Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1085 (OG) |
150976-Construction of road from Miskeen Abad Jalala to Jewar via Gulpur Killi Distt Mardan. |
Mardan HW |
- | - | - | 10-09-15 | - | 75 | 9.5 | 10 | 17 | 17 | 17 | 26.5 | 55.5 | 26% |
35% December - 2017 |
Length 5.5 Km - sub base 1.5 Km, RW 2 Km, drain 1000 mtr completed. |
No Image |
1085 (OG) |
150976-Construction of road from Miskeen Abad Jalala to Jewar via Gulpur Killi Distt Mardan. |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 75 | 9.5 | 10 | 17 | 17 | 17 | 26.5 | 55.5 | 26% |
35% November - 2017 |
Length 5.5 Km - sub base 1.5 Km, RW 2 Km, drain 1000 mtr completed. |
No Image |
1085 (OG) |
150976-Construction of road from Miskeen Abad Jalala to Jewar via Gulpur Killi Distt Mardan. |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 75 | 9.5 | 10 | 13.95 | 13.2 | 13.2 | 22.7 | 55.5 | 26% |
30% October - 2017 |
Length 5.5 Km - sub base 1.5 Km, RW 2 Km, drain 1000 mtr completed. |
No Image |
1085 (OG) |
150976-Construction of road from Miskeen Abad Jalala to Jewar via Gulpur Killi Distt Mardan. |
Mardan HW |
- | - | - | 10-09-15 | - | 75 | 9.5 | 10 | 10 | 3.7 | 3.7 | 13.2 | 55.5 | 26% |
18% September - 2017 |
Length 5.5 Km - sub base 1.5 Km, RW 2 Km, drain 1000 mtr completed. |
No Image |
1085 (OG) |
150976-Construction of road from Miskeen Abad Jalala to Jewar via Gulpur Killi Distt Mardan. |
Mardan HW |
- | - | - | 10-09-15 | - | 75 | 9.5 | 10 | 10 | 3.55 | 3.55 | 13.05 | 55.5 | 26% |
17% August - 2017 |
Length 5.5 Km - sub base 1.5 Km, RW 2 Km, drain 1000 mtr completed. |
No Image |
1085 (OG) |
150976-Construction of road from Miskeen Abad Jalala to Jewar via Gulpur Killi Distt Mardan. |
Mardan HW |
- | - | - | 10-09-15 | - | 75 | 9.5 | 10 | 10 | 3.55 | 0 | 9.5 | 55.5 | 26% |
13% July - 2017 |
Length 5.5 Km - sub base 1.5 Km, RW 2 Km, drain 1000 mtr completed. |
No Image |
1085 (OG) |
150976-Construction of road from Miskeen Abad Jalala to Jewar via Gulpur Killi Distt Mardan. |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 75 | 9.5 | 10 | 47 | 47 | 47 | 56.5 | 55.5 | 26% |
75% June - 2018 |
Length 5.5 Km - sub base 1.5 Km, RW 2 Km, drain 1000 mtr completed. |
No Image |
PK-27, Mardan (5.5 Km) - Construction of road from Miskeen Abad Jalala to Jewar via Gulpur Killiwidth 18 ft | |||||||||||||||||||
1085 (OG) |
150976-Construction of road from Miskeen Abad Jalala to Jewar via Gulpur Killi Distt Mardan. |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 75 | 9.5 | 10 | 47 | 47 | 47 | 56.5 | 55.5 | 26% |
75% May - 2018 |
Length 5.5 Km - sub base 1.5 Km, RW 2 Km, drain 1000 mtr completed. |
No Image |
PK-27, Mardan (5.5 Km) - Construction of road from Miskeen Abad Jalala to Jewar via Gulpur Killiwidth 18 ft | |||||||||||||||||||
1085 (OG) |
150976-Construction of road from Miskeen Abad Jalala to Jewar via Gulpur Killi Distt Mardan. |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 75 | 9.5 | 10 | 47 | 47 | 29.402 | 38.902 | 55.5 | 26% |
52% April - 2018 |
Length 5.5 Km - sub base 1.5 Km, RW 2 Km, drain 1000 mtr completed. |
No Image |
PK-27, Mardan (5.5 Km) - Construction of road from Miskeen Abad Jalala to Jewar via Gulpur Killiwidth 18 ft | |||||||||||||||||||
1085 (OG) |
150976-Construction of road from Miskeen Abad Jalala to Jewar via Gulpur Killi Distt Mardan. |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 75 | 9.5 | 10 | 47 | 47 | 22.415 | 31.915 | 55.5 | 26% |
43% March - 2018 |
Length 5.5 Km - sub base 1.5 Km, RW 2 Km, drain 1000 mtr completed. |
No Image |
PK-27, Mardan (5.5 Km) - Construction of road from Miskeen Abad Jalala to Jewar via Gulpur Killiwidth 18 ft | |||||||||||||||||||
1085 (OG) |
150976-Construction of road from Miskeen Abad Jalala to Jewar via Gulpur Killi Distt Mardan. |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 75 | 9.5 | 10 | 17 | 17 | 17 | 26.5 | 55.5 | 26% |
35% February - 2018 |
Length 5.5 Km - sub base 1.5 Km, RW 2 Km, drain 1000 mtr completed. |
No Image |
PK-27, Mardan (5.5 Km)
1) Construction of road from Miskeen Abad Jalala to Jewar via Gulpur Killiwidth 18 ft | |||||||||||||||||||
1085 (OG) |
150976-Construction of road from Miskeen Abad Jalala to Jewar via Gulpur Killi Distt Mardan. |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 75 | 9.5 | 10 | 17 | 17 | 17 | 26.5 | 55.5 | 26% |
35% January - 2018 |
Length 5.5 Km - sub base 1.5 Km, RW 2 Km, drain 1000 mtr completed. |
No Image |
1085 (OG) |
170533-Provision of Swimming Pool at Hayatabad Sports Complex. |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 79.144 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- August - 2019 |
No Image | |
1085 (OG) |
170533-Provision of Swimming Pool at Hayatabad Sports Complex. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 88.227 | 0 | 10 | 10 | 0 | 0 | 0 | 78.227 | 11% |
- December - 2019 |
Revised approved. Tender called on 15/01/2020. |
No Image |
1085 (OG) |
170533-Provision of Swimming Pool at Hayatabad Sports Complex. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 88.227 | 0 | 10 | 10 | 0 | 0 | 0 | 78.227 | 11% |
- November - 2019 |
Revised approved. Tendering in progress. |
No Image |
1085 (OG) |
170533-Provision of Swimming Pool at Hayatabad Sports Complex. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 88.227 | 0 | 10 | 10 | 0 | 0 | 0 | 78.227 | 11% |
- October - 2019 |
Revised approved. Tendering in progress. |
No Image |
1085 (OG) |
170533-Provision of Swimming Pool at Hayatabad Sports Complex. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 88.227 | 0 | 10 | 10 | 0 | 0 | 0 | 78.227 | 11% |
- September - 2019 |
Revised approved. Tendering in progress. |
No Image |
1085 (OG) |
170533-Provision of Swimming Pool at Hayatabad Sports Complex. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 88.227 | 0 | 10 | 10 | 0 | 0 | 0 | 78.227 | 11% |
- May - 2020 |
Tender called on 15/01/2020. Technical Evaluation is in progress. |
No Image |
1085 (OG) |
170533-Provision of Swimming Pool at Hayatabad Sports Complex. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 88.227 | 0 | 10 | 10 | 0 | 0 | 0 | 78.227 | 11% |
- April - 2020 |
Tender called on 15/01/2020. Technical Evaluation is in progress. |
No Image |
1085 (OG) |
170533-Provision of Swimming Pool at Hayatabad Sports Complex. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 88.227 | 0 | 10 | 10 | 0 | 0 | 0 | 78.227 | 11% |
- March - 2020 |
Tender called on 15/01/2020. Technical Evaluation is in progress. |
No Image |
1085 (OG) |
170533-Provision of Swimming Pool at Hayatabad Sports Complex. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 88.227 | 0 | 10 | 10 | 0 | 0 | 0 | 78.227 | 11% |
- February - 2020 |
Tender called on 15/01/2020. Technical Evaluation is in progress. |
No Image |
1085 (OG) |
170533-Provision of Swimming Pool at Hayatabad Sports Complex. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 88.227 | 0 | 10 | 10 | 0 | 0 | 0 | 78.227 | 11% |
- January - 2020 |
Tender called on 15/01/2020. Technical Evaluation is in progress. |
No Image |
1085 (OG) |
110489-Procurerment of Equipments / Machinery, Furniture & Library Books for GPIs in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 363.78 | 65.15 | 0 | 0 | 0 | 0 | 65.15 | 0 | - |
- December - 2020 |
No Image | |
1085 (OG) |
110489-Procurerment of Equipments / Machinery, Furniture & Library Books for GPIs in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 363.78 | 65.15 | 0 | 0 | 0 | 0 | 65.15 | 0 | - |
- December - 2020 |
No Image | |
1085 (OG) |
110489-Procurerment of Equipments / Machinery, Furniture & Library Books for GPIs in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 363.78 | 65.15 | 0 | 0 | 0 | 0 | 65.15 | 0 | - |
- October - 2020 |
No Image | |
1085 (OG) |
110489-Procurerment of Equipments / Machinery, Furniture & Library Books for GPIs in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 363.78 | 65.15 | 0 | 0 | 0 | 0 | 65.15 | 0 | - |
- September - 2020 |
No Image | |
1085 (OG) |
110489-Procurerment of Equipments / Machinery, Furniture & Library Books for GPIs in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 363.78 | 65.15 | 0 | 0 | 0 | 0 | 65.15 | 0 | - |
- August - 2020 |
No Image | |
1085 (OG) |
110489-Procurerment of Equipments / Machinery, Furniture & Library Books for GPIs in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 363.78 | 65.15 | 0 | 0 | 0 | 0 | 65.15 | 0 | - |
July - 2020 |
No Image | |
1085 (OG) |
110489-Procurerment of Equipments / Machinery, Furniture & Library Books for GPIs in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 363.78 | 65.15 | 0 | 0 | 0 | 0 | 65.15 | 0 | - |
- May - 2021 |
No Image | |
1085 (OG) |
110489-Procurerment of Equipments / Machinery, Furniture & Library Books for GPIs in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 363.78 | 65.15 | 0 | 0 | 0 | 0 | 65.15 | 0 | - |
- April - 2021 |
No Image | |
1085 (OG) |
110489-Procurerment of Equipments / Machinery, Furniture & Library Books for GPIs in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 363.78 | 65.15 | 0 | 0 | 0 | 0 | 65.15 | 0 | - |
- March - 2021 |
No Image | |
1085 (OG) |
110489-Procurerment of Equipments / Machinery, Furniture & Library Books for GPIs in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 363.78 | 65.15 | 0 | 0 | 0 | 0 | 65.15 | 0 | - |
- February - 2021 |
No Image | |
1085 (OG) |
110489-Procurerment of Equipments / Machinery, Furniture & Library Books for GPIs in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 363.78 | 65.15 | 0 | 0 | 0 | 0 | 65.15 | 0 | - |
- January - 2021 |
No Image | |