Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1079 (OG) |
150828-Construction / Rehabilitation of road (a) Kandary to Chatlay, Kombat to Qasam Kalay (b) Haspital road Qumbat from Dheki to Chunkay Bara Qadar Naseer road, Mardan. |
Mardan HW |
11-07-16 | - | - | 10-09-15 | - | 100 | 9.5 | 30 | 20.65 | 13.15 | 12.537 | 22.037 | 60.5 | 40% |
22% December - 2017 |
Length 6.5 Km - RW, drain completed. |
No Image |
a) Gumbat Chungay to Dhaki Killi (5.500 Kms)
b) Bara Qadar Naseer Killi road (1 Km) | |||||||||||||||||||
1079 (OG) |
150828-Construction / Rehabilitation of road (a) Kandary to Chatlay, Kombat to Qasam Kalay (b) Haspital road Qumbat from Dheki to Chunkay Bara Qadar Naseer road, Mardan. |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 9.5 | 30 | 20.65 | 13.15 | 12.537 | 22.037 | 60.5 | 40% |
22% November - 2017 |
Length 6.5 Km - RW, drain completed. |
No Image |
a) Gumbat Chungay to Dhaki Killi (5.500 Kms)
b) Bara Qadar Naseer Killi road (1 Km) | |||||||||||||||||||
1079 (OG) |
150828-Construction / Rehabilitation of road (a) Kandary to Chatlay, Kombat to Qasam Kalay (b) Haspital road Qumbat from Dheki to Chunkay Bara Qadar Naseer road, Mardan. |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 9.5 | 30 | 30 | 22.5 | 10.65 | 20.15 | 60.5 | 40% |
20% October - 2017 |
Length 6.5 Km - RW, drain completed. |
No Image |
a) Gumbat Chungay to Dhaki Killi (5.500 Kms)
b) Bara Qadar Naseer Killi road (1 Km) | |||||||||||||||||||
1079 (OG) |
150828-Construction / Rehabilitation of road (a) Kandary to Chatlay, Kombat to Qasam Kalay (b) Haspital road Qumbat from Dheki to Chunkay Bara Qadar Naseer road, Mardan. |
Mardan HW |
11-07-16 | - | - | 10-09-15 | - | 100 | 9.5 | 30 | 30 | 10.65 | 10.65 | 20.15 | 60.5 | 40% |
20% September - 2017 |
Length 6.5 Km - RW, drain completed. |
No Image |
a) Gumbat Chungay to Dhaki Killi (5.500 Kms)
b) Bara Qadar Naseer Killi road (1 Km) | |||||||||||||||||||
1079 (OG) |
150828-Construction / Rehabilitation of road (a) Kandary to Chatlay, Kombat to Qasam Kalay (b) Haspital road Qumbat from Dheki to Chunkay Bara Qadar Naseer road, Mardan. |
Mardan HW |
11-07-16 | - | - | 10-09-15 | - | 100 | 9.5 | 30 | 30 | 10.65 | 10.65 | 20.15 | 60.5 | 40% |
20% August - 2017 |
Length 6.5 Km - RW, drain completed. |
No Image |
a) Gumbat Chungay to Dhaki Killi (5.500 Kms)
b) Bara Qadar Naseer Killi road (1 Km) | |||||||||||||||||||
1079 (OG) |
150828-Construction / Rehabilitation of road (a) Kandary to Chatlay, Kombat to Qasam Kalay (b) Haspital road Qumbat from Dheki to Chunkay Bara Qadar Naseer road, Mardan. |
Mardan HW |
11-07-16 | - | - | 10-09-15 | - | 100 | 9.5 | 30 | 30 | 10.65 | 0 | 9.5 | 60.5 | 40% |
10% July - 2017 |
Length 6.5 Km - RW, drain completed. |
No Image |
a) Gumbat Chungay to Dhaki Killi (5.500 Kms)
b) Bara Qadar Naseer Killi road (1 Km) | |||||||||||||||||||
1079 (OG) |
150828-Construction / Rehabilitation of road (a) Kandary to Chatlay, Kombat to Qasam Kalay (b) Haspital road Qumbat from Dheki to Chunkay Bara Qadar Naseer road, Mardan. |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 9.5 | 30 | 33.584 | 33.584 | 33.584 | 43.084 | 60.5 | 40% |
43% June - 2018 |
Length 6.5 Km - RW, drain completed. |
No Image |
1) Gumbat Chungay to Dhaki Killi (5.5 Km), PK-25 Mardan width 20 ft
2) Bara Qadar Naseer Killi road (1 Km), PK-25 Mardan width 20 ft | |||||||||||||||||||
1079 (OG) |
150828-Construction / Rehabilitation of road (a) Kandary to Chatlay, Kombat to Qasam Kalay (b) Haspital road Qumbat from Dheki to Chunkay Bara Qadar Naseer road, Mardan. |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 9.5 | 30 | 33.584 | 33.584 | 33.584 | 43.084 | 60.5 | 40% |
43% May - 2018 |
Length 6.5 Km - RW, drain completed. |
No Image |
1) Gumbat Chungay to Dhaki Killi (5.5 Km), PK-25 Mardan width 20 ft
2) Bara Qadar Naseer Killi road (1 Km), PK-25 Mardan width 20 ft | |||||||||||||||||||
1079 (OG) |
150828-Construction / Rehabilitation of road (a) Kandary to Chatlay, Kombat to Qasam Kalay (b) Haspital road Qumbat from Dheki to Chunkay Bara Qadar Naseer road, Mardan. |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 9.5 | 30 | 33.584 | 33.584 | 33.584 | 43.084 | 60.5 | 40% |
43% April - 2018 |
Length 6.5 Km - RW, drain completed. |
No Image |
1) Gumbat Chungay to Dhaki Killi (5.5 Km), PK-25 Mardan width 20 ft
2) Bara Qadar Naseer Killi road (1 Km), PK-25 Mardan width 20 ft | |||||||||||||||||||
1079 (OG) |
150828-Construction / Rehabilitation of road (a) Kandary to Chatlay, Kombat to Qasam Kalay (b) Haspital road Qumbat from Dheki to Chunkay Bara Qadar Naseer road, Mardan. |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 9.5 | 30 | 33.584 | 33.584 | 25.809 | 35.309 | 60.5 | 40% |
35% March - 2018 |
Length 6.5 Km - RW, drain completed. |
No Image |
1) Gumbat Chungay to Dhaki Killi (5.5 Km), PK-25 Mardan width 20 ft
2) Bara Qadar Naseer Killi road (1 Km), PK-25 Mardan width 20 ft | |||||||||||||||||||
1079 (OG) |
150828-Construction / Rehabilitation of road (a) Kandary to Chatlay, Kombat to Qasam Kalay (b) Haspital road Qumbat from Dheki to Chunkay Bara Qadar Naseer road, Mardan. |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 9.5 | 30 | 30.894 | 30.894 | 24.275 | 33.775 | 60.5 | 40% |
34% February - 2018 |
Length 6.5 Km - RW, drain completed. |
ADP's Images |
1) Gumbat Chungay to Dhaki Killi (5.5 Km), PK-25 Mardan width 20 ft
2) Bara Qadar Naseer Killi road (1 Km), PK-25 Mardan width 20 ft | |||||||||||||||||||
1079 (OG) |
150828-Construction / Rehabilitation of road (a) Kandary to Chatlay, Kombat to Qasam Kalay (b) Haspital road Qumbat from Dheki to Chunkay Bara Qadar Naseer road, Mardan. |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 9.5 | 30 | 30.894 | 30.894 | 15.919 | 25.419 | 60.5 | 40% |
25% January - 2018 |
Length 6.5 Km - RW, drain completed. |
No Image |
a) Gumbat Chungay to Dhaki Killi (5.500 Kms) b) Bara Qadar Naseer Killi road (1 Km) | |||||||||||||||||||
1079 (OG) |
140279-Rehabilitation of Existing SIDB Small Industrial Estates (D.I.Khan, Bannu, Kohat and Mansehra). |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 322.671 | 271.671 | 0 | 0 | 0 | 0 | 271.671 | 0 | - |
- December - 2020 |
No Image | |
1079 (OG) |
140279-Rehabilitation of Existing SIDB Small Industrial Estates (D.I.Khan, Bannu, Kohat and Mansehra). |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 322.671 | 271.671 | 0 | 0 | 0 | 0 | 271.671 | 0 | - |
- December - 2020 |
No Image | |
1079 (OG) |
140279-Rehabilitation of Existing SIDB Small Industrial Estates (D.I.Khan, Bannu, Kohat and Mansehra). |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 322.671 | 271.671 | 0 | 0 | 0 | 0 | 271.671 | 0 | - |
- October - 2020 |
No Image | |
1079 (OG) |
140279-Rehabilitation of Existing SIDB Small Industrial Estates (D.I.Khan, Bannu, Kohat and Mansehra). |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 322.671 | 271.671 | 0 | 0 | 0 | 0 | 271.671 | 0 | - |
- September - 2020 |
No Image | |
1079 (OG) |
140279-Rehabilitation of Existing SIDB Small Industrial Estates (D.I.Khan, Bannu, Kohat and Mansehra). |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 322.671 | 271.671 | 0 | 0 | 0 | 0 | 271.671 | 0 | - |
- August - 2020 |
No Image | |
1079 (OG) |
140279-Rehabilitation of Existing SIDB Small Industrial Estates (D.I.Khan, Bannu, Kohat and Mansehra). |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 322.671 | 271.671 | 0 | 0 | 0 | 0 | 271.671 | 0 | - |
- July - 2020 |
No Image | |
1079 (OG) |
140279-Rehabilitation of Existing SIDB Small Industrial Estates (D.I.Khan, Bannu, Kohat and Mansehra). |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 322.671 | 271.671 | 0 | 0 | 0 | 0 | 271.671 | 0 | - |
- May - 2021 |
No Image | |
1079 (OG) |
140279-Rehabilitation of Existing SIDB Small Industrial Estates (D.I.Khan, Bannu, Kohat and Mansehra). |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 322.671 | 271.671 | 0 | 0 | 0 | 0 | 271.671 | 0 | - |
- April - 2021 |
No Image | |
1079 (OG) |
140279-Rehabilitation of Existing SIDB Small Industrial Estates (D.I.Khan, Bannu, Kohat and Mansehra). |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 322.671 | 271.671 | 0 | 0 | 0 | 0 | 271.671 | 0 | - |
- March - 2021 |
No Image | |
1079 (OG) |
140279-Rehabilitation of Existing SIDB Small Industrial Estates (D.I.Khan, Bannu, Kohat and Mansehra). |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 322.671 | 271.671 | 0 | 0 | 0 | 0 | 271.671 | 0 | - |
- February - 2021 |
No Image | |
1079 (OG) |
140279-Rehabilitation of Existing SIDB Small Industrial Estates (D.I.Khan, Bannu, Kohat and Mansehra). |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 322.671 | 271.671 | 0 | 0 | 0 | 0 | 271.671 | 0 | - |
- January - 2021 |
No Image | |
Pages : 1 |