Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2021, January - 2018, January - 2019, February - 2021, February - 2018, February - 2019, March - 2021, March - 2018, March - 2019, April - 2021, April - 2018, April - 2019, May - 2021, May - 2018, June - 2018, July - 2017, July - 2020, August - 2017, August - 2020, September - 2017, September - 2020, October - 2017, October - 2020, November - 2017, November - 2018, December - 2020, December - 2017, December - 2018,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1071
(New)
190191-Land Acquisition for Marble City, Buner (100 Acres)
Buner
30-11--1 30-11--1 - 30-11--1 Line Deptt 500 0 0 0 0 0 0 0 - -
December - 2020
No Image
1071
(New)
190191-Land Acquisition for Marble City, Buner (100 Acres)
Buner
30-11--1 30-11--1 - 30-11--1 Line Deptt 500 0 0 0 0 0 0 0 - -
December - 2020
No Image
1071
(New)
190191-Land Acquisition for Marble City, Buner (100 Acres)
Buner
30-11--1 30-11--1 - 30-11--1 Line Deptt 500 0 0 0 0 0 0 0 - -
October - 2020
No Image
1071
(New)
190191-Land Acquisition for Marble City, Buner (100 Acres)
Buner
30-11--1 30-11--1 - 30-11--1 Line Deptt 500 0 0 0 0 0 0 0 - -
September - 2020
No Image
1071
(New)
190191-Land Acquisition for Marble City, Buner (100 Acres)
Buner
30-11--1 30-11--1 - 30-11--1 Line Deptt 500 0 0 0 0 0 0 0 - -
August - 2020
No Image
1071
(New)
190191-Land Acquisition for Marble City, Buner (100 Acres)
Buner
30-11--1 30-11--1 - 30-11--1 Line Deptt 500 0 0 0 0 0 0 0 - -
July - 2020
No Image
1071
(New)
190191-Land Acquisition for Marble City, Buner (100 Acres)
Buner
30-11--1 30-11--1 - 30-11--1 Line Deptt 500 0 0 0 0 0 0 0 - -
May - 2021
No Image
1071
(New)
190191-Land Acquisition for Marble City, Buner (100 Acres)
Buner
30-11--1 30-11--1 - 30-11--1 Line Deptt 500 0 0 0 0 0 0 0 - -
April - 2021
No Image
1071
(New)
190191-Land Acquisition for Marble City, Buner (100 Acres)
Buner
30-11--1 30-11--1 - 30-11--1 Line Deptt 500 0 0 0 0 0 0 0 - -
March - 2021
No Image
1071
(New)
190191-Land Acquisition for Marble City, Buner (100 Acres)
Buner
30-11--1 30-11--1 - 30-11--1 Line Deptt 500 0 0 0 0 0 0 0 - -
February - 2021
No Image
1071
(New)
190191-Land Acquisition for Marble City, Buner (100 Acres)
Buner
30-11--1 30-11--1 - 30-11--1 Line Deptt 500 0 0 0 0 0 0 0 - -
January - 2021
No Image
1071
(OG)
170234-Construction / Up-gradation of School for Deaf & Dumb Children at Timergara Dir Lower.
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 55.9 0 11 11 11 5.5 5.5 44.9 20% 10%
December - 2018
Academic block - raft in progress.
No Image
Timergara, Dir Lower
1071
(OG)
170234-Construction / Up-gradation of School for Deaf & Dumb Children at Timergara Dir Lower.
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 55.9 0 11 11 5.5 5.5 5.5 44.9 20% 10%
November - 2018
Academic block - raft in progress.
No Image
Timergara, Dir Lower
1071
(OG)
170234-Construction / Up-gradation of School for Deaf & Dumb Children at Timergara Dir Lower.
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 55.9 0 11 11 5.5 5.5 5.5 44.9 20% 10%
November - 2018
Academic block - raft in progress.
No Image
Timergara, Dir Lower
1071
(OG)
170234-Construction / Up-gradation of School for Deaf & Dumb Children at Timergara Dir Lower.
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 55.9 0 11 11 11 11 11 44.9 20% 20%
April - 2019
Academic block - raft in progress. Rs.25 m demanded.
No Image
Timergara, Dir Lower
1071
(OG)
170234-Construction / Up-gradation of School for Deaf & Dumb Children at Timergara Dir Lower.
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 55.9 0 11 11 11 11 11 44.9 20% 20%
March - 2019
Academic block - raft in progress. Rs.25 m demanded.
No Image
Timergara, Dir Lower
1071
(OG)
170234-Construction / Up-gradation of School for Deaf & Dumb Children at Timergara Dir Lower.
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 55.9 0 11 11 11 11 11 44.9 20% 20%
March - 2019
Academic block - raft in progress. Rs.25 m demanded.
No Image
Timergara, Dir Lower
1071
(OG)
170234-Construction / Up-gradation of School for Deaf & Dumb Children at Timergara Dir Lower.
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 55.9 0 11 11 11 11 11 44.9 20% 20%
February - 2019
Academic block - raft in progress. Rs.25 m demanded.
No Image
Timergara, Dir Lower
1071
(OG)
170234-Construction / Up-gradation of School for Deaf & Dumb Children at Timergara Dir Lower.
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 55.9 0 11 11 11 11 11 44.9 20% 20%
January - 2019
Academic block - raft in progress.
No Image
Timergara, Dir Lower
1071
(OG)
140669-F/S, Design and Construction of Bridge and Approach Roads on Khan Gari Kalpani Nullah to Arbi Banda U/C Jehangir Abad and Sari Bahlol (5 Km including Bridge), District Mardan.
Mardan
HW
21-10-15 30-06-18 - 22-01-15 - 85.614 55.654 27.36 27.36 13.68 13.68 69.334 2.6 97% 81%
December - 2017
5 Km/Bridge - Bridge completed. 5 Km approcahes in progress.
No Image
5 Kms including bridge PK-26
1071
(OG)
140669-F/S, Design and Construction of Bridge and Approach Roads on Khan Gari Kalpani Nullah to Arbi Banda U/C Jehangir Abad and Sari Bahlol (5 Km including Bridge), District Mardan.
Mardan
HW
30-11--1 30-11--1 - 30-11--1 - 85.614 55.654 27.36 27.36 13.68 12.732 68.386 2.6 97% 80%
November - 2017
5 Km/Bridge - Bridge completed. 5 Km approcahes in progress.
No Image
5 Kms including bridge PK-26
1071
(OG)
140669-F/S, Design and Construction of Bridge and Approach Roads on Khan Gari Kalpani Nullah to Arbi Banda U/C Jehangir Abad and Sari Bahlol (5 Km including Bridge), District Mardan.
Mardan
HW
30-11--1 30-11--1 - 30-11--1 - 85.614 55.654 27.36 27.36 13.68 5.173 60.827 2.6 97% 71%
October - 2017
5 Km/Bridge - Bridge completed. 5 Km approcahes in progress.
No Image
5 Kms including bridge PK-26
1071
(OG)
140669-F/S, Design and Construction of Bridge and Approach Roads on Khan Gari Kalpani Nullah to Arbi Banda U/C Jehangir Abad and Sari Bahlol (5 Km including Bridge), District Mardan.
Mardan
HW
21-10-15 30-06-18 - 22-01-15 - 85.614 55.654 27.36 27.36 13.68 6.5 62.154 2.6 97% 73%
September - 2017
5 Km/Bridge - deck slab 3/4, work on road work started.
No Image
5 Kms including bridge PK-26
1071
(OG)
140669-F/S, Design and Construction of Bridge and Approach Roads on Khan Gari Kalpani Nullah to Arbi Banda U/C Jehangir Abad and Sari Bahlol (5 Km including Bridge), District Mardan.
Mardan
HW
21-10-15 30-06-18 - 22-01-15 - 85.614 55.654 27.36 27.36 13.68 0 55.654 2.6 97% 65%
August - 2017
5 Km/Bridge - deck slab 2/4, work on road work started.
No Image
5 Kms including bridge PK-26
1071
(OG)
140669-F/S, Design and Construction of Bridge and Approach Roads on Khan Gari Kalpani Nullah to Arbi Banda U/C Jehangir Abad and Sari Bahlol (5 Km including Bridge), District Mardan.
Mardan
HW
21-10-15 30-06-18 - 22-01-15 - 85.614 55.654 27.36 27.36 9.713 0 55.654 2.6 97% 65%
July - 2017
5 Km/Bridge - deck slab 2/4, work on road work started.
No Image
5 Kms including bridge PK-26
1071
(OG)
140669-F/S, Design and Construction of Bridge and Approach Roads on Khan Gari Kalpani Nullah to Arbi Banda U/C Jehangir Abad and Sari Bahlol (5 Km including Bridge), District Mardan.
Mardan
HW
30-11--1 30-11--1 - 30-11--1 - 85.614 55.652 27.36 29.921 29.921 29.921 85.573 2.602 97% 100%
June - 2018
5 Km/Bridge - Bridge completed. 5 Km approcahes in progress.
No Image
1) Bridge i/c Bridge approaches (4 span n length 24 m each)
2) 5 Km road on both sides
1071
(OG)
140669-F/S, Design and Construction of Bridge and Approach Roads on Khan Gari Kalpani Nullah to Arbi Banda U/C Jehangir Abad and Sari Bahlol (5 Km including Bridge), District Mardan.
Mardan
HW
30-11--1 30-11--1 - 30-11--1 - 85.614 55.652 27.36 29.921 29.921 29.921 85.573 2.602 97% 100%
May - 2018
5 Km/Bridge - Bridge completed. 5 Km approcahes in progress. Amount to the tune of Rs. 13.114 m required for financial closing.
No Image
1) Bridge i/c Bridge approaches (4 span n length 24 m each)
2) 5 Km road on both sides
1071
(OG)
140669-F/S, Design and Construction of Bridge and Approach Roads on Khan Gari Kalpani Nullah to Arbi Banda U/C Jehangir Abad and Sari Bahlol (5 Km including Bridge), District Mardan.
Mardan
HW
30-11--1 30-11--1 - 30-11--1 - 85.614 55.652 27.36 29.921 29.921 29.921 85.573 2.602 97% 100%
April - 2018
5 Km/Bridge - Bridge completed. 5 Km approcahes in progress.
No Image
1) Bridge i/c Bridge approaches (4 span n length 24 m each)
2) 5 Km road on both sides
1071
(OG)
140669-F/S, Design and Construction of Bridge and Approach Roads on Khan Gari Kalpani Nullah to Arbi Banda U/C Jehangir Abad and Sari Bahlol (5 Km including Bridge), District Mardan.
Mardan
HW
30-11--1 30-11--1 - 30-11--1 - 85.614 55.652 27.36 29.921 29.921 19.824 75.476 2.602 97% 88%
March - 2018
5 Km/Bridge - Bridge completed. 5 Km approcahes in progress.
No Image
1) Bridge i/c Bridge approaches (4 span n length 24 m each)
2) 5 Km road on both sides
1071
(OG)
140669-F/S, Design and Construction of Bridge and Approach Roads on Khan Gari Kalpani Nullah to Arbi Banda U/C Jehangir Abad and Sari Bahlol (5 Km including Bridge), District Mardan.
Mardan
HW
30-11--1 30-11--1 - 30-11--1 - 85.614 55.652 27.36 29.241 29.241 15.569 71.221 2.602 97% 83%
February - 2018
5 Km/Bridge - Bridge completed. 5 Km approcahes in progress.
No Image
1) Bridge I/c bride approaches ( Span 4 span length 24 m each )
2) 5 KM road on both sides
1071
(OG)
140669-F/S, Design and Construction of Bridge and Approach Roads on Khan Gari Kalpani Nullah to Arbi Banda U/C Jehangir Abad and Sari Bahlol (5 Km including Bridge), District Mardan.
Mardan
HW
30-11--1 30-11--1 - 30-11--1 - 85.614 55.654 27.36 29.241 29.241 13.68 69.334 2.6 97% 81%
January - 2018
5 Km/Bridge - Bridge completed. 5 Km approcahes in progress.
No Image
5 Km including bridge PK-26
Pages : 1