Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1102 (OG) |
191595-140082 - Establishment of Govt Poly Technic Institute Bar Muhammad Khel Kalaya Lower Orakzai Agency. [MA] |
Orakzai |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 192.665 | 175.415 | 9.5 | 9.5 | 0 | 0 | 175.415 | 7.75 | 96% |
91% December - 2020 |
MB Ist Floor Roof ceiling in progress. Tube Well boring completed. Admn Block finishing in progress. Mining workshop finishing in progress. |
No Image |
1102 (OG) |
191595-140082 - Establishment of Govt Poly Technic Institute Bar Muhammad Khel Kalaya Lower Orakzai Agency. [MA] |
Orakzai |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 192.665 | 175.415 | 9.5 | 9.5 | 0 | 0 | 175.415 | 7.75 | 96% |
91% December - 2020 |
MB Ist Floor Roof ceiling in progress. Tube Well boring completed. Admn Block finishing in progress. Mining workshop finishing in progress. |
No Image |
1102 (OG) |
191595-140082 - Establishment of Govt Poly Technic Institute Bar Muhammad Khel Kalaya Lower Orakzai Agency. [MA] |
Orakzai |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 192.665 | 175.415 | 9.5 | 9.5 | 0 | 0 | 175.415 | 7.75 | 96% |
91% October - 2020 |
MB Ist Floor Roof ceiling in progress. Tube Well boring completed. Admn Block finishing in progress. Mining workshop finishing in progress. |
No Image |
1102 (OG) |
191595-140082 - Establishment of Govt Poly Technic Institute Bar Muhammad Khel Kalaya Lower Orakzai Agency. [MA] |
Orakzai |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 192.665 | 175.415 | 9.5 | 9.5 | 0 | 0 | 175.415 | 7.75 | 96% |
91% September - 2020 |
MB Ist Floor Roof ceiling in progress. Tube Well boring completed. Admn Block finishing in progress. Mining workshop finishing in progress. |
No Image |
1102 (OG) |
191595-140082 - Establishment of Govt Poly Technic Institute Bar Muhammad Khel Kalaya Lower Orakzai Agency. [MA] |
Orakzai |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 192.665 | 175.415 | 9.5 | 9.5 | 0 | 0 | 175.415 | 7.75 | 96% |
91% August - 2020 |
MB Ist Floor Roof ceiling in progress. Tube Well boring completed. Admn Block finishing in progress. Mining workshop finishing in progress. |
No Image |
1102 (OG) |
191595-140082 - Establishment of Govt Poly Technic Institute Bar Muhammad Khel Kalaya Lower Orakzai Agency. [MA] |
Orakzai |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 192.665 | 183.165 | 9.5 | 0 | 0 | 0 | 183.165 | 0 |
July - 2020 |
No Image | ||
1102 (OG) |
191595-140082 - Establishment of Govt Poly Technic Institute Bar Muhammad Khel Kalaya Lower Orakzai Agency. [MA] |
Orakzai |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 192.665 | 175.415 | 9.5 | 0 | 0 | 0 | 175.415 | 7.75 | 96% |
91% May - 2021 |
01- Unit
MB Ist Floor Roof ceiling in progress. Tube Well boring completed. Admn Block finishing in progress. Mining workshop finishing in progress. |
No Image |
Mian Building
Work Shops
Residential Portion
Type IV Qtrs 2 Nos
Type V Qtrs 2 Nos
Dev: work
Land 77 Kanal | |||||||||||||||||||
1102 (OG) |
191595-140082 - Establishment of Govt Poly Technic Institute Bar Muhammad Khel Kalaya Lower Orakzai Agency. [MA] |
Orakzai |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 192.665 | 175.415 | 9.5 | 0 | 0 | 0 | 175.415 | 7.75 | 96% |
91% April - 2021 |
MB Ist Floor Roof ceiling in progress. Tube Well boring completed. Admn Block finishing in progress. Mining workshop finishing in progress. |
No Image |
Mian Building
Work Shops
Residential Portion
Type IV Qtrs 2 Nos
Type V Qtrs 2 Nos
Dev: work
Land 77 Kanal | |||||||||||||||||||
1102 (OG) |
191595-140082 - Establishment of Govt Poly Technic Institute Bar Muhammad Khel Kalaya Lower Orakzai Agency. [MA] |
Orakzai |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 192.665 | 175.415 | 9.5 | 0 | 0 | 0 | 175.415 | 7.75 | 96% |
91% March - 2021 |
MB Ist Floor Roof ceiling in progress. Tube Well boring completed. Admn Block finishing in progress. Mining workshop finishing in progress. |
No Image |
Mian Building
Work Shops
Residential Portion
Type IV Qtrs 2 Nos
Type V Qtrs 2 Nos
Dev: work
Land 77 Kanal | |||||||||||||||||||
1102 (OG) |
191595-140082 - Establishment of Govt Poly Technic Institute Bar Muhammad Khel Kalaya Lower Orakzai Agency. [MA] |
Orakzai |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 192.665 | 175.415 | 9.5 | 0 | 0 | 0 | 175.415 | 7.75 | 96% |
91% February - 2021 |
MB Ist Floor Roof ceiling in progress. Tube Well boring completed. Admn Block finishing in progress. Mining workshop finishing in progress. |
No Image |
Mian Building
Work Shops
Residential Portion
Type IV Qtrs 2 Nos
Type V Qtrs 2 Nos
Dev: work
Land 77 Kanal | |||||||||||||||||||
1102 (OG) |
191595-140082 - Establishment of Govt Poly Technic Institute Bar Muhammad Khel Kalaya Lower Orakzai Agency. [MA] |
Orakzai |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 192.665 | 175.415 | 9.5 | 0 | 0 | 0 | 175.415 | 7.75 | 96% |
91% January - 2021 |
MB Ist Floor Roof ceiling in progress. Tube Well boring completed. Admn Block finishing in progress. Mining workshop finishing in progress. |
No Image |
Orakzai | |||||||||||||||||||
1102 (OG) |
130556-Improvement / construction of 8 Km road from Kirai to Mole Sar, Tehsil Besham District Shangla. |
Shangla |
- | - | - | - | - | 91.144 | 17.962 | 20 | 20 | 10 | 5.6 | 23.562 | 53.182 | 42% |
26% December - 2017 |
Length 4 Km - earth work 90% completed base Course upto 2 Km. SW started. |
No Image |
1) Kirai to Mole Sar road (4 Km) | |||||||||||||||||||
1102 (OG) |
130556-Improvement / construction of 8 Km road from Kirai to Mole Sar, Tehsil Besham District Shangla. |
Shangla |
- | - | - | - | - | 91.144 | 17.962 | 20 | 20 | 10 | 2.224 | 20.186 | 53.182 | 42% |
22% September - 2017 |
Length 4 Km - earth work 90% completed upto 3 Km. SW started. |
No Image |
1) Kirai to Mole Sar road (4 Km) | |||||||||||||||||||
1102 (OG) |
130556-Improvement / construction of 8 Km road from Kirai to Mole Sar, Tehsil Besham District Shangla. |
Shangla |
- | - | - | - | - | 91.144 | 17.962 | 20 | 20 | 10 | 0 | 17.962 | 53.182 | 42% |
20% August - 2017 |
Length 4 Km - earth work 90% completed upto 3 Km. SW started. |
No Image |
1) Kirai to Mole Sar road (4 Km) | |||||||||||||||||||
1102 (OG) |
130556-Improvement / construction of 8 Km road from Kirai to Mole Sar, Tehsil Besham District Shangla. |
Shangla |
- | - | - | - | - | 91.144 | 17.962 | 20 | 20 | 10 | 0 | 17.962 | 53.182 | 42% |
20% July - 2017 |
Length 4 Km - earth work 90% completed upto 3 Km. SW started. |
No Image |
1) Kirai to Mole Sar road (4 Km) | |||||||||||||||||||
1102 (OG) |
130556-Improvement / construction of 8 Km road from Kirai to Mole Sar, Tehsil Besham District Shangla. |
Shangla |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 91.144 | 17.962 | 20 | 20 | 10 | 5.6 | 23.562 | 53.182 | 42% |
26% November - 2017 |
Length 4 Km - earth work 90% completed base Course upto 2 Km. SW started. |
No Image |
1) Kirai to Mole Sar road (4 Km) | |||||||||||||||||||
1102 (OG) |
130556-Improvement / construction of 8 Km road from Kirai to Mole Sar, Tehsil Besham District Shangla. |
Shangla |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 91.144 | 17.962 | 20 | 20 | 10 | 2.224 | 20.186 | 53.182 | 42% |
22% October - 2017 |
Length 4 Km - earth work 90% completed base Course upto 2 Km. SW started. |
No Image |
1) Kirai to Mole Sar road (4 Km) | |||||||||||||||||||
1102 (OG) |
130556-Improvement / construction of 8 Km road from Kirai to Mole Sar, Tehsil Besham District Shangla. |
Shangla |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 91.144 | 17.962 | 20 | 9.197 | 9.197 | 7.259 | 25.221 | 53.182 | 42% |
28% June - 2018 |
Length 4 Km - earth work 90% completed base Course upto 2 Km. SW started. Revised DCE approved in PDWP subject to the approval of summary from CA for change in nomenclature. |
No Image |
Kirai to Mole Sar road (4 Km) Shangla (width 12 ft) | |||||||||||||||||||
1102 (OG) |
130556-Improvement / construction of 8 Km road from Kirai to Mole Sar, Tehsil Besham District Shangla. |
Shangla |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 91.144 | 17.962 | 20 | 25.251 | 25.251 | 5.197 | 23.159 | 53.182 | 42% |
25% May - 2018 |
Length 4 Km - earth work 90% completed base Course upto 2 Km. SW started. Revised DCE approved in PDWP subject to the approval of summary from CA for Cahnge in nomenclature. |
No Image |
Kirai to Mole Sar road (4 Km) Shangla (width 12 ft) | |||||||||||||||||||
1102 (OG) |
130556-Improvement / construction of 8 Km road from Kirai to Mole Sar, Tehsil Besham District Shangla. |
Shangla |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 91.144 | 17.962 | 20 | 25.251 | 25.251 | 5.6 | 23.562 | 53.182 | 42% |
26% April - 2018 |
Length 4 Km - earth work 90% completed base Course upto 2 Km. SW started. |
No Image |
Kirai to Mole Sar road (4 Km) Shangla (width 12 ft) | |||||||||||||||||||
1102 (OG) |
130556-Improvement / construction of 8 Km road from Kirai to Mole Sar, Tehsil Besham District Shangla. |
Shangla |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 91.144 | 17.962 | 20 | 25.251 | 25.251 | 5.6 | 23.562 | 53.182 | 42% |
26% March - 2018 |
Length 4 Km - earth work 90% completed base Course upto 2 Km. SW started. |
No Image |
Kirai to Mole Sar road (4 Km) Shangla (width 12 ft) | |||||||||||||||||||
1102 (OG) |
130556-Improvement / construction of 8 Km road from Kirai to Mole Sar, Tehsil Besham District Shangla. |
Shangla |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 91.144 | 17.962 | 20 | 22.561 | 22.561 | 5.6 | 23.562 | 53.182 | 42% |
26% February - 2018 |
Length 4 Km - earth work 90% completed base Course upto 2 Km. SW started. |
ADP's Images |
1) Kirai to Mole Sar road (4 Km) width 12 ft | |||||||||||||||||||
1102 (OG) |
130556-Improvement / construction of 8 Km road from Kirai to Mole Sar, Tehsil Besham District Shangla. |
Shangla |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 91.144 | 17.962 | 20 | 22.561 | 22.561 | 5.6 | 23.562 | 53.182 | 42% |
26% January - 2018 |
Length 4 Km - earth work 90% completed base Course upto 2 Km. SW started. |
No Image |
1) Kirai to Mole Sar road (4 Km) | |||||||||||||||||||