Progressive Review for the month(s) of : January - 2018, January - 2020, January - 2021, February - 2018, February - 2020, February - 2021, March - 2018, March - 2020, March - 2021, April - 2018, April - 2020, April - 2021, May - 2018, May - 2020, May - 2021, June - 2018, July - 2020, July - 2017, August - 2019, August - 2020, August - 2017, September - 2019, September - 2020, September - 2017, October - 2017, October - 2019, October - 2020, November - 2017, November - 2019, December - 2019, December - 2020, December - 2017,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1110
(New)
190257-Construction of Sports stadium Tamergara at Dir Lower.
Dir Lower
30-11--1 30-11--1 - 30-11--1 Line Deptt 150 0 15 15 0.633 0.633 0.633 0 - -
December - 2019
Site/scope awaited.
No Image
1110
(New)
190257-Construction of Sports stadium Tamergara at Dir Lower.
Dir Lower
30-11--1 30-11--1 - 30-11--1 Line Deptt 150 0 15 15 0.633 0.633 0.633 0 - -
November - 2019
Site/scope awaited.
No Image
1110
(New)
190257-Construction of Sports stadium Tamergara at Dir Lower.
Dir Lower
30-11--1 30-11--1 - 30-11--1 Line Deptt 150 0 15 15 0 0 0 0 - -
October - 2019
Site/scope awaited.
No Image
1110
(New)
190257-Construction of Sports stadium Tamergara at Dir Lower.
Dir Lower
30-11--1 30-11--1 - 30-11--1 Line Deptt 150 0 15 15 0 0 0 0 - -
September - 2019
Site/scope awaited.
No Image
1110
(New)
190257-Construction of Sports stadium Tamergara at Dir Lower.
Dir Lower
30-11--1 30-11--1 - 30-11--1 Line Deptt 150 0 15 15 0 0 0 0 - -
August - 2019
Site/scope awaited.
No Image
1110
(New)
190257-Construction of Sports stadium Tamergara at Dir Lower.
Dir Lower
30-11--1 30-11--1 - 30-11--1 Line Deptt 150 0 15 15 0.633 0.633 0.633 0 - -
May - 2020
Site/scope awaited.
No Image
1110
(New)
190257-Construction of Sports stadium Tamergara at Dir Lower.
Dir Lower
30-11--1 30-11--1 - 30-11--1 Line Deptt 150 0 15 15 0.633 0.633 0.633 0 - -
April - 2020
Site/scope awaited.
No Image
1110
(New)
190257-Construction of Sports stadium Tamergara at Dir Lower.
Dir Lower
30-11--1 30-11--1 - 30-11--1 Line Deptt 150 0 15 15 0.633 0.633 0.633 0 - -
March - 2020
Site/scope awaited.
No Image
1110
(New)
190257-Construction of Sports stadium Tamergara at Dir Lower.
Dir Lower
30-11--1 30-11--1 - 30-11--1 Line Deptt 150 0 15 15 0.633 0.633 0.633 0 - -
February - 2020
Site/scope awaited.
No Image
1110
(New)
190257-Construction of Sports stadium Tamergara at Dir Lower.
Dir Lower
30-11--1 30-11--1 - 30-11--1 Line Deptt 150 0 15 15 0.633 0.633 0.633 0 - -
January - 2020
Site/scope awaited.
No Image
1110
(OG)
193152-FATA Youth Skills programme in Health courses (Phase-II) (A) BOD/25/5/2017 [FDA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 113.283 56.412 0 0 0 0 56.412 0 - -
December - 2020
No Image
1110
(OG)
193152-FATA Youth Skills programme in Health courses (Phase-II) (A) BOD/25/5/2017 [FDA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 113.283 56.412 0 0 0 0 56.412 0 - -
December - 2020
No Image
1110
(OG)
193152-FATA Youth Skills programme in Health courses (Phase-II) (A) BOD/25/5/2017 [FDA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 113.283 56.412 0 0 0 0 56.412 0 - -
October - 2020
No Image
1110
(OG)
193152-FATA Youth Skills programme in Health courses (Phase-II) (A) BOD/25/5/2017 [FDA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 113.283 56.412 0 0 0 0 56.412 0 - -
September - 2020
No Image
1110
(OG)
193152-FATA Youth Skills programme in Health courses (Phase-II) (A) BOD/25/5/2017 [FDA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 113.283 56.412 0 0 0 0 56.412 0 - -
August - 2020
No Image
1110
(OG)
193152-FATA Youth Skills programme in Health courses (Phase-II) (A) BOD/25/5/2017 [FDA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 113.283 56.412 0 0 0 0 56.412 0 -
July - 2020
No Image
1110
(OG)
193152-FATA Youth Skills programme in Health courses (Phase-II) (A) BOD/25/5/2017 [FDA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 113.283 56.412 0 0 0 0 56.412 0 - -
May - 2021
No Image
1110
(OG)
193152-FATA Youth Skills programme in Health courses (Phase-II) (A) BOD/25/5/2017 [FDA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 113.283 56.412 0 0 0 0 56.412 0 - -
April - 2021
No Image
1110
(OG)
193152-FATA Youth Skills programme in Health courses (Phase-II) (A) BOD/25/5/2017 [FDA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 113.283 56.412 0 0 0 0 56.412 0 - -
March - 2021
No Image
1110
(OG)
193152-FATA Youth Skills programme in Health courses (Phase-II) (A) BOD/25/5/2017 [FDA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 113.283 56.412 0 0 0 0 56.412 0 - -
February - 2021
No Image
1110
(OG)
193152-FATA Youth Skills programme in Health courses (Phase-II) (A) BOD/25/5/2017 [FDA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 113.283 56.412 0 0 0 0 56.412 0 - -
January - 2021
No Image
1110
(OG)
150821-Construction and Rehabilitation of Biana Machkandi road, Gear Chagharzai Road, Begai Towa and Mandoria Road, District Shangla.
Shangla
- - - 02-11-15 - 148.761 45.544 10 9.65 7.15 7.15 52.694 93.217 37% 35%
December - 2017
Length 14.1 Km - 4 units - all earth work in progress.
No Image
Namenclature changed.
1110
(OG)
150821-Construction and Rehabilitation of Biana Machkandi road, Gear Chagharzai Road, Begai Towa and Mandoria Road, District Shangla.
Shangla
- - - 02-11-15 - 148.761 45.544 10 10 4.65 4.65 50.194 93.217 37% 34%
September - 2017
Length 14.1 Km - 4 units - all earth work in progress.
No Image
Namenclature changed.
1110
(OG)
150821-Construction and Rehabilitation of Biana Machkandi road, Gear Chagharzai Road, Begai Towa and Mandoria Road, District Shangla.
Shangla
- - - 02-11-15 - 148.761 45.544 10 10 4.65 4.65 50.194 93.217 37% 34%
August - 2017
Length 14.1 Km - 4 units - all earth work in progress.
No Image
Namenclature changed.
1110
(OG)
150821-Construction and Rehabilitation of Biana Machkandi road, Gear Chagharzai Road, Begai Towa and Mandoria Road, District Shangla.
Shangla
- - - 02-11-15 - 148.761 45.544 10 10 4.65 0 45.544 93.217 37% 31%
July - 2017
Length 14.1 Km - 4 units - all earth work in progress.
No Image
Namenclature changed.
1110
(OG)
150821-Construction and Rehabilitation of Biana Machkandi road, Gear Chagharzai Road, Begai Towa and Mandoria Road, District Shangla.
Shangla
30-11--1 30-11--1 - 30-11--1 - 148.761 45.544 10 9.65 7.15 7.15 52.694 93.217 37% 35%
November - 2017
Length 14.1 Km - 4 units - all earth work in progress.
No Image
Namenclature changed.
1110
(OG)
150821-Construction and Rehabilitation of Biana Machkandi road, Gear Chagharzai Road, Begai Towa and Mandoria Road, District Shangla.
Shangla
30-11--1 30-11--1 - 30-11--1 - 148.761 45.544 10 10 7.15 4.65 50.194 93.217 37% 34%
October - 2017
Length 14.1 Km - 4 units - all earth work in progress.
No Image
Namenclature changed.
1110
(OG)
150821-Construction and Rehabilitation of Biana Machkandi road, Gear Chagharzai Road, Begai Towa and Mandoria Road, District Shangla.
Shangla
30-11--1 30-11--1 - 30-11--1 - 148.761 45.549 10 21.303 21.303 21.303 66.852 93.212 37% 45%
June - 2018
Length 14.1 Km (width 18 ft) - 4 units - all earth work in progress.
No Image
1) Peshloor road (2 Km)
2) Gear Chagarzai road (2.25 Km)
3) Mandoraia road Shangla (7.25 Km)
4) Baina road (2 Km)
1110
(OG)
150821-Construction and Rehabilitation of Biana Machkandi road, Gear Chagharzai Road, Begai Towa and Mandoria Road, District Shangla.
Shangla
30-11--1 30-11--1 - 30-11--1 - 148.761 45.549 10 21.303 21.303 21.303 66.852 93.212 37% 45%
May - 2018
Length 14.1 Km (width 18 ft) - 4 units - all earth work in progress.
No Image
1) Peshloor road (2 Km)
2) Gear Chagarzai road (2.25 Km)
3) Mandoraia road Shangla (7.25 Km)
4) Baina road (2 Km)
1110
(OG)
150821-Construction and Rehabilitation of Biana Machkandi road, Gear Chagharzai Road, Begai Towa and Mandoria Road, District Shangla.
Shangla
30-11--1 30-11--1 - 30-11--1 - 148.761 45.549 10 21.303 21.303 21.303 66.852 93.212 37% 45%
April - 2018
Length 14.1 Km (width 18 ft) - 4 units - all earth work in progress.
No Image
1) Peshloor road (2 Km)
2) Gear Chagarzai road (2.25 Km)
3) Mandoraia road Shangla (7.25 Km)
4) Baina road (2 Km)
1110
(OG)
150821-Construction and Rehabilitation of Biana Machkandi road, Gear Chagharzai Road, Begai Towa and Mandoria Road, District Shangla.
Shangla
30-11--1 30-11--1 - 30-11--1 - 148.761 45.549 10 21.303 21.303 21.303 66.852 93.212 37% 45%
March - 2018
Length 14.1 Km (width 18 ft ) - 4 units - all earth work in progress.
No Image
1) Peshloor road (2 Km)
2) Gear Chagarzai road (2.25 Km)
3) Mandoraia road Shangla (7.25 Km)
4) Baina road (2 Km)
1110
(OG)
150821-Construction and Rehabilitation of Biana Machkandi road, Gear Chagharzai Road, Begai Towa and Mandoria Road, District Shangla.
Shangla
30-11--1 30-11--1 - 30-11--1 - 148.761 45.549 10 18.613 18.613 14.813 60.362 93.212 37% 41%
February - 2018
Length 14.1 Km (width 18 ft ) - 4 units - all earth work in progress.
ADP's Images
Namenclature changed.
1110
(OG)
150821-Construction and Rehabilitation of Biana Machkandi road, Gear Chagharzai Road, Begai Towa and Mandoria Road, District Shangla.
Shangla
30-11--1 30-11--1 - 30-11--1 - 148.761 45.544 10 18.613 18.613 7.15 52.694 93.217 37% 35%
January - 2018
Length 14.1 Km - 4 units - all earth work in progress.
No Image
Namenclature changed.