Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1110 (New) |
190257-Construction of Sports stadium Tamergara at Dir Lower. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 150 | 0 | 15 | 15 | 0.633 | 0.633 | 0.633 | 0 | - |
- December - 2019 |
Site/scope awaited. |
No Image |
1110 (New) |
190257-Construction of Sports stadium Tamergara at Dir Lower. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 150 | 0 | 15 | 15 | 0.633 | 0.633 | 0.633 | 0 | - |
- November - 2019 |
Site/scope awaited. |
No Image |
1110 (New) |
190257-Construction of Sports stadium Tamergara at Dir Lower. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 150 | 0 | 15 | 15 | 0 | 0 | 0 | 0 | - |
- October - 2019 |
Site/scope awaited. |
No Image |
1110 (New) |
190257-Construction of Sports stadium Tamergara at Dir Lower. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 150 | 0 | 15 | 15 | 0 | 0 | 0 | 0 | - |
- September - 2019 |
Site/scope awaited. |
No Image |
1110 (New) |
190257-Construction of Sports stadium Tamergara at Dir Lower. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 150 | 0 | 15 | 15 | 0 | 0 | 0 | 0 | - |
- August - 2019 |
Site/scope awaited. |
No Image |
1110 (New) |
190257-Construction of Sports stadium Tamergara at Dir Lower. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 150 | 0 | 15 | 15 | 0.633 | 0.633 | 0.633 | 0 | - |
- May - 2020 |
Site/scope awaited. |
No Image |
1110 (New) |
190257-Construction of Sports stadium Tamergara at Dir Lower. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 150 | 0 | 15 | 15 | 0.633 | 0.633 | 0.633 | 0 | - |
- April - 2020 |
Site/scope awaited. |
No Image |
1110 (New) |
190257-Construction of Sports stadium Tamergara at Dir Lower. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 150 | 0 | 15 | 15 | 0.633 | 0.633 | 0.633 | 0 | - |
- March - 2020 |
Site/scope awaited. |
No Image |
1110 (New) |
190257-Construction of Sports stadium Tamergara at Dir Lower. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 150 | 0 | 15 | 15 | 0.633 | 0.633 | 0.633 | 0 | - |
- February - 2020 |
Site/scope awaited. |
No Image |
1110 (New) |
190257-Construction of Sports stadium Tamergara at Dir Lower. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 150 | 0 | 15 | 15 | 0.633 | 0.633 | 0.633 | 0 | - |
- January - 2020 |
Site/scope awaited. |
No Image |
1110 (OG) |
193152-FATA Youth Skills programme in Health courses (Phase-II) (A) BOD/25/5/2017 [FDA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 113.283 | 56.412 | 0 | 0 | 0 | 0 | 56.412 | 0 | - |
- December - 2020 |
No Image | |
1110 (OG) |
193152-FATA Youth Skills programme in Health courses (Phase-II) (A) BOD/25/5/2017 [FDA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 113.283 | 56.412 | 0 | 0 | 0 | 0 | 56.412 | 0 | - |
- December - 2020 |
No Image | |
1110 (OG) |
193152-FATA Youth Skills programme in Health courses (Phase-II) (A) BOD/25/5/2017 [FDA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 113.283 | 56.412 | 0 | 0 | 0 | 0 | 56.412 | 0 | - |
- October - 2020 |
No Image | |
1110 (OG) |
193152-FATA Youth Skills programme in Health courses (Phase-II) (A) BOD/25/5/2017 [FDA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 113.283 | 56.412 | 0 | 0 | 0 | 0 | 56.412 | 0 | - |
- September - 2020 |
No Image | |
1110 (OG) |
193152-FATA Youth Skills programme in Health courses (Phase-II) (A) BOD/25/5/2017 [FDA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 113.283 | 56.412 | 0 | 0 | 0 | 0 | 56.412 | 0 | - |
- August - 2020 |
No Image | |
1110 (OG) |
193152-FATA Youth Skills programme in Health courses (Phase-II) (A) BOD/25/5/2017 [FDA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 113.283 | 56.412 | 0 | 0 | 0 | 0 | 56.412 | 0 | - |
July - 2020 |
No Image | |
1110 (OG) |
193152-FATA Youth Skills programme in Health courses (Phase-II) (A) BOD/25/5/2017 [FDA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 113.283 | 56.412 | 0 | 0 | 0 | 0 | 56.412 | 0 | - |
- May - 2021 |
No Image | |
1110 (OG) |
193152-FATA Youth Skills programme in Health courses (Phase-II) (A) BOD/25/5/2017 [FDA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 113.283 | 56.412 | 0 | 0 | 0 | 0 | 56.412 | 0 | - |
- April - 2021 |
No Image | |
1110 (OG) |
193152-FATA Youth Skills programme in Health courses (Phase-II) (A) BOD/25/5/2017 [FDA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 113.283 | 56.412 | 0 | 0 | 0 | 0 | 56.412 | 0 | - |
- March - 2021 |
No Image | |
1110 (OG) |
193152-FATA Youth Skills programme in Health courses (Phase-II) (A) BOD/25/5/2017 [FDA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 113.283 | 56.412 | 0 | 0 | 0 | 0 | 56.412 | 0 | - |
- February - 2021 |
No Image | |
1110 (OG) |
193152-FATA Youth Skills programme in Health courses (Phase-II) (A) BOD/25/5/2017 [FDA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 113.283 | 56.412 | 0 | 0 | 0 | 0 | 56.412 | 0 | - |
- January - 2021 |
No Image | |
1110 (OG) |
150821-Construction and Rehabilitation of Biana Machkandi road, Gear Chagharzai Road, Begai Towa and Mandoria Road, District Shangla. |
Shangla |
- | - | - | 02-11-15 | - | 148.761 | 45.544 | 10 | 9.65 | 7.15 | 7.15 | 52.694 | 93.217 | 37% |
35% December - 2017 |
Length 14.1 Km - 4 units - all earth work in progress. |
No Image |
Namenclature changed. | |||||||||||||||||||
1110 (OG) |
150821-Construction and Rehabilitation of Biana Machkandi road, Gear Chagharzai Road, Begai Towa and Mandoria Road, District Shangla. |
Shangla |
- | - | - | 02-11-15 | - | 148.761 | 45.544 | 10 | 10 | 4.65 | 4.65 | 50.194 | 93.217 | 37% |
34% September - 2017 |
Length 14.1 Km - 4 units - all earth work in progress. |
No Image |
Namenclature changed. | |||||||||||||||||||
1110 (OG) |
150821-Construction and Rehabilitation of Biana Machkandi road, Gear Chagharzai Road, Begai Towa and Mandoria Road, District Shangla. |
Shangla |
- | - | - | 02-11-15 | - | 148.761 | 45.544 | 10 | 10 | 4.65 | 4.65 | 50.194 | 93.217 | 37% |
34% August - 2017 |
Length 14.1 Km - 4 units - all earth work in progress. |
No Image |
Namenclature changed. | |||||||||||||||||||
1110 (OG) |
150821-Construction and Rehabilitation of Biana Machkandi road, Gear Chagharzai Road, Begai Towa and Mandoria Road, District Shangla. |
Shangla |
- | - | - | 02-11-15 | - | 148.761 | 45.544 | 10 | 10 | 4.65 | 0 | 45.544 | 93.217 | 37% |
31% July - 2017 |
Length 14.1 Km - 4 units - all earth work in progress. |
No Image |
Namenclature changed. | |||||||||||||||||||
1110 (OG) |
150821-Construction and Rehabilitation of Biana Machkandi road, Gear Chagharzai Road, Begai Towa and Mandoria Road, District Shangla. |
Shangla |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 148.761 | 45.544 | 10 | 9.65 | 7.15 | 7.15 | 52.694 | 93.217 | 37% |
35% November - 2017 |
Length 14.1 Km - 4 units - all earth work in progress. |
No Image |
Namenclature changed. | |||||||||||||||||||
1110 (OG) |
150821-Construction and Rehabilitation of Biana Machkandi road, Gear Chagharzai Road, Begai Towa and Mandoria Road, District Shangla. |
Shangla |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 148.761 | 45.544 | 10 | 10 | 7.15 | 4.65 | 50.194 | 93.217 | 37% |
34% October - 2017 |
Length 14.1 Km - 4 units - all earth work in progress. |
No Image |
Namenclature changed. | |||||||||||||||||||
1110 (OG) |
150821-Construction and Rehabilitation of Biana Machkandi road, Gear Chagharzai Road, Begai Towa and Mandoria Road, District Shangla. |
Shangla |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 148.761 | 45.549 | 10 | 21.303 | 21.303 | 21.303 | 66.852 | 93.212 | 37% |
45% June - 2018 |
Length 14.1 Km (width 18 ft) - 4 units - all earth work in progress. |
No Image |
1) Peshloor road (2 Km)
2) Gear Chagarzai road (2.25 Km)
3) Mandoraia road Shangla (7.25 Km)
4) Baina road (2 Km) | |||||||||||||||||||
1110 (OG) |
150821-Construction and Rehabilitation of Biana Machkandi road, Gear Chagharzai Road, Begai Towa and Mandoria Road, District Shangla. |
Shangla |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 148.761 | 45.549 | 10 | 21.303 | 21.303 | 21.303 | 66.852 | 93.212 | 37% |
45% May - 2018 |
Length 14.1 Km (width 18 ft) - 4 units - all earth work in progress. |
No Image |
1) Peshloor road (2 Km)
2) Gear Chagarzai road (2.25 Km)
3) Mandoraia road Shangla (7.25 Km)
4) Baina road (2 Km) | |||||||||||||||||||
1110 (OG) |
150821-Construction and Rehabilitation of Biana Machkandi road, Gear Chagharzai Road, Begai Towa and Mandoria Road, District Shangla. |
Shangla |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 148.761 | 45.549 | 10 | 21.303 | 21.303 | 21.303 | 66.852 | 93.212 | 37% |
45% April - 2018 |
Length 14.1 Km (width 18 ft) - 4 units - all earth work in progress. |
No Image |
1) Peshloor road (2 Km)
2) Gear Chagarzai road (2.25 Km)
3) Mandoraia road Shangla (7.25 Km)
4) Baina road (2 Km) | |||||||||||||||||||
1110 (OG) |
150821-Construction and Rehabilitation of Biana Machkandi road, Gear Chagharzai Road, Begai Towa and Mandoria Road, District Shangla. |
Shangla |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 148.761 | 45.549 | 10 | 21.303 | 21.303 | 21.303 | 66.852 | 93.212 | 37% |
45% March - 2018 |
Length 14.1 Km (width 18 ft ) - 4 units - all earth work in progress. |
No Image |
1) Peshloor road (2 Km)
2) Gear Chagarzai road (2.25 Km)
3) Mandoraia road Shangla (7.25 Km)
4) Baina road (2 Km) | |||||||||||||||||||
1110 (OG) |
150821-Construction and Rehabilitation of Biana Machkandi road, Gear Chagharzai Road, Begai Towa and Mandoria Road, District Shangla. |
Shangla |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 148.761 | 45.549 | 10 | 18.613 | 18.613 | 14.813 | 60.362 | 93.212 | 37% |
41% February - 2018 |
Length 14.1 Km (width 18 ft ) - 4 units - all earth work in progress. |
ADP's Images |
Namenclature changed. | |||||||||||||||||||
1110 (OG) |
150821-Construction and Rehabilitation of Biana Machkandi road, Gear Chagharzai Road, Begai Towa and Mandoria Road, District Shangla. |
Shangla |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 148.761 | 45.544 | 10 | 18.613 | 18.613 | 7.15 | 52.694 | 93.217 | 37% |
35% January - 2018 |
Length 14.1 Km - 4 units - all earth work in progress. |
No Image |
Namenclature changed. | |||||||||||||||||||