt. Tehcnical Insitite (Boys) Darra Adam Khel FR Kohat
1120
(OG)
193189-Establishment of Vocational Training Centers/Institutes in Bajaur Agency, NWA and FR Kohat. (A) BOD 15/09/2017 [FDA]
North Waziristan
30-11--1 30-11--1 - 30-11--1 - 38.851 23.859 15 15 0 0 23.859 0 100% 61%
December - 2020
Admn: ABC in finishing stage. B/W & Boring completed.
No Image
1120
(OG)
193189-Establishment of Vocational Training Centers/Institutes in Bajaur Agency, NWA and FR Kohat. (A) BOD 15/09/2017 [FDA]
North Waziristan
30-11--1 30-11--1 - 30-11--1 - 38.851 23.859 15 15 0 0 23.859 0 100% 61%
December - 2020
Admn: ABC in finishing stage. B/W & Boring completed.
No Image
1120
(OG)
193189-Establishment of Vocational Training Centers/Institutes in Bajaur Agency, NWA and FR Kohat. (A) BOD 15/09/2017 [FDA]
North Waziristan
30-11--1 30-11--1 - 30-11--1 - 38.851 23.859 15 15 0 0 23.859 0 100% 61%
October - 2020
Admn: ABC in finishing stage. B/W & Boring completed.
No Image
1120
(OG)
193189-Establishment of Vocational Training Centers/Institutes in Bajaur Agency, NWA and FR Kohat. (A) BOD 15/09/2017 [FDA]
North Waziristan
30-11--1 30-11--1 - 30-11--1 - 38.851 23.859 15 15 0 0 23.859 0 100% 61%
September - 2020
Admn: ABC in finishing stage. B/W & Boring completed.
No Image
1120
(OG)
193189-Establishment of Vocational Training Centers/Institutes in Bajaur Agency, NWA and FR Kohat. (A) BOD 15/09/2017 [FDA]
North Waziristan
30-11--1 30-11--1 - 30-11--1 - 38.851 23.859 15 15 0 0 23.859 0 100% 61%
August - 2020
Admn: ABC in finishing stage. B/W & Boring completed.
No Image
1120
(OG)
193189-Establishment of Vocational Training Centers/Institutes in Bajaur Agency, NWA and FR Kohat. (A) BOD 15/09/2017 [FDA]
North Waziristan
30-11--1 30-11--1 - 30-11--1 - 38.851 23.859 15 0 0 0 23.859 0 100% 61%
July - 2020
Admn: ABC in finishing stage. B/W & Boring completed.
No Image
1120
(OG)
193189-Establishment of Vocational Training Centers/Institutes in Bajaur Agency, NWA and FR Kohat. (A) BOD 15/09/2017 [FDA]
North Waziristan
30-11--1 30-11--1 - 30-11--1 - 38.851 34.043 15 0 0 0 34.043 0 100% 88%
May - 2021
Admn: ABC in finishing stage. B/W & Boring completed.
No Image
Women vocational Training Centers/Institutes in , NWA
1120
(OG)
193189-Establishment of Vocational Training Centers/Institutes in Bajaur Agency, NWA and FR Kohat. (A) BOD 15/09/2017 [FDA]
North Waziristan
30-11--1 30-11--1 - 30-11--1 - 38.851 34.043 15 0 0 0 34.043 0 100% 88%
April - 2021
Admn: ABC in finishing stage. B/W & Boring completed.
No Image
Women vocational Training Centers/Institutes in , NWA
1120
(OG)
193189-Establishment of Vocational Training Centers/Institutes in Bajaur Agency, NWA and FR Kohat. (A) BOD 15/09/2017 [FDA]
North Waziristan
30-11--1 30-11--1 - 30-11--1 - 38.851 34.043 15 0 0 0 34.043 0 100% 88%
March - 2021
Admn: ABC in finishing stage. B/W & Boring completed.
No Image
Women vocational Training Centers/Institutes in , NWA
1120
(OG)
193189-Establishment of Vocational Training Centers/Institutes in Bajaur Agency, NWA and FR Kohat. (A) BOD 15/09/2017 [FDA]
North Waziristan
30-11--1 30-11--1 - 30-11--1 - 38.851 34.043 15 0 0 0 34.043 0 100% 88%
February - 2021
Admn: ABC in finishing stage. B/W & Boring completed.
No Image
Women vocational Training Centers/Institutes in , NWA
1120
(OG)
193189-Establishment of Vocational Training Centers/Institutes in Bajaur Agency, NWA and FR Kohat. (A) BOD 15/09/2017 [FDA]
North Waziristan
30-11--1 30-11--1 - 30-11--1 - 38.851 23.859 15 0 0 0 23.859 0 100% 61%
January - 2021
Admn: ABC in finishing stage. B/W & Boring completed.
No Image
Women vocational Training Centers/Institutes in , NWA
1120
(OG)
193189-Establishment of Vocational Training Centers/Institutes in Bajaur Agency, NWA and FR Kohat. (A) BOD 15/09/2017 [FDA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 156.621 72.851 15 15 0 0 72.851 0 - -
December - 2020
No Image
1120
(OG)
193189-Establishment of Vocational Training Centers/Institutes in Bajaur Agency, NWA and FR Kohat. (A) BOD 15/09/2017 [FDA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 156.621 72.851 15 15 0 0 72.851 0 - -
December - 2020
No Image
1120
(OG)
193189-Establishment of Vocational Training Centers/Institutes in Bajaur Agency, NWA and FR Kohat. (A) BOD 15/09/2017 [FDA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 156.621 72.851 15 15 0 0 72.851 0 - -
October - 2020
No Image
1120
(OG)
193189-Establishment of Vocational Training Centers/Institutes in Bajaur Agency, NWA and FR Kohat. (A) BOD 15/09/2017 [FDA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 156.621 72.851 15 15 0 0 72.851 0 - -
September - 2020
No Image
1120
(OG)
193189-Establishment of Vocational Training Centers/Institutes in Bajaur Agency, NWA and FR Kohat. (A) BOD 15/09/2017 [FDA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 156.621 72.851 15 15 0 0 72.851 0 - -
August - 2020
No Image
1120
(OG)
193189-Establishment of Vocational Training Centers/Institutes in Bajaur Agency, NWA and FR Kohat. (A) BOD 15/09/2017 [FDA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 156.621 72.851 15 0 0 0 72.851 0
July - 2020
No Image
1120
(OG)
193189-Establishment of Vocational Training Centers/Institutes in Bajaur Agency, NWA and FR Kohat. (A) BOD 15/09/2017 [FDA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 156.621 72.851 15 15 0 0 72.851 0 - -
May - 2021
No Image
1120
(OG)
193189-Establishment of Vocational Training Centers/Institutes in Bajaur Agency, NWA and FR Kohat. (A) BOD 15/09/2017 [FDA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 156.621 72.851 15 15 0 0 72.851 0 - -
April - 2021
No Image
1120
(OG)
193189-Establishment of Vocational Training Centers/Institutes in Bajaur Agency, NWA and FR Kohat. (A) BOD 15/09/2017 [FDA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 156.621 72.851 15 15 0 0 72.851 0 - -
March - 2021
No Image
1120
(OG)
193189-Establishment of Vocational Training Centers/Institutes in Bajaur Agency, NWA and FR Kohat. (A) BOD 15/09/2017 [FDA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 156.621 72.851 15 15 0 0 72.851 0 - -
February - 2021
No Image
1120
(OG)
193189-Establishment of Vocational Training Centers/Institutes in Bajaur Agency, NWA and FR Kohat. (A) BOD 15/09/2017 [FDA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 156.621 72.851 15 15 0 0 72.851 0 - -
January - 2021
No Image
1120
(OG)
141030-Construction & Blacktopping of Manglawar to Malam Jabba Road 35 Km, District Swat.
Swat
PKHA
03-08-15 - - 28-03-17 - 1299.6 290 10 8.55 6.05 0 290 999.6 23% 22%
December - 2017
Work order issued. Contractor Mobilized
No Image
1120
(OG)
141030-Construction & Blacktopping of Manglawar to Malam Jabba Road 35 Km, District Swat.
Swat
PKHA
30-11--1 30-11--1 - 30-11--1 - 1299.6 290 10 8.55 3.5 0 290 999.6 23% 22%
November - 2017
LOA issued to contractor.
No Image
1120
(OG)
141030-Construction & Blacktopping of Manglawar to Malam Jabba Road 35 Km, District Swat.
Swat
PKHA
30-11--1 30-11--1 - 30-11--1 - 1299.6 36.507 10 10 0 0 36.507 1253.093 4% 3%
October - 2017
LOA issued to contractor.
No Image
1120
(OG)
141030-Construction & Blacktopping of Manglawar to Malam Jabba Road 35 Km, District Swat.
Swat
PKHA
03-08-15 - - 28-03-17 - 1299.6 36.507 10 10 0 0 36.507 1253.093 4% 3%
September - 2017
Road transferred to PKHA. Summary to CM regarding loan of Rs.1.6 b from BOK has been processed. Pre-qualification of contractors completed. NIT floated. Tender opened on 11/10/2017. Evaluation under process.
No Image
1120
(OG)
141030-Construction & Blacktopping of Manglawar to Malam Jabba Road 35 Km, District Swat.
Swat
PKHA
03-08-15 - - 28-03-17 - 1299.6 36.507 10 10 0 0 36.507 1253.093 4% 3%
August - 2017
Road transferred to PKHA. Summary to CM regarding loan of Rs.1.6 b from BOK has been processed. Pre-qualification of contractors completed. NIT floated. Tender invited on 20/09/2017.
No Image
1120
(OG)
141030-Construction & Blacktopping of Manglawar to Malam Jabba Road 35 Km, District Swat.
Swat
PKHA
03-08-15 - - 28-03-17 - 1299.6 36.507 10 10 3.55 0 36.507 1253.093 4% 3%
July - 2017
Road transferred to PKHA. Summary to CM regarding loan of Rs.1.6 b from BOK has been processed. Pre-qualification of contractors under process.
No Image
1120
(OG)
141030-Construction & Blacktopping of Manglawar to Malam Jabba Road 35 Km, District Swat.
Swat
PKHA
30-11--1 30-11--1 - 30-11--1 - 1299.6 161.973 10 8.55 8.55 8.55 170.523 1127.627 13% 13%
June - 2018
Embankment, sub-grade, sub-base, WBM, structure work, culvert in progress.
No Image
Package-1 (12 Km)
Package-2 (12 Km)
Package-3 (11.25 Km)
1120
(OG)
141030-Construction & Blacktopping of Manglawar to Malam Jabba Road 35 Km, District Swat.
Swat
PKHA
30-11--1 30-11--1 - 30-11--1 - 1299.6 161.973 10 10 8.55 8.55 170.523 1127.627 13% 13%
May - 2018
Embankment, sub-grade, sub-base, WBM, structure work, culvert in progress.
No Image
Package-1 (12 Km)
Package-2 (12 Km)
Package-3 (11.25 Km)
1120
(OG)
141030-Construction & Blacktopping of Manglawar to Malam Jabba Road 35 Km, District Swat.
Swat
PKHA
30-11--1 30-11--1 - 30-11--1 - 1299.6 161.973 10 10 6.05 3.55 165.523 1127.627 13% 13%
April - 2018
Embankment, sub-grade, sub-base, WBM, structure work, culvert in progress.
No Image
Package-1 (12 Km)
Package-2 (12 Km)
Package-3 (11.25 Km)
1120
(OG)
141030-Construction & Blacktopping of Manglawar to Malam Jabba Road 35 Km, District Swat.
Swat
PKHA
30-11--1 30-11--1 - 30-11--1 - 1299.6 161.973 10 10 3.55 3.55 165.523 1127.627 13% 13%
March - 2018
Embankment, sub-grade, sub-base, WBM, structure work, culvert in progress.
No Image
Package-1 (12 Km)
Package-2 (12 Km)
Package-3 (11.25 Km)
1120
(OG)
141030-Construction & Blacktopping of Manglawar to Malam Jabba Road 35 Km, District Swat.
Swat
PKHA
30-11--1 30-11--1 - 30-11--1 - 1299.6 161.973 10 10 3.55 3.55 165.523 1127.627 13% 13%
February - 2018
Work order issued. Contractors mobilized.
No Image
Package-1
Package-2
Package-3
1120
(OG)
141030-Construction & Blacktopping of Manglawar to Malam Jabba Road 35 Km, District Swat.
Swat
PKHA
30-11--1 30-11--1 - 30-11--1 - 1299.6 290 10 8.55 6.05 0 290 999.6 23% 22%
January - 2018
Work order issued. Contractors mobilized.
No Image
Package-1 Package-2 Package-3
Pages : 1