Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1078 (OG) |
150826-Construction / rehabilitation of internal roads of UC Toru Maira and UC Maho Dheri road, District Mardan. |
Mardan HW |
01-04-16 | - | - | 02-11-15 | - | 129.829 | 41.272 | 60 | 49.225 | 32.775 | 31.299 | 72.571 | 28.557 | 78% |
56% December - 2017 |
Length 7.3 Km - 4.75 Km BT completed. |
No Image |
1078 (OG) |
150826-Construction / rehabilitation of internal roads of UC Toru Maira and UC Maho Dheri road, District Mardan. |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 129.829 | 41.272 | 60 | 51.225 | 36.225 | 30.458 | 71.73 | 28.557 | 78% |
55% November - 2017 |
Length 7.3 Km - 4.75 Km BT completed. |
No Image |
1078 (OG) |
150826-Construction / rehabilitation of internal roads of UC Toru Maira and UC Maho Dheri road, District Mardan. |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 129.829 | 41.272 | 60 | 60 | 37.789 | 21.683 | 62.955 | 28.557 | 78% |
48% October - 2017 |
Length 7.3 Km - 4.75 Km BT completed. |
No Image |
1078 (OG) |
150826-Construction / rehabilitation of internal roads of UC Toru Maira and UC Maho Dheri road, District Mardan. |
Mardan HW |
01-04-16 | - | - | 02-11-15 | - | 129.829 | 41.272 | 60 | 60 | 21.3 | 21.3 | 62.572 | 28.557 | 78% |
48% September - 2017 |
Length 7.3 Km - 4.75 Km BT completed. |
No Image |
1078 (OG) |
150826-Construction / rehabilitation of internal roads of UC Toru Maira and UC Maho Dheri road, District Mardan. |
Mardan HW |
01-04-16 | - | - | 02-11-15 | - | 129.829 | 41.272 | 60 | 60 | 21.3 | 21.261 | 62.533 | 28.557 | 78% |
48% August - 2017 |
Length 7.3 Km - 1 Km BT completed. |
No Image |
1078 (OG) |
150826-Construction / rehabilitation of internal roads of UC Toru Maira and UC Maho Dheri road, District Mardan. |
Mardan HW |
01-04-16 | - | - | 02-11-15 | - | 129.829 | 41.272 | 60 | 60 | 21.3 | 0 | 41.272 | 28.557 | 78% |
32% July - 2017 |
Length 7.3 Km - 1 Km BT completed. |
No Image |
1078 (OG) |
150826-Construction / rehabilitation of internal roads of UC Toru Maira and UC Maho Dheri road, District Mardan. |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 129.829 | 41.272 | 60 | 42.033 | 52.033 | 42.033 | 83.305 | 28.557 | 78% |
64% June - 2018 |
Length 7.3 Km - 4.75 Km BT completed. |
No Image |
1) Toru Degree College upto Marhatti Canal 3 Km (construciton/rehabilitation) width 20ft
2) Canal to Qamar Gay via Chota Kala Khel 1.2 Km (construciton/rehabilitation) width 12 ft
3) Jewar road upto Canal 0.525 Km (construciton/rehabilitation) width 12 ft
4) Dosehra road to Akram Abad Shah Killi 0.33 Km (construciton/rehabilitation) width 16 ft
5) Shamilat to Kochyano Killi 0.75 Km (construciton/rehabilitation) Width 12 ft
6) Maza Killi road 0.35 Km UC Maho Dheri (construciton/rehabilitation) width 12 ft
7) Bakri Banda road 0.3 Km (construciton/rehabilitation) width 12 ft
8) Maho Dheri to Hakim Abad along with drain 0.55 Km and Maho Dheri to Ajmal Killi 0.35 Km width 12 ft (construciton/rehabilitation)
9) Khwaja to Shaukat Abad 0.75 Km (construciton/rehabilitation) width 12 ft | |||||||||||||||||||
1078 (OG) |
150826-Construction / rehabilitation of internal roads of UC Toru Maira and UC Maho Dheri road, District Mardan. |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 129.829 | 41.272 | 60 | 62.159 | 62.159 | 42.033 | 83.305 | 28.557 | 78% |
64% May - 2018 |
Length 7.3 Km - 4.75 Km BT completed. |
No Image |
1) Toru Degree College upto Marhatti Canal 3 Km (construciton/rehabilitation) width 20ft
2) Canal to Qamar Gay via Chota Kala Khel 1.2 Km (construciton/rehabilitation) width 12 ft
3) Jewar road upto Canal 0.525 Km (construciton/rehabilitation) width 12 ft
4) Dosehra road to Akram Abad Shah Killi 0.33 Km (construciton/rehabilitation) width 16 ft
5) Shamilat to Kochyano Killi 0.75 Km (construciton/rehabilitation) Width 12 ft
6) Maza Killi road 0.35 Km UC Maho Dheri (construciton/rehabilitation) width 12 ft
7) Bakri Banda road 0.3 Km (construciton/rehabilitation) width 12 ft
8) Maho Dheri to Hakim Abad along with drain 0.55 Km and Maho Dheri to Ajmal Killi 0.35 Km width 12 ft (construciton/rehabilitation)
9) Khwaja to Shaukat Abad 0.75 Km (construciton/rehabilitation) width 12 ft | |||||||||||||||||||
1078 (OG) |
150826-Construction / rehabilitation of internal roads of UC Toru Maira and UC Maho Dheri road, District Mardan. |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 129.829 | 41.272 | 60 | 62.159 | 62.159 | 36.411 | 77.683 | 28.557 | 78% |
60% April - 2018 |
Length 7.3 Km - 4.75 Km BT completed. |
No Image |
1) Toru Degree College upto Marhatti Canal 3 Km (construciton/rehabilitation) width 20ft
2) Canal to Qamar Gay via Chota Kala Khel 1.2 Km (construciton/rehabilitation) width 12 ft
3) Jewar road upto Canal 0.525 Km (construciton/rehabilitation) width 12 ft
4) Dosehra road to Akram Abad Shah Killi 0.33 Km (construciton/rehabilitation) width 16 ft
5) Shamilat to Kochyano Killi 0.75 Km (construciton/rehabilitation) Width 12 ft
6) Maza Killi road 0.35 Km UC Maho Dheri (construciton/rehabilitation) width 12 ft
7) Bakri Banda road 0.3 Km (construciton/rehabilitation) width 12 ft
8) Maho Dheri to Hakim Abad along with drain 0.55 Km and Maho Dheri to Ajmal Killi 0.35 Km width 12 ft (construciton/rehabilitation)
9) Khwaja to Shaukat Abad 0.75 Km (construciton/rehabilitation) width 12 ft | |||||||||||||||||||
1078 (OG) |
150826-Construction / rehabilitation of internal roads of UC Toru Maira and UC Maho Dheri road, District Mardan. |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 129.829 | 41.272 | 60 | 62.159 | 62.159 | 36.411 | 77.683 | 28.557 | 78% |
60% March - 2018 |
Length 7.3 Km - 4.75 Km BT completed. |
No Image |
1) Toru Degree College upto Marhatti Canal 3 Km (construciton/rehabilitation) width 20ft
2) Canal to Qamar Gay via Chota Kala Khel 1.2 Km (construciton/rehabilitation) width 12 ft
3) Jewar road upto Canal 0.525 Km (construciton/rehabilitation) width 12 ft
4) Dosehra road to Akram Abad Shah Killi 0.33 Km (construciton/rehabilitation) width 16 ft
5) Shamilat to Kochyano Killi 0.75 Km (construciton/rehabilitation) Width 12 ft
6) Maza Killi road 0.35 Km UC Maho Dheri (construciton/rehabilitation) width 12 ft
7) Bakri Banda road 0.3 Km (construciton/rehabilitation) width 12 ft
8) Maho Dheri to Hakim Abad along with drain 0.55 Km and Maho Dheri to Ajmal Killi 0.35 Km width 12 ft (construciton/rehabilitation)
9) Khwaja to Shaukat Abad 0.75 Km (construciton/rehabilitation) width 12 ft | |||||||||||||||||||
1078 (OG) |
150826-Construction / rehabilitation of internal roads of UC Toru Maira and UC Maho Dheri road, District Mardan. |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 129.829 | 41.272 | 60 | 59.469 | 58.019 | 31.299 | 72.571 | 28.557 | 78% |
56% February - 2018 |
Length 7.3 Km - 4.75 Km BT completed. |
No Image |
1) Toru Degree College upto Marhatti Canal 3 Km (construciton/rehabilitation) width 20ft
2) Canal to Qamar Gay via Chota Kala Khel 1.2 Km (construciton/rehabilitation) width 12 ft
3) Jewar road upto Canal 0.525 Km (construciton/rehabilitation) width 12 ft
4) Dosehra road to Akram Abad Shah Killi 0.33 Km (construciton/rehabilitation) width 16 ft
5) Shamilat to Kochyano Killi 0.75 Km (construciton/rehabilitation) Width 12 ft
6) Maza Killi road 0.35 Km UC Maho Dheri (construciton/rehabilitation) width 12 ft
7) Bakri Banda road 0.3 Km (construciton/rehabilitation) width 12 ft
8) Maho Dheri to Hakim Abad along with drain 0.55 Km and Maho Dheri to Ajmal Killi 0.35 Km width 12 ft (construciton/rehabilitation)
9) Khwaja to Shaukat Abad 0.75 Km (construciton/rehabilitation) width 12 ft | |||||||||||||||||||
1078 (OG) |
150826-Construction / rehabilitation of internal roads of UC Toru Maira and UC Maho Dheri road, District Mardan. |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 129.829 | 41.272 | 60 | 58.019 | 58.019 | 31.299 | 72.571 | 28.557 | 78% |
56% January - 2018 |
Length 7.3 Km - 4.75 Km BT completed. |
No Image |
1078 (New) |
180315-Construction of District Social Welfare Office Peshawar. |
Peshawar BD-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.498 | 0 | 5 | 5 | 0 | 0 | 0 | 22.498 | 18% |
- December - 2018 |
Approved. |
No Image |
1078 (New) |
180315-Construction of District Social Welfare Office Peshawar. |
Peshawar BD-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 25 | 0 | 5 | 5 | 0 | 0 | 0 | 0 | - |
- November - 2018 |
PC-I/DCE usubmitted for Rs. 27.5 M |
No Image |
1078 (New) |
180315-Construction of District Social Welfare Office Peshawar. |
Peshawar BD-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 25 | 0 | 5 | 5 | 0 | 0 | 0 | 0 | - |
- November - 2018 |
PC-I/DCE usubmitted for Rs. 27.5 M |
No Image |
1078 (New) |
180315-Construction of District Social Welfare Office Peshawar. |
Peshawar BD-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.498 | 0 | 5 | 5 | 1.25 | 1.25 | 1.25 | 22.498 | 18% |
5% April - 2019 |
Work in progress. |
No Image |
1078 (New) |
180315-Construction of District Social Welfare Office Peshawar. |
Peshawar BD-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.498 | 0 | 5 | 5 | 1.25 | 0 | 0 | 22.498 | 18% |
- March - 2019 |
Work order issued. |
No Image |
1078 (New) |
180315-Construction of District Social Welfare Office Peshawar. |
Peshawar BD-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.498 | 0 | 5 | 5 | 1.25 | 0 | 0 | 22.498 | 18% |
- March - 2019 |
Work order issued. |
No Image |
1078 (New) |
180315-Construction of District Social Welfare Office Peshawar. |
Peshawar BD-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.498 | 0 | 5 | 5 | 0 | 0 | 0 | 22.498 | 18% |
- February - 2019 |
Tender called. Technical bid will be opened on 14/02/2019. |
No Image |
1078 (New) |
180315-Construction of District Social Welfare Office Peshawar. |
Peshawar BD-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.498 | 0 | 5 | 5 | 0 | 0 | 0 | 22.498 | 18% |
- January - 2019 |
Tender called. Technical bid will be opened on 14/2/2019. |
No Image |
1078 (OG) |
120677-Provision of Gas & Independent Electric Feeders in Existing SIDB SIEs in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 130 | 77 | 0 | 0 | 0 | 0 | 77 | 0 | - |
- December - 2020 |
No Image | |
1078 (OG) |
120677-Provision of Gas & Independent Electric Feeders in Existing SIDB SIEs in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 130 | 77 | 0 | 0 | 0 | 0 | 77 | 0 | - |
- December - 2020 |
No Image | |
1078 (OG) |
120677-Provision of Gas & Independent Electric Feeders in Existing SIDB SIEs in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 130 | 77 | 0 | 0 | 0 | 0 | 77 | 0 | - |
- October - 2020 |
No Image | |
1078 (OG) |
120677-Provision of Gas & Independent Electric Feeders in Existing SIDB SIEs in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 130 | 77 | 0 | 0 | 0 | 0 | 77 | 0 | - |
- September - 2020 |
No Image | |
1078 (OG) |
120677-Provision of Gas & Independent Electric Feeders in Existing SIDB SIEs in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 130 | 77 | 0 | 0 | 0 | 0 | 77 | 0 | - |
- August - 2020 |
No Image | |
1078 (OG) |
120677-Provision of Gas & Independent Electric Feeders in Existing SIDB SIEs in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 130 | 77 | 0 | 0 | 0 | 0 | 77 | 0 | - |
July - 2020 |
No Image | |
1078 (OG) |
120677-Provision of Gas & Independent Electric Feeders in Existing SIDB SIEs in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 130 | 77 | 0 | 0 | 0 | 0 | 77 | 0 | - |
- May - 2021 |
No Image | |
1078 (OG) |
120677-Provision of Gas & Independent Electric Feeders in Existing SIDB SIEs in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 130 | 77 | 0 | 0 | 0 | 0 | 77 | 0 | - |
- April - 2021 |
No Image | |
1078 (OG) |
120677-Provision of Gas & Independent Electric Feeders in Existing SIDB SIEs in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 130 | 77 | 0 | 0 | 0 | 0 | 77 | 0 | - |
- March - 2021 |
No Image | |
1078 (OG) |
120677-Provision of Gas & Independent Electric Feeders in Existing SIDB SIEs in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 130 | 77 | 0 | 0 | 0 | 0 | 77 | 0 | - |
- February - 2021 |
No Image | |
1078 (OG) |
120677-Provision of Gas & Independent Electric Feeders in Existing SIDB SIEs in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 130 | 77 | 0 | 0 | 0 | 0 | 77 | 0 | - |
- January - 2021 |
No Image | |
Pages : 1 |